Gode Wind 3

Located northwest of Norderney. Co-developed with Borkum Riffgrund 3.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2017’18’19’20’21’22’23’24’25’26BNetzA Offshore Wind Auction 2017 (transitional) — awarded to DONG Energy (now Ørsted)BNetzA Offshore Wind Auction 2017 (transitional) Apr 2017 · auction recordView the source for Consent grantedConsent granted 26 Mar 2021 View the sources for Final investment decisionFinal investment decision 1 Dec 2021 View the source for Offshore constructionOffshore construction Aug 2023 View the source for First powerFirst power May 2024 View the sources for Commercial operationCommercial operation Feb 2025 BNetzA Offshore Wind Auction 2017 (transitional) — awarded to DONG Energy (now Ørsted) 2017-04 ORIGINATIONØrsted → Glennmont Partners (Nuveen) — 50.0% · closed 2023-12 2023-10 FARMDOWNTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYØrsted — 50% today · operator Ørsted Ørsted 50%Glennmont Partners (Nuveen) Glennmont Partners Glennmont Partners exited 2023-10Nuveen Infrastructure — 50% today · investor Nuveen Infrastructure Nuveen Infrastructure 50%BNetzA Offshore Wind Auction 2017 (transitional) — awarded to DONG Energy (now Ørsted) Ørsted → Glennmont Partners (Nuveen) — 50.0% · closed 2023-12 50%Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 20242024202420242025-Q12025-02 · 6 recorded revisions · slipped +0.6 yr (first announced 2024)

Revenue & offtake contract duration and price levels · money of the day

242 MW contracted — tender award
Tender award · BNetzA Offshore Wind Auction 2017 (transitional)
Price6 ct/kWh ·Capacity110 MWAwardedApr 2017
Term20 yrs
Tender award · BNetzA Offshore Wind Auction 2018 (transitional)
Price9.83 ct/kWh ·Capacity131.75 MWAwardedApr 2018
Term20 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations22 of 2396% · first seen 2023-08-05
Turbines18 of 2378% · first seen 2023-08-20
Latest count2026-09-01from 462 satellite passes · 2 substation platforms left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (23 turbines + 2 platforms); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
51015202525 planned (turbines and platforms)latest count 2026-09-01foundations — running total, confirmedfoundations — running total, seen in the last 60 days and not yet confirmedAug 2023 — 6 this month · 6 in totalSep 2023 — 6 this month · 12 in totalOct 2023 — 5 this month · 17 in totalNov 2023 — 4 this month · 21 in totalDec 2023 — 2 this month · 23 in totalApr 2024 — 0 this month · 23 in totalMay 2024 — 0 this month · 23 in totalJun 2024 — 0 this month · 23 in totalJul 2024 — 0 this month · 23 in totalAug 2024 — 0 this month · 23 in totalOct 2024 — 0 this month · 23 in totalJan 2025 — 0 this month · 23 in totalJul 2025 — 1 this month · 24 in totalNov 2025 — 0 this month · 24 in totalMar 2026 — 0 this month · 24 in totalMay 2026 — 0 this month · 24 in totalJul 2026 — 0 this month · 24 in totalturbines up — running total, confirmedturbines up — running total, seen in the last 60 days and not yet confirmedAug 2023 — 1 this month · 1 in totalSep 2023 — 0 this month · 1 in totalOct 2023 — 0 this month · 1 in totalNov 2023 — 0 this month · 1 in totalDec 2023 — 0 this month · 1 in totalApr 2024 — 2 this month · 3 in totalMay 2024 — 3 this month · 6 in totalJun 2024 — 3 this month · 9 in totalJul 2024 — 2 this month · 11 in totalAug 2024 — 2 this month · 13 in totalOct 2024 — 1 this month · 14 in totalJan 2025 — 1 this month · 15 in totalJul 2025 — 0 this month · 15 in totalNov 2025 — 1 this month · 16 in totalMar 2026 — 1 this month · 17 in totalMay 2026 — 2 this month · 19 in totalJul 2026 — 1 this month · 20 in total24 foundations20 turbines upAug 2023Oct 2023Dec 2023May 2024Jul 2024Oct 2024Jul 2025Mar 2026Jul 2026
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed40 confirmed · 0 not yet confirmedas counted on 2026-09-01 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortBOW Terminal Eemshaven ·marshalling harbour · quay 5000 m · crane 50 t · draft 14 m
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (40)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Gode Wind 3, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationGode Wind 3 offshore substation·66 (array) kV · in service 2023 · owner Oersted with Glennmont Partners / Nuveen Infrastructure (wind farm owners) — farm-owned, not TSO-owned
HVDC systemDolWin6·900 MW · ±320 kV · in service 2023-09
Converter supplierSiemens Energy·DolWin6 · Dragados Offshore · for TenneT
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2023202420252026developer’s stated start 2025-Q1nowDolWin6DolWin6first planned 2023first planned 2023in service 2023-09in service 2023-09Gode Wind 3 offshore substationGode Wind 3 offshore substationin service 2023in service 2023

Sources & verification

14/17 fields verified · rests on 17 sources (12 primary) · ◆ 12 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
Bundesamt für Seeschifffahrt und Hydrographie (BSH)2021-03-26◆ Planfeststellungsbeschluss Offshore-Wind…
“BSH Az: 5111/Gode Wind 3/PFV/O3103 Hamburg, den 26.03.2021. Der Planfeststellungsbeschluss umfasst 23 (dreiundzwanzig) Windenergieanlagen. Nennleistung je WEA: 11 MW (Power Boost: 11,55 MW). Rotordu…”
supportsConsentTurbinesUnit capacityFoundationCoordinates+1 more
[18]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Gode Wind 3": 23 units, 265.65 MW gross, statuses {'In Betrieb': 23}, operators ['Gode Wind 3 GmbH & Co. oHG'], commissioned 2024-05-07..2024-09-16, planned None..None.”
supportsRegister entry
Operator8
[2]
Ørsted (then DONG Energy)2017-04◆ DONG Energy awarded three German offshor…
“DONG Energy awarded three German offshore wind projects … Gode Wind 3 (110MW). The Gode Wind 3 project was awarded based on a bid price of EUR 60 per MWh. The three projects are planned to be commissi…”
supportsMechanismDetail
[3]
Ørsted2018-04-27◆ Orsted wins 551.75MW in German offshore …
“Orsted's Gode Wind 3 and 4 projects will have a total capacity of 241.75MW at a weighted average price of EUR 81 per MWh. Gode Wind 4: 131.75 MW at EUR 98.30 per MWh.”
supportsMechanismDetail
[4]
Ørsted2021-12-01◆ Orsted takes final investment decision o…
“Orsted's Board of Directors has taken final investment decision (FID) on the two German offshore wind farms Gode Wind 3 (242 MW) and Borkum Riffgrund 3 (900 MW) which are expected to be commissioned i…”
supportsFinal investment decision
[5]
Ørsted2022-02-03◆ Ørsted Annual Report 2021
“In Germany, we took FID on our originally fully merchant Borkum Riffgrund 3 project and the Gode Wind 3 project. … Gode Wind 3 (253 MW) and Borkum Riffgrund 3 (913 MW), Germany, FID'ed. Expected COD i…”
supportsFinal investment decision
[6]
Ørsted2023-12-05◆ Ørsted completes divestment of 50 % of G…
“Orsted has completed the divestment of 50 % of the Gode Wind 3 offshore wind farm to funds managed by Glennmont Partners from Nuveen. Gode Wind 3 has a capacity of 253 MW and was awarded to Orsted in …”
supportsoperatorTotal capacityMechanismStrike / priceDetail
[9]
Ørsted2025-03-06◆ More renewable power from offshore wind …
“More renewable power from offshore wind - Gode Wind 3 starts commercial operation. Orsted will now receive a weighted average price of EUR 81 per MWh for the electricity generated. In Germany, Orsted …”
supportsCommercial operationCOD historyMechanismDetail
[10]
Ørsted2026-02-05◆ Ørsted Annual Report 2025
“In Germany, we commissioned Gode Wind 3 in February and also completed the installation of all foundations and turbines for Borkum Riffgrund 3. Installed renewable capacity increased by 2 % to 18.5 GW…”
supportsCommercial operationTotal capacity
[12]
Ørsted2023-12◆ Ørsted completes divestment of 50 % of G…
supportsinvestor
Auction results2
[19]
Bundesministerium der Justiz2026-06-22◆ de-tender-2017-windseeg-82
WindSeeG 82: Poenale - 100% of security for missing realisation deadline 1 or 2 (30% pre-2021)
supportsTender award · BNetzA Offshore Wind Auction 2017 (transitional)
[20]
Bundesministerium der Justiz2026-06-22◆ de-tender-2018-windseeg-82
WindSeeG 82: Poenale - 100% of security for missing realisation deadline 1 or 2 (30% pre-2021)
supportsTender award · BNetzA Offshore Wind Auction 2018 (transitional)
Trade press5
[7]
offshoreWIND.biz2024-05-08
Press report — cited, not quoted; read it at the source link.
supportsFirst powerModelUnit capacity
[8]
offshoreWIND.biz2025-03-06
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionCommercial operationTurbinesModelUnit capacity+2 more
[11]
offshoreWIND.biz2023-02-06
Press report — cited, not quoted; read it at the source link.
supportsmarshalling harbour
[13]
GEBCO Compilation Group2020
supportsWater depth
[14]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed