Vineyard Wind 1
Located approximately 24 km south of Nantucket, Massachusetts (14 miles / 23 km southeast of Martha's Vineyard per BOEM ROD).
Status
Operationallifecycle stage
Ownership
AIAvangrid Renewables (Iberdrola) — 50% ◆
CIP — 50% ◆Location
Northwest Atlantic
Technology
Capacity
806 MW ◆
Turbines
62 × 13 MW ◆
Model
GE Haliade X 13 MW ◆
Foundation
Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Origination
BOEM Lease Sale 4 · 2015 ·
Water depth
37–49 m ◆
Distance from shore
24 km ◆
Wind speed
10.2 m/s @ 150 m ≈
Revenue & grid
Offtake
PPA · $74/MWh ◆
Grid
Secured · 2020-10-29 ◆
Connection
NSTAR 115kV switch station, Barnstable (Independence Park, MA); … ◆
Schedule
FID
15 Sep 2021 ◆
COD
24 Apr 2026 ◆
Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2015-01
BOEM Lease Sale 4
- Awarded to
- Offshore MW LLC
- Lease
- OCS-A 0501
- Basis
- seabed award
From the auction results — the round that created the project.
Acquisition · 2016-09
Offshore MW LLC (Blackstone-owned) → CIP 100%
- Stake
- 100%
- Consideration
- not disclosed
- Announced
- 2016-09
- Project stage
- early development
"International law firm Watson Farley & Williams advised Copenhagen Infrastructure Partners on the acquisition, on behalf of its Copenhagen Infrastructure II fund, of 100% of OffshoreMW LLC from leading US private equity firm Blackstone. OffshoreMW holds a 675 square km offshore wind energy lease issued by the US Bureau of Ocean Energy Management and located off the coast of Massachusetts" (WFW release, 6 Sep 2016, republished on windfair.net — copyrighted host, internal reading). OffshoreMW LLC is the BOEM ATLW-4 awardee of lease OCS-A 0501 (origination); the seller string names the vehicle sold with its owner, so the chain links the 2015 awardee to CIP. OffshoreMW was renamed Vineyard Wind; Avangrid bought 50% from CIP in May 2017 (next row). Price undisclosed. Written 2026-08-19.
Evidence
- Watson Farley & Williams (press release republished on windfair.net) — WFW advises CIP on Massachusetts offshore wind project acquisition ↗ 2016-09-06 ◆ held
From Hafrok’s transactions record
JV entry · 2017-05
CIP → Avangrid 50%
- Stake
- 50%
- Consideration
- not disclosed
- Announced
- 2017-05
- Project stage
- early development
Avangrid Renewables (the US subsidiary of Iberdrola) acquired a 50% stake in Vineyard Wind from Copenhagen Infrastructure Partners (CIP), announced May 9, 2017. CIP had originally acquired the Vineyard Wind developer (then known as OffshoreMW) from Blackstone in August 2016, and was developing the project through its funds CI-II and CI-III. Following the Avangrid entry, Vineyard Wind LLC was held 25% by CI-II, 25% by CI-III, and 50% by Avangrid Renewables — constituting a 50/50 split between CIP funds and Avangrid. Deal consideration was not publicly disclosed; the CEO of Avangrid declined to comment on the terms of the deal. Project was at early development stage — the BOEM Commercial Lease OCS-A 0501 had been awarded in January 2015. At the time of announcement, the project was one of the first large-scale US offshore wind projects to secure a corporate anchor partner. The eventual project is 806 MW (Vineyard Wind 1) with 62x GE Haliade-X 13 MW turbines.
Evidence
- businesswire.com — AVANGRID Acquires Major Stake in Massachusetts Off-Shore Wind Project with Vineyard Wind ↗ 2017-05 ◆ held
- offshoreWIND.biz — Avangrid Takes Half of Vineyard Wind ↗ 2017-05 ◆ held
- iberdrola.com — Avangrid joins the offshore wind project, Vineyard Wind, off the coast of Massachusetts ↗ 2017-05 ◆ held
From Hafrok’s transactions record
JV formation · 2019-12
Avangrid · CIP stake not disclosed
- Stake
- not disclosed
- Consideration
- not disclosed
- Announced
- 2019-12
- Closed
- 2020-03
- Project stage
- pre-FID
JV restructured — Avangrid (Iberdrola) and CIP formed 50/50 joint venture. CIP later divested position.
Evidence
- vineyardwind.com — Vineyard Wind ↗ 2019-12 ◆ held
- vineyardwind.com — Partners ↗ 2019-12 ◆ held
From Hafrok’s transactions record
Secondary trade · 2021-09
CIP / Avangrid → Avangrid / CIP stake not disclosed
- Stake
- not disclosed
- Consideration
- €142m
- Announced
- 2021-09
- Closed
- 2022-01
- Project stage
- pre-FID
Avangrid Renewables and CIP agreed to restructure their joint Vineyard Wind LLC holding entity to separate assets across the broader portfolio. The restructuring was announced September 2021 and closed January 10, 2022. Under the transaction: Avangrid Renewables took 100% ownership of the Park City Wind (804 MW, Connecticut) and Commonwealth Wind (1,232 MW, Massachusetts) offshore wind projects. CIP took 100% of BOEM Lease OCS-A 0522 (an undeveloped lease). The Vineyard Wind 1 (806 MW) project was retained as a 50/50 JV between Avangrid and CIP, unchanged. Avangrid made a net payment of USD 167.5 million to CIP to equalise the asset values exchanged. At USD/EUR 0.85 (2021 announcement), net payment = approximately EUR 142 million. This restructuring was primarily an asset swap / portfolio rationalisation rather than a direct sale of stakes in Vineyard Wind 1. Both partners retain 50% of Vineyard Wind 1. Vineyard Wind 1 achieved financial close (debt) in September 2021, shortly before this restructuring announcement.
Evidence
- renewablesnow.com — Avangrid, CIP to split Vineyard Wind LLC's offshore wind rights in US - Offshore Wind News ↗ 2021-09 ◆ held
- businesswire.com — Avangrid Renewables Closes Vineyard Wind JV Restructuring and Increases Offshore Wind Portfolio to 4.9 GW ↗ 2021-09 ◆ held
- vineyardwind.com — Avangrid Renewables and Copenhagen Infrastructure Partners Announce Strategic Transaction to Advance Offshore Wind Development ↗ 2021-09 ◆ held
From Hafrok’s transactions record
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2021→2025-12→2025→2026-04-24 · 4 recorded revisions · slipped +4.8 yr (first announced 2021)
Revenue & offtake contract duration and price levels · money of the day
800 MW contracted — utility PPA
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation complete
not yet surveyed by satellite; the built farm can be, on request
Installation · on record
StageOperational
In operation since2026-04-24
Offshore construction2023-06 → 2026-04-24
Construction ports
PortNew Bedford Marine Commerce Terminal ◆·staging · quay 366 m · draft 9.8 m
Sources & verification
17/18 fields verified · rests on 15 sources (14 primary) · ◆ 7 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator4
[1]
U.S. Department of the Interior / BOEM2021-05-11◆ Vineyard Wind 1 Final Record of Decision…
“joint Record of Decision (ROD) for the final Environmental Impact Statement (FEIS) prepared for the Vineyard Wind 1 Offshore Wind Energy Project (Project) Construction and Operations Plan (COP). The R…”
supportsConsentDistance from shoreConsent granted
[3]
Bureau of Ocean Energy Management2015-04-01◆ document
“Offshore MW LLC (later renamed Vineyard Wind LLC) secured commercial lease OCS-A 0501 from BOEM... The lease covers 166,886 acres in federal waters approximately 12 nautical miles south of Martha's Vi…”
supportsWater depthCoordinates
[13]
Bureau of Ocean Energy Management2021-07-15◆ Vineyard Wind 1 COP approval letter
“Bureau of Ocean Energy Management (BOEM), Office of Renewable Energy Programs regarding Vineyard Wind LLC's (Vineyard Wind) regulatory departure request… BOEM approved Vineyard Wind's Construction and…”
supportsConsentConsent granted
[33]
Bureau of Ocean Energy Management (BOEM)2026-08-23◆ US BOEM offshore-wind register (FR docum…
“Lease row OCS-A 0501: companies ['Vineyard Wind 1 LLC']; lease_dates ['04/01/2015']; lease_terms ['25 Years']; states ['Massachussets']; block_count 100.”
supportsRegister entry
Operator5
[4]
[5]
Vineyard Wind (Avangrid / CIP)2024-01-03
"At 11:52 PM on January 2, 2024, a single Vineyard Wind 1 turbine delivered approximately 5 MW to the New England grid… Total Capacity: 806 megawatts, 62 wind turbines, Turbine Model: GE Haliade-X." .…
supportsFirst powerTurbinesModelUnit capacityTotal capacity
[6]
Vineyard Wind (Avangrid / CIP)2023-06-07
“CEO Klaus S. Moeller stated: 'We can finally say it – as of today, there is steel in the water.' DEME's heavy-lift vessel ORION installed the first monopile foundation at the Vineyard Wind 1 site… 62 …”
supportsOnshore constructionOffshore constructionFoundationstaging
[9]
Vineyard Wind2020-10-29
“This agreement allows Vineyard Wind's first 800 MW offshore wind farm to connect its generation into the New England electric power grid at the NSTAR 115kV switch station in Barnstable, Mass.”
supportsStatusConnection point
[27]
Vineyard Wind (Avangrid / CIP)2021-11-19
“(NEW BEDFORD, MA) – Vineyard Wind, a joint venture between Avangrid Renewables, a subsidiary of AVANGRID, Inc. (NYSE: AGR), and Copenhagen Infrastructure Partners (CIP), today broke ground on Vineyard…”
supportsOnshore constructionOffshore construction
Auction results1
[34]
MA DOER / EDCs2017◆ us-ma-83c-r1
Massachusetts 83C Round 1 RFP (Jun 2017) - selected Vineyard Wind 1 (survived).
supportsUtility PPA · Massachusetts Section 83C Round 1
Trade press5
[7]
offshoreWIND.biz2026-03-16
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityTotal capacityFoundation+1 more
[11]
Union of Concerned Scientists2018-08-01◆ document
“Vineyard Wind levelized price $65/MWh over the term; 20-year average $84.23/MWh levelized nominal, equivalent to a levelized NPV of $64.97/MWh in 2017 dollars. The 800 MW Vineyard Wind project priced …”
supportsMechanismStrike / priceDetail
[26]
[28]
The New Bedford Light2026-06-01
“Vineyard Wind announced it reached its commercial operation date on April 24. However, if the project achieves commercial operation with a "capacity deficiency," it can exercise a "capacity downsize o…”
supportsCommercial operationCOD history
[29]