N-12.3

BNetzA auction result June 2024. Grid connection target end of 2030.

Status
Early Developmentlifecycle stage
PossibleHafrok delivery likelihood
Ownership
EnBW — split undisclosed ◆
Location
Germany
North Sea
Technology
Capacity 1,000 MW ◆
Turbines —
Foundation Monopile ◆
Site & conditions
Site rights Seabed rights held ∴
Origination BNetzA Offshore Wind Auction 2024 (dynamic bidding / concession) · 2024 ·
Water depth 38–43 m ≈ Wind speed 10.4 m/s @ 150 m ≈
Revenue & grid
Offtake Merchant ◆ Grid Offered · Jun 2024 ◆ Connection Statutory TSO grid connection right under WindSeeG §12 granted … ◆
Schedule
FID expected 2029 ◆ COD · announced 2032 ◆
COD · Hafrok for registered readers

Delivery outlook modelled by Hafrok · calibrated on delivered projects

PossibleHafrok's delivery likelihood for N-12.3
The developer says 2032. Hafrok's year sits later than that; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

the dated milestones on the spine, each with its source · 1 recorded ownership deal from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 12 sources (4 primary) · ◆ 7 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[2]
Bundesnetzagentur (Federal Network Agency)2024-06-21◆ Bundesnetzagentur - Press - Results of d…
“The two offshore sites, which have a capacity of 1,500 MW and 1,000 MW respectively, are located about 120 km north-west of Helgoland in the North Sea. [...] The successful bidders were Offshore Wind …”
supportsoperatorConsentTotal capacityMechanismDetail+3 more
Operator5
[3]
EnBW Energie Baden-Württemberg AG2024-06-21◆ EnBW awarded contract for offshore wind …
“EnBW has been awarded a contract by the Federal Network Agency at an auction to develop a one gigawatt (GW) offshore wind farm in the North Sea. [...] EnBW plans to sell much of the electricity produc…”
supportsTotal capacityMechanismDetail
[8]
EnBW2026-03-18◆ EnBW completes ground investigations for…
“The Dreekant offshore wind farm is set to go online 120 km northwest of Heligoland in 2032. ... "The data obtained is essential for planning the foundations. We are pleased that it is possible to use …”
supportsCommercial operationCOD historyFoundation
[9]
EnBW2026-06◆ EnBW — enbw factbook 2026
“Offshore wind projects under development Location Germany, 140 km off the island of Sylt (North Sea) Capacity 1 GW [...] Foundation Bottom fixed monopiles Commissioning Late 2032/early 2033 (planned) …”
supportsFinal investment decisionCommercial operationFoundation
[10]
EnBW2026◆ EnBW wind farm Dreekant | EnBW
“It plans to submit the approval application in 2027, with the final investment decision due to be made in 2029. The wind farm is set to go online 120 km northwest of Helgoland in 2032”
supportsCommercial operation
[11]
EnBW Energie Baden-Württemberg AG2024-06◆ EnBW awarded contract for offshore wind …
"EnBW won the contract for a one gigawatt (GW) offshore wind farm in the North Sea." (EnBW erhaelt Zuschlag fuer 1-GW-Offshore- Windpark; the BNetzA result names the winning bidder as EnBW Offshore Pr…
supports↳ parents
Auction pipeline1
[12]
Bundesnetzagentur2026◆ bnetza-noncentral-2027
BNetzA — 2026 non-central offshore tenders suspended; N-10.1/N-10.2/N-12.4/N-12.5/N-13.1/N-13.2 moved to tender year 2027.
supportsGermany offshore tender — 2027 (FEP cluster)
Trade press4
[4]
offshoreWIND.biz2024
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[5]
4C Offshore2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[6]
GEBCO Compilation Group2020
supportsWater depth
[7]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
Press report — cited, not quoted; read it at the source link.
supportsTotal capacityWater depthCoordinates
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.