Coastal Virginia Offshore Wind Pilot (CVOW-P)

Located 43.5 km (27 miles) east of Virginia Beach. Monopiles 7.8 m diameter, 877 t each.

Project timeline verified milestones only — each date carries its provenance mark

Dashed tick marks today (9 Sep 2026).
Announced-COD history: 2020-Q42020-Q4 · 2 recorded revisions · held (announced 2020-Q4, unchanged)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation complete
not yet surveyed by satellite; the built farm can be, on request
Installation · on record
StageOperational
In operation since2020-Q4
Offshore construction2020-05 → 2020-Q4

Sources & verification

12/17 fields verified · rests on 11 sources (5 primary) · ◆ 7 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
Bureau of Ocean Energy Management (BOEM)2016-03-24◆ BOEM approves VOWTAP Research Activities…
“today the Bureau of Ocean Energy Management (BOEM) announced its approval of the first wind energy Research Activities Plan (RAP) for a facility to be located in U.S. federal waters [...] clearing the…”
supportsConsentTurbinesUnit capacityTotal capacityConsent granted
[2]
Bureau of Ocean Energy Management (BOEM)2019-06◆ Coastal Virginia Offshore Wind Project (…
“June 2019: BOEM announced the approval of the Research Activities Plan revision”
supportsConsentConsent granted
[11]
Bureau of Ocean Energy Management (BOEM)2026-08-23◆ US BOEM offshore-wind register (FR docum…
“Lease row OCS-A 0497: companies ['Virginia Department of Energy']; lease_dates ['04/01/2015']; lease_terms ['30 Years']; states ['Virginia']; block_count 7.”
supportsRegister entry
Operator3
[3]
Dominion Energy2019-07-01◆ Construction Begins on Dominion Energy O…
“Dominion Energy formally began construction on the Coastal Virginia Offshore Wind project, breaking ground to install a half-mile conduit, which will hold the final stretch of cables connecting the tu…”
supportsoperatorFinal investment decisionOnshore constructionOffshore constructionSite rights+4 more
[5]
Dominion Energy2020-06-29◆ Dominion Energy Completes Construction o…
“The first offshore wind farm to be approved by the Bureau of Ocean Energy Management (BOEM) and installed in federal waters, and second constructed in the United States, was built safely and on schedu…”
supportsTurbinesTotal capacityDistance from shore
[7]
Dominion Energy2020-10-14
“CVOW is the only project currently permitted under the BOEM process and will be the first fully operational wind power generation facility in U.S. federal waters with the capability to generate enough…”
supportsCommercial operationCOD historyTurbinesTotal capacity
Trade press5
[4]
offshoreWIND.biz2020-06-23◆ First Wind Turbine Installed in US Feder…
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityFoundation
[6]
offshoreWIND.biz2020-09-29◆ Virginia's Offshore Wind Turbines Now Ge…
Press report — cited, not quoted; read it at the source link.
supportsFirst powerModelUnit capacityTotal capacityDistance from shore
[8]
Global Energy Monitor2026-07-02
supportsCoordinates
[9]
GEBCO Compilation Group2020
supportsWater depth
[10]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed