VinEnergo Ky Anh Ha Tinh

Ky Anh district, Ha Tinh Province. 825 hectares. 50-year term. VND 17.05 trillion (~USD 647 million).

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2033
expected year of commercial operation
The developer says 2028-Q4; Hafrok expects 2033 — 5 years later.
Chance of delivery
≈50% estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. This one sits well below that: a market with no delivery record yet, technical complexity and no offtake contract yet.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2032: 14.1% (conditional on completion) 2033: 28.0% (conditional on completion) 2034: 22.7% (conditional on completion) 2035: 14.6% (conditional on completion) 2036: 8.7% (conditional on completion) 2037: 5.1% (conditional on completion) 2038: 3.1% (conditional on completion) 2039: 1.8% (conditional on completion) 2040: 1.1% (conditional on completion) 2041: 0.7% (conditional on completion)2026now202820302032203328%EXPECTED2034203620382040 Developer-announced COD: 2028 ANNOUNCED 2028
COD probability by year, conditional on completion
YearProbability
203214.1%
2033 (expected)28.0%
203422.7%
203514.6%
20368.7%
20375.1%
20383.1%
20391.8%
20401.1%
20410.7%
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (2026), adds the time similar projects (in new offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.
2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before 2033 is not credible.
3
Merchant project — financing counted from today
The project has no offtake contract yet. This project's route offers no support scheme: it has to sign a power contract and take a financing decision on its own, and Hafrok counts that from today (2026 Q3) rather than from a tender it cannot enter. The permits are not affected; winners typically reach final investment decision about 2 years after an award (2028 Q3), then build time on top gives 2031 Q3. The milestone timing is already later than that, so it stands.
4
Result
Expected commercial operation 2033, likely range 2033–2038 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.
5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈50%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

2027’28’29’30’31’32’33Developer-announced COD: 2028-Q4 announced COD 2028-Q4Commercial operation 2033 ·Hafrok expected
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2028-Q4

Sources & verification

0/12 fields verified · rests on 7 sources · ◆ 3 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Trade press6
[2]
VietnamPlus (Vietnam News Agency)2025-10-22◆ Ha Tinh Approves 17 Trillion Vnd Ky Anh …
“The Ha Tinh People's Committee has assigned the provincial Department of Industry and Trade to act as the lead agency in seeking expressions of interest and selecting investors. The wind farm will hav…”
supportsCommercial operationTotal capacityStatusConnection point
[3]
The Investor (Vietnam)2025-12◆ Central Vietnam province Ha Tinh picks V…
Press report — cited, not quoted; read it at the source link.
supportsoperatorConsentSite rights
[4]
Vietnam Plus2025
supportsTurbinesTotal capacity
[5]
Global Energy Monitor2026-07-02
supportsCoordinates
[6]
GEBCO Compilation Group2020
supportsWater depth
[7]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown◆ Ha Tinh Approves 17 Trillion Vnd Ky Anh …
supportsTurbinesTotal capacityWater depthCoordinates