Thang Long Wind (Ke Ga)

Ke Ga Cape, Binh Thuan Province. First survey licence in Vietnam. 2,000 km² site. UK-registered developer.

Status
On Holdlifecycle stage
FragileHafrok completion outlook
Ownership
ENEnterprize Energy — 50% 
Undisclosed investor — 50% 
Location
Vietnam
South China Sea
Technology
Capacity 3,400 MW 
Turbines
Foundation
Site & conditions
Site rights Not established we have not found a document granting or refusing rights over this seabed — a gap in our research, not a finding about the project 
Water depth 11–24 m 
Revenue & grid
Offtake
Grid
Schedule
FID Not taken
COD · announced 2031 
COD · Hafrok

Delivery outlook modelled by Hafrok · calibrated on delivered projects

on hold — no credible date; the chart shows when a restarted project might complete
The developer's last guidance was 2031 · not treated as a schedule while the project is on hold
Chance of delivery
≈11% estimated chance this project reaches commercial operation
Projects put on hold complete ≈15% of the time on Hafrok's record. This one sits below that: a market with no delivery record yet, a very large build, technical complexity and no offtake contract yet. Only a restart would change that — there is no dated schedule to judge against.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2030: 20.0% (conditional on completion) 2031: 20.0% (conditional on completion) 2032: 20.0% (conditional on completion) 2033: 20.0% (conditional on completion) 2034: 20.0% (conditional on completion)2026now20272028202920302031203220332034 Developer-announced COD: 2031 ANNOUNCED 2031
COD probability by year, conditional on completion
YearProbability
203020.0%
203120.0%
203220.0%
203320.0%
203420.0%
How Hafrok got this date
1
On hold — no dated schedule
The project is recorded as On Hold, so no sequence of milestones can be trusted. Hafrok publishes no expected year; the chart instead spreads the remaining chance of completion over the years a restarted project might finish in.
2
Chance of delivery — separate from timing
Start from the share of On Hold projects that went on to complete — ≈15%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Historically only a minority of projects put on hold returned to delivery — the estimate reflects that. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈11%, which rates it Fragile on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageOn Hold
Offshore constructionnot started
Expected start of operation2031

Sources & verification

1/8 fields verified · rests on 5 sources
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator2
[2]
Enterprize Energy2024
“Enterprize Energy project page (Thang Long Offshore Wind): "Owned: EE 50% - Confidential Investor 50%". Page notes "In Q4 of 2020, Enterprize Energy secured investment from a partner to co-invest in t…”
supportsoperatorinvestor
[5]
Enterprize Energy2024
supportsTotal capacity
Trade press2
[3]
GEM2026
supportsCoordinates
[4]
GEBCO Compilation Group2020
supportsWater depth
Unverified import1
[1]
unknown
supportsConsentCommercial operationTotal capacityWater depthCoordinates