Triton Knoll

Located off Lincolnshire coast. 857 MW capacity.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2004’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 2 — awarded to RWE / J-Power / KansaiCrown Estate Round 2 Dec 2003 · auction recordView the source for Final investment decisionFinal investment decision 2018 View the source for Onshore constructionOnshore construction 2020 View the source for First powerFirst power 2021-Q1 View the source for Commercial operationCommercial operation 2022-Q1 Crown Estate Round 2 — awarded to RWE / J-Power / Kansai 2003-12 ORIGINATIONRWE → Statkraft — 50% 2015-02 JV ENTRYStatkraft → innogy — 50% 2017-10 ACQUISITIONinnogy → J-Power — 25% 2018-08 FARMDOWNinnogy → Kansai Electric Power — 16% 2018-08 FARMDOWNTODAYRWE — 59% today · operator RWE RWE 59%J-Power — 25% today J-Power J-Power 25%Kansai Electric — 16% today Kansai Kansai 16%Statkraft Statkraft Statkraft exited 2017-10innogy innogy innogy exited 2018-08Crown Estate Round 2 — awarded to RWE / J-Power / Kansai RWE → Statkraft — 50% 50%Statkraft → innogy — 50% 50%innogy → J-Power — 25% 25%innogy → Kansai Electric Power — 16% 16%
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 20222022-Q12022-Q12022-01 · 4 recorded revisions · pulled forward -0.5 yr (first announced 2022)

Revenue & offtake contract duration and price levels · money of the day

CfD-backed offtake
CfD · AR2
Price£74.75/MWh ·
Basis2012 real · CPI-indexed
Capacity860 MWAwardedSep 2017
Term15 yrs · delivery 2021/22
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-07, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR2
50100150nowCfD · AR2 — £74.75/MWh · 2012 real · CPI-indexedCfD · AR2 — £74.75/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR2 term · 15 yrs2017202020232026202920322035CfD · AR2 — £74.75/MWh · 2012 real · CPI-indexed — 80.4 at award110.1 now

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations90 of 90100% · first seen 2020-01-22
Turbines90 of 90100% · first seen 2020-04-13
Latest count2023-12-30from 645 satellite passes · 2 substation platforms left out so the counts compare with the turbine number · the count has ended: the build is complete
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (90 turbines + 2 platforms); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
2040608092 planned (turbines and platforms)latest count 2023-12-30foundations — running total, confirmedJan 2020 — 2 this month · 2 in totalFeb 2020 — 1 this month · 3 in totalMar 2020 — 5 this month · 8 in totalApr 2020 — 6 this month · 14 in totalMay 2020 — 6 this month · 20 in totalJun 2020 — 13 this month · 33 in totalJul 2020 — 34 this month · 67 in totalAug 2020 — 25 this month · 92 in totalSep 2020 — 0 this month · 92 in totalFeb 2021 — 0 this month · 92 in totalMar 2021 — 0 this month · 92 in totalApr 2021 — 0 this month · 92 in totalMay 2021 — 0 this month · 92 in totalJun 2021 — 0 this month · 92 in totalJul 2021 — 0 this month · 92 in totalAug 2021 — 0 this month · 92 in totalSep 2021 — 0 this month · 92 in totalOct 2021 — 0 this month · 92 in totalturbines up — running total, confirmedJan 2020 — 0 this month · 0 in totalFeb 2020 — 0 this month · 0 in totalMar 2020 — 0 this month · 0 in totalApr 2020 — 1 this month · 1 in totalMay 2020 — 0 this month · 1 in totalJun 2020 — 1 this month · 2 in totalJul 2020 — 0 this month · 2 in totalAug 2020 — 0 this month · 2 in totalSep 2020 — 1 this month · 3 in totalFeb 2021 — 7 this month · 10 in totalMar 2021 — 3 this month · 13 in totalApr 2021 — 14 this month · 27 in totalMay 2021 — 16 this month · 43 in totalJun 2021 — 14 this month · 57 in totalJul 2021 — 12 this month · 69 in totalAug 2021 — 6 this month · 75 in totalSep 2021 — 16 this month · 91 in totalOct 2021 — 1 this month · 92 in total92 foundations92 turbines upJan 2020Mar 2020May 2020Jul 2020Sep 2020Mar 2021May 2021Jul 2021Sep 2021
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass · 1 newer pass skipped because the satellite’s track only caught part of the farm (the best of them 0%)
Farm covered100%the whole farm lies inside the image
Structures ringed92 confirmed · 0 not yet confirmedas counted on 2023-12-30 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortAble Seaton Port Marshalling / turbine installation
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (92)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Triton Knoll, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationTriton Knoll OSP West·owner Triton Knoll OFTO (see notes); built by RWE-led Triton Knoll Offshore Wind Farm Ltd
Offshore substationTriton Knoll OSP East·owner Triton Knoll OFTO (see notes); built by RWE-led Triton Knoll Offshore Wind Farm Ltd

Sources & verification

14/18 fields verified · rests on 15 sources (13 primary) · ◆ 10 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator4
[5]
Planning Inspectorate2013-07-11◆ Triton Knoll Offshore Wind Farm - Projec…
“This project is at the post-decision stage. This application was granted on 11 July 2013.”
supportsConsent
[6]
UK Department for Business, Energy & Industrial Strategy (BEIS)2017-09-11◆ CfD Allocation Round 2 results
“Triton Knoll Offshore Wind Farm | Triton Knoll Offshore Wind Farm Limited | Offshore Wind | 860.00 [MW capacity] | 74.75 [strike price, 2012 prices] | 2021/22 [delivery year] | England ... footnote 1:…”
supportsMechanismDetail
[8]
UK Statutory Instruments (legislation.gov.uk)2022◆ The Triton Knoll Offshore Wind Farm (Tra…
supportsCoordinates
[16]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2532: Site Name "Triton Knoll", Development Status "Operational", Installed Capacity 857 MWelec, Operator "Innogy"”
supportsRegister entry
Operator6
[1]
RWE◆ Offshore Wind Farm Triton Knoll
“owned by RWE (59%), J-Power (25%) and Kansai Electric Power (16%). Offshore work began January 2020; commissioning completed January 2022. ... Offshore construction commenced in January 2020, 20 miles…”
supportsOnshore constructionCommercial operationTurbinesModelUnit capacity+2 more
[2]
RWE2021-03-01◆ Triton Knoll Offshore Wind Farm generate…
“Triton Knoll offshore wind farm generated first power on 1 March 2021. ... Triton Knoll Offshore Wind Farm generates first power ... RWE has taken a significant step towards achieving full power at it…”
supportsFirst powerMarshalling / turbine installation
[4]
RWE2022-01-13◆ RWE announces further milestone for Trit…
“Triton Knoll turbines commissioned on time, with full operations expected Q1 2022 ... Standing at 164 meters tall, full operations of the 90 turbines are expected in the first quarter of 2022.”
supportsStatusConnection point
[9]
Triton Knoll Offshore Wind Farm (RWE)
supportsFoundation
[15]
RWE AG2023-12-05◆ Triton Knoll Offshore Wind Farm: Sale of…
“Construction of Triton Knoll was completed in April 2021 and all turbines were fully commissioned in January 2022. The power output of Triton Knoll is 857 megawatts (MW)”
supportsCOD history
[17]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000193: "Triton Knoll Offshore Wind Farm", Status "Built", MW Connected 824, Effective From n/a, Customer "TRITON KNOLL OFFSHORE WIND FARM LIMITED"”
supportsRegister entry
Auction results1
[18]
BEIS (gov.uk)2017-09◆ cfd-ar2-results-2017
Triton Knoll Offshore Wind Farm — Offshore Wind 860.00 MW, GBP 74.75, 2021/22; Hornsea Project 2 (Breesea Limited) — 1,386.00 MW, GBP 57.50, 2022/23; Moray Offshore Windfarm (East) — 950.00 MW, GBP 57…
supportsCfD · AR2
Trade press4
[10]
Power Technology
Press report — cited, not quoted; read it at the source link.
supportsWater depth
[11]
NS Energy2022
Press report — cited, not quoted; read it at the source link.
supportsoperatorowner
[12]
offshoreWIND.biz2018-08-31
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[13]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed