DanTysk

Located 70km west of Sylt at German-Danish EEZ border. JV Vattenfall/SWM.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2006’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26View the source for Consent grantedConsent granted Aug 2005 View the sources for Onshore constructionOnshore construction Mar 2012 View the sources for Offshore constructionOffshore construction Feb 2013 View the source for First powerFirst power Dec 2014 View the source for Commercial operationCommercial operation Apr 2015 No origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDVattenfall → Stadtwerke München — 49.0% 2010-07 JV ENTRYTODAYVattenfall — 51% today · operator Vattenfall Vattenfall 51%Stadtwerke München — 49% today · co-owner Stadtwerke München Stadtwerke München 49%Vattenfall → Stadtwerke München — 49.0% 49%
Dashed tick marks today (9 Sep 2026). Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2015-Q22015-04 · 2 recorded revisions · held (announced 2015-Q2, unchanged)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite survey
the farm as it stands, counted from satellite radar images · built before the count began, so there is no build to chart
Satellite survey
Structures standing8180 turbines + 2 platforms expected · 1 fewer than expected — a position the survey missed
Surveyed2026-09-01from 118 satellite passes
Built2013-02 → 2015-04offshore construction to start of operation, from the record
Hafrok counts the structures standing in the sea from satellite radar images (≈) and reads the count against the turbines and platforms on record. The farm was built before this count began, so the images show it complete; they cannot date its construction. Rows marked with a dot (·) come from Hafrok’s own registers.
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered97%a ring on black is a structure this pass could not see, not a mistake
Structures ringed81 confirmed · 0 not yet confirmedas counted on 2026-09-01 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (81)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over DanTysk, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationDanTysk offshore substation·33/155 kV · in service 2013 · owner Vattenfall / Stadtwerke Muenchen (wind farm owners) — farm-owned, not TSO-owned
HVDC systemSylWin1·864 MW · ±320 kV · in service 2015-04 · shared with Butendiek, Sandbank
Converter supplierSiemens·SylWin1 · Nordic Yards (Warnowwerft, Rostock) · for TenneT
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20132014201520162017201820192020202120222023202420252026developer’s stated start 2015-Q2nowSylWin1SylWin1first planned 2014first planned 2014in service 2015-04in service 2015-04DanTysk offshore substationDanTysk offshore substationin service 2013in service 2013

Sources & verification

16/18 fields verified · rests on 9 sources (4 primary) · ◆ 8 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
Bundesamt fuer Seeschifffahrt und Hydrographie (BSH)2005-08◆ Genehmigungsbescheid Offshore-Windpark D…
“Hamburg, den 23.08.2005 — Auf den Antrag der Gesellschaft fuer Energie und Oekologie mbH [...] werden Errichtung und Betrieb von 80 Windenergieanlagen (WEA) einschliesslich Nebenanlagen [...] genehmig…”
supportsConsentTurbinesCoordinatesConsent granted
[9]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "OWP DanTysk": 80 units, 302.4 MW gross, statuses {'In Betrieb': 80}, operators ['DanTysk Sandbank Offshore Wind GmbH & Co.KG'], commissioned 2014-12-02..2015-03-26, planned None..None.”
supportsRegister entry
Operator2
[2]
Vattenfall AB2013-02◆ Vattenfall start bouw van windpark DanTy…
“7 februari 2013 — Vattenfall, het moederbedrijf van Nuon, is gestart met de bouw van DanTysk, een groot windpark van 288MW op zee. Het windpark DanTysk ligt op de grens van de Duitse en Deense economi…”
supportsOnshore constructionOffshore constructionSite rightsTurbinesTotal capacity+1 more
[3]
Vattenfall AB2015-04-30◆ DanTysk offshore wind farm formally open…
“30 April 2015 — Located 70 kilometres west of Sylt Island, the DanTysk offshore wind farm is the first infrastructure project jointly implemented by Vattenfall and SWM as part of the energy transition…”
supportsCommercial operationCOD historyTurbinesModelUnit capacity+6 more
Trade press5
[4]
Offshore Wind Biz2014-12-03◆ DanTysk Starts to Power Germany | Offsho…
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[5]
Offshore Wind Biz2012-03-19◆ Germany: Vattenfall Starts Construction …
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decisionOnshore constructionOffshore constructionSite rights
[6]
Offshore Wind Biz2010-07-20◆ Vattenfall and Munich utility intend to …
Press report — cited, not quoted; read it at the source link.
supportsoperatorco-owner
[7]
Mondaq (legal commentary)2012◆ The German Renewable Energy Act Of 2012 …
“Offshore wind parks that commission by 2017 will receive 15 ct/kWh for an initial period of 12 years. Those that begin operating in 2019, however, will receive only 12.97 ct/kWh.”
supportsMechanismDetail
[8]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed