Jiangsu Dafeng H2-1 (Longyuan)

Jiangsu Dafeng H2-1 (Longyuan). GEM records phase 1 100 MW construction.

Status
Under Constructionlifecycle stage
DeliveringHafrok completion outlook
Ownership
Location
China
Yellow Sea
Technology
Capacity 100 MW 
Turbines
Foundation Fixed-bottom (structure not recorded) 
Site & conditions
Site rights Seabed rights held 
Revenue & grid
Offtake
Grid
Schedule
FID Taken · date not recorded 
COD · Hafrok 2028 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2028
expected year of commercial operation
Chance of delivery
≈97% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. Technical complexity and no offtake contract yet pull this one slightly below that.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2027: 10.0% (conditional on completion) 2028: 58.5% (conditional on completion) 2029: 26.6% (conditional on completion) 2030: 4.5% (conditional on completion) 2031: 0.5% (conditional on completion)2026now2027202858%EXPECTED202920302031
COD probability by year, conditional on completion
YearProbability
202710.0%
2028 (expected)58.5%
202926.6%
20304.5%
20310.5%
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2026. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2028; the faster quarter of similar projects would be done by 2027, the slower quarter not until 2029.
3
Result
Expected commercial operation 2028, likely range 2027–2029 (the middle half of outcomes for similar projects). The typical build time from the construction start is used.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈97%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

2027’28Commercial operation 2028 ·Hafrok expected
Dashed tick marks today (9 Sep 2026).

Revenue & offtake the regime the project was built under

Offtake regime not on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation under way
no satellite count yet: this farm is outside the tracker’s coverage so far
Installation · on record
StageUnder Construction
Offshore constructionstarted
Expected start of operationnot stated

Sources & verification

0/7 fields verified · rests on 2 sources · ◆ 2 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Trade press2
[1]
Global Energy Monitor2026◆ Jiangsu Dafeng H2-1 (Longyuan) Offshore …
supportsoperatorConsentFinal investment decisionSite rightsTotal capacity+2 more
[2]
Global Energy Monitor◆ Global Wind Power Tracker Methodology
“Offshore hard mount: have wind turbines that are usually designed for installation in water no deeper than 60 meters [...] Offshore floating: are an emerging technology designed for installation in de…”
supportsFoundation