N-10.1

Failed auction August 2025 alongside N-10.2. Industry cited risks without revenue protection, deep water challenges, grid uncertainty.

Status
On Holdlifecycle stage
FragileHafrok completion outlook
Ownership
Location
Germany
North Sea
Technology
Capacity 2,000 MW 
Turbines
Foundation
Site & conditions
Site rights State-designated Germany offshore tender — 2027 (FEP cluster) 
Water depth 39.5–42 m  Distance from shore 120 km  Wind speed 10.4 m/s @ 150 m 
Revenue & grid
Offtake Other  Grid Not recorded 
Schedule
FID Not taken
COD · announced 2033 
COD · Hafrok

Delivery outlook modelled by Hafrok · calibrated on delivered projects

on hold — no credible date; the chart shows when a restarted project might complete
The developer's last guidance was 2033 · not treated as a schedule while the project is on hold
Chance of delivery
≈14% estimated chance this project reaches commercial operation
Projects put on hold complete ≈15% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; a very large build and technical complexity pull a little the other way. Only a restart would change that — there is no dated schedule to judge against.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2030: 20.0% (conditional on completion) 2031: 20.0% (conditional on completion) 2032: 20.0% (conditional on completion) 2033: 20.0% (conditional on completion) 2034: 20.0% (conditional on completion)2026now20272028202920302031203220332034 Developer-announced COD: 2033 ANNOUNCED 2033
COD probability by year, conditional on completion
YearProbability
203020.0%
203120.0%
203220.0%
203320.0%
203420.0%
How Hafrok got this date
1
On hold — no dated schedule
The project is recorded as On Hold, so no sequence of milestones can be trusted. Hafrok publishes no expected year; the chart instead spreads the remaining chance of completion over the years a restarted project might finish in.
2
Chance of delivery — separate from timing
Start from the share of On Hold projects that went on to complete — ≈15%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Historically only a minority of projects put on hold returned to delivery — the estimate reflects that. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈14%, which rates it Fragile on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Revenue & offtake route to market — open

No offtake secured — route to market open

No award — August 2025 centrally pre-investigated site auction received zero bids.

The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
Germany offshore tender — 2027 (FEP cluster)
expected 2027 · planned · the round names this project
indicative

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageOn Hold
Offshore constructionnot started
Expected start of operation2033
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemBalWin2·2000 MW · ±525 kV · under construction, expected 2031
Export & onshore
Export cableBalWin2 Export Cable (Amprion)·HVDC subsea · 376 km · Prysmian · ordered · to Westerkappeln (onshore converter)
Converter supplierSiemens Energy·BalWin2 · Dragados Offshore (Cádiz, Spain) — topside; Aker Solutions (Verdal, Norway) — steel substructure · for Amprion
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20262027202820292030203120322033developer’s stated start 2033nowBalWin2BalWin2expected 2031expected 2031BalWin2 Export Cable (Amprion)BalWin2 Export Cable (Amprion)expected 2031expected 2031

Sources & verification

0/14 fields verified · rests on 7 sources · ◆ 2 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[1]
Bundesamt für Seeschifffahrt und Hydrographie (BSH)2025◆ BSH - Homepage - Offshore: BSH publishes…
“The sites N-10.1 and N-10.2 are located in the German EEZ of the North Sea, around 120 kilometers distant from the island of Helgoland. [N-10.1 capacity] 2,000 megawatts. Water depth: Between 39.5 and…”
supportsTotal capacityWater depthDistance from shore
Auction pipeline1
[7]
Bundesnetzagentur2026◆ bnetza-noncentral-2027
BNetzA — 2026 non-central offshore tenders suspended; N-10.1/N-10.2/N-12.4/N-12.5/N-13.1/N-13.2 moved to tender year 2027.
supportsGermany offshore tender — 2027 (FEP cluster)
Trade press5
[2]
Windtech International (reporting BNetzA auction result)2025-08
Press report — cited, not quoted; read it at the source link.
supportsConsentStatus
[3]
Offshore Wind (offshorewind.biz)2025-08-06
Press report — cited, not quoted; read it at the source link.
supportsMechanismDetailOfftake history
[4]
Offshore Wind (offshorewind.biz)2026-01-29
Press report — cited, not quoted; read it at the source link.
supportsCommercial operation
[5]
4C Offshore2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[6]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed