Phu Cuong Soc Trang Phase 1

Soc Trang Province, Mekong Delta. Mainstream 70% / Phu Cuong 30%. Pioneer project in shallow southern Vietnam.

Status
Early Developmentlifecycle stage
ProspectiveHafrok completion outlook
Ownership
PCPhu Cuong Group — 30% 
Location
Vietnam
South China Sea
Technology
Capacity 200 MW 
Turbines
Foundation
Site & conditions
Site rights Application filed 2021-11  Water depth 1–3 m  Wind speed 6.7 m/s @ 150 m 
Revenue & grid
Offtake
Grid Applied · 2021-11  Connection EVN grid connection substation (onshore) 
Schedule
FID Not taken
COD · Hafrok 2033 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2033
expected year of commercial operation
Chance of delivery
≈50% estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. This one sits well below that: a market with no delivery record yet, technical complexity and no offtake contract yet.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2032: 14.1% (conditional on completion) 2033: 28.0% (conditional on completion) 2034: 22.7% (conditional on completion) 2035: 14.6% (conditional on completion) 2036: 8.7% (conditional on completion) 2037: 5.1% (conditional on completion) 2038: 3.1% (conditional on completion) 2039: 1.8% (conditional on completion) 2040: 1.1% (conditional on completion) 2041: 0.7% (conditional on completion)2026now202820302032203328%EXPECTED2034203620382040
COD probability by year, conditional on completion
YearProbability
203214.1%
2033 (expected)28.0%
203422.7%
203514.6%
20368.7%
20375.1%
20383.1%
20391.8%
20401.1%
20410.7%
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (2026), adds the time similar projects (in new offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.
2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before 2033 is not credible.
3
Merchant project — financing counted from today
The project has no offtake contract yet. This project's route offers no support scheme: it has to sign a power contract and take a financing decision on its own, and Hafrok counts that from today (2026 Q3) rather than from a tender it cannot enter. The permits are not affected; winners typically reach final investment decision about 2 years after an award (2028 Q3), then build time on top gives 2031 Q3. The milestone timing is already later than that, so it stands.
4
Result
Expected commercial operation 2033, likely range 2033–2038 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.
5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈50%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2022’23’24’25’26’27’28’29’30’31’32’33View the source for Consent appliedConsent applied Nov 2021 Commercial operation 2033 ·Hafrok expectedMainstream Renewable Power, Phu Cuong Group — stake not disclosed · closed 2021-Q4 2017-Q1 JV FORMATIONTODAYMainstream Renewable Power — 70% today · operator Mainstream Renewable Po… Mainstream Renewable Po… 70%Phu Cuong Group — 30% today · developer Phu Cuong Group Phu Cuong Group 30%Mainstream Renewable Power, Phu Cuong Group — stake not disclosed · closed 2021-Q4
Dashed tick marks today (9 Sep 2026). Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

1/11 fields verified · rests on 6 sources · ◆ 1 document held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator2
[2]
PR Newswire / Mainstream Renewable Power2021-11-12
“Mainstream owning 70% of the asset and the Phu Cuong Group owning the remaining 30%. … 200 MW of capacity set to be delivered in phase 1 … The project is anticipated to reach financial close in 2022, …”
supportsConsentSite rightsTotal capacityStatusConnection point+1 more
[5]
Mainstream Renewable Power2025◆ Phu Cuong Soc Trang Wind Farm - Mainstre…
supportsoperatordeveloper
Trade press3
[6]
GEM2026
supportsTotal capacityCoordinates
[7]
GEBCO Compilation Group2020
supportsWater depth
[8]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsTotal capacityWater depthCoordinates