Sofia Offshore Wind Farm
Located on Dogger Bank. Part of original Forewind Dogger Bank development, formerly known as Teesside B.
Status
Under Constructionlifecycle stage
DeliveringHafrok completion outlook
Ownership
RWE — 100% ◆Location
North Sea
Technology
Capacity
1,400 MW ◆
Turbines
100 × 14 MW ◆
Model
Siemens Gamesa SG 14-222 DD ◆
Foundation
Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Origination
Crown Estate Round 3 · 2010 ·
Water depth
20–35 m ◆
Distance from shore
195 km ◆
Wind speed
10.4 m/s @ 150 m ≈
Revenue & grid
Offtake
CfD · AR3 · £39.65/MWh ◆
Grid
Secured · 2021-03-24 ◆
Connection
Lackenby 400kV substation, Teesside ◆
Schedule
FID
24 Mar 2021 ◆
COD · announced
2026-Q3 ◆
COD · Hafrok
2026 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2026
expected year of commercial operation
Chance of delivery
≈98%
estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
| Year | Probability |
|---|---|
| 2026 (expected) | 86.7% |
| 2027 | 13.3% |
| Stated | Announced COD |
|---|---|
| 2021-03-24 | 2026-Q4 |
| 2023-09-04 | 2026 |
| 2025-03-27 | 2026-H2 |
| 2025-11-10 | 2026-09 |
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in
2021. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of
2023; the faster quarter of similar projects would be done by 2022, the slower quarter not until 2024. Dates already in the past are moved up to today — this project has run beyond the typical timing.3
Result
Expected commercial operation
2026, likely range 2025–2027 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it
Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2010-01
Crown Estate Round 3
- Awarded to
- Forewind (SSE, RWE Npower, Statoil, Statkraft)
- Zone
- Dogger Bank zone
- Basis
- seabed award
From the auction results — the round that created the project.
Acquisition · 2017-08
Forewind (E.ON / RWE / Statkraft / Masdar consortium) → RWE 100%
- Stake
- 100%
- Consideration
- not disclosed
- Announced
- 2017-08
- Project stage
- early development
innogy (then separate from RWE, majority-owned by RWE) acquired 100% of the Dogger Bank Teesside B lease from the Forewind consortium and renamed it Sofia Offshore Wind Farm. Deal value not publicly disclosed. innogy was subsequently reintegrated into RWE via the RWE/E.ON asset swap completed July 2020, meaning RWE became the ultimate owner of Sofia with no separate consideration for this project.
Evidence
From Hafrok’s transactions record
Farmdown · 2025-05
RWE 50%
- Stake
- 50%
- Consideration
- not disclosed
- Announced
- 2025-05
- Project stage
- under construction
RWE CFO Michael Muller announced in May 2025 that RWE intends to sell approximately a 50% partner stake in Sofia in 2026, consistent with RWE's portfolio recycling strategy. No buyer has been named as of Feb 2026. The project is currently under construction and on schedule for end-2026 commissioning.
Evidence
- offshoreWIND.biz — RWE Mulls Stake Sale in 1.4 GW Sofia Offshore Wind Farm ↗ 2025-05 ◆ held
- RWE — RWE — 2025 03 20 RWE FY 2024 presentation ↗ 2025 ◆ held
From Hafrok’s transactions record
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: held (announced 2026-Q4, unchanged) · the full guidance history is in the delivery chart above
Revenue & offtake contract duration and price levels · money of the day
CfD-backed offtake
● CfD · AR3
Price£39.65/MWh ·Basis2012 real · CPI-indexed
Capacity1,400 MWAwardedSep 2019Term15 yrs · delivery 2023/24
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-07, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR3
Installation how the build is going · from satellite counts and Hafrok’s registers
Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations100 of 100≈100% · first seen 2024-05-22
Turbines100 of 100≈100% · first seen 2024-12-29
Latest count2026-08-29from 498 satellite passes · 1 substation platform left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (100 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
Installation contracts
FoundationsAeolus◇Van Oord · foundation and turbine installation vessel · 2024-05 → 2025-07 · Completed
TurbinesWind Peak◇Cadeler · foundation and turbine installation vessel · 2025-03 → 2026-06-10 · Completed
Offshore substationSleipnir◇Heerema · heavy-lift vessel · 2024-08 → 2024-08 · CompletedSatellite image
Image taken2026-09-07≈Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%≈the whole farm lies inside the image
Structures ringed101 confirmed · 0 not yet confirmed≈as counted on 2026-08-29 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Tyne ◆·foundations · draft 13.5 m
PortPort of Hull ◆turbines
PortPort of Blyth ◆offshore construction base
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (101)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary

Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemSofia HVDC·1320 MW · ±320 kV · under construction, expected 2026
Export & onshore
Export cableSofia Export Cable·HVDC subsea · 455 km · Prysmian · under construction · to Redcar, Teesside
Onshore connectionLackenby Substation (Dogger Bank C / Sofia connection)·400 kV · under construction · also serves Dogger Bank C
Converter supplierGE Vernova·Sofia HVDC · Seatrium Batam Yard, Batam, Indonesia (the CONSORTIUM partner Seatrium, formerly Sembcorp Marine, is Singapore-headquartered; the YARD is in Indonesia) · for National Grid ESO
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
Sources & verification
16/19 fields verified · rests on 25 sources (19 primary) · ◆ 21 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[14]
Planning Inspectorate / UK Government2015-08-04◆ Sofia Offshore Windfarm (Dogger Bank Tee…
“On 4 August 2015 the Secretary of State for Energy and Climate Change granted consent for the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015. Following the 2015 consent, Dogger Bank Teessi…”
supportsConsentConsent granted
[15]
BEIS / UK Government2019-09-20◆ Contracts for Difference (CfD) Allocatio…
“Sofia Offshore Wind Farm Phase 1: strike price £39.650/MWh (2012 prices), delivery year 2023/24, capacity awarded 1,400 MW, developer Sofia Offshore Wind Farm Limited.”
supportsMechanismStrike / priceDetailCfD · AR3
[19]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 6556: Site Name "Sofia (Teesside B)", Development Status "Under Construction", Installed Capacity 1400 MWelec, Operator "RWE Renewables UK Limited"”
supportsRegister entry
Operator15
[1]
RWE AG2021-03-24◆ RWE marks financial investment decision …
“RWE, one of the world's leading players in offshore wind, has taken the Financial Investment Decision on its 1.4 gigawatt (GW) flagship Sofia Offshore Wind Farm project. The 100% RWE-owned project rep…”
supportsoperatorConsentFinal investment decisionOnshore constructionOffshore construction+7 more
[2]
RWE AG2020-11-17◆ Power export cable preferred bidder anno…
“Prysmian Group is set to provide a turn-key high voltage submarine and land export cable connection for RWE Renewable's largest offshore wind project, 1.4 gigawatt (GW) Sofia Offshore Wind Farm sited …”
supportsStatusConnection point
[3]
RWE AG2020-12-10◆ RWE chooses Van Oord for foundations and…
“RWE has selected Van Oord as the preferred supplier for monopile foundations and array cables for Sofia Offshore Wind Farm. The 1.4 Gigawatt (GW) Sofia is sited on Dogger Bank in the central North Sea…”
supportsOnshore constructionOffshore constructionFoundationfoundationsturbines+1 more
[4]
RWE AG2023-09-04◆ Offshore construction in the North Sea b…
“Offshore construction has officially started at RWE's 1.4 gigawatt (GW) Sofia Offshore Wind Farm, to install essential subsea cable infrastructure from the UK's north east coast to the wind farm site …”
supportsOnshore constructionOffshore constructionDistance from shore
[5]
RWE AG2024-05-21◆ RWE installs first turbine foundation at…
“RWE has taken a huge step forward in delivering its flagship Sofia Offshore Wind Farm with the installation of the project's first offshore turbine foundation. EPCI contractor Van Oord is operating fo…”
supportsFoundationfoundationsturbinesoffshore construction base
[6]
RWE AG2024-08-29◆ RWE marks major milestone with installat…
“RWE has achieved a major milestone in the delivery of its flagship Sofia Offshore Wind Farm with the successful installation of the Offshore Converter Platform (OCP). The use of HVDC technology enable…”
supportsTotal capacityStatusConnection point
[7]
RWE AG2025-07-15◆ RWE reaches major construction milestone…
“All 100 steel monopile foundation structures have now been installed across the Sofia offshore array on Dogger Bank, 195 km off the north-east coast of the UK. The 1.4 gigawatts (GW) Sofia Offshore Wi…”
supportsTurbinesFoundationWater depthfoundationsturbines+2 more
[8]
RWE AG2025-03-17◆ RWE marks major construction milestones …
“RWE is celebrating significant progress in the construction of its 1.4 gigawatts (GW) Sofia offshore wind farm located on the Dogger Bank off the UK east coast. Wind turbine blades manufactured in Hul…”
supportsOnshore constructionOffshore constructionTurbinesModelUnit capacity+3 more
[9]
RWE AG2025-03-27◆ RWE celebrates next milestone for Sofia …
“The first turbine has been successfully installed at Sofia Offshore Wind Farm. The turbine installation vessel, Wind Peak, from Cadeler, arrived at the offshore site for the first time during the week…”
supportsOnshore constructionOffshore constructionTurbinesModelUnit capacity
[10]
RWE AG2025-11-10◆ RWE completes installation of all recycl…
“62 of the project's 100 Siemens Gamesa 14 megawatts (MW) wind turbines have now been installed. The project remains on track to reach commercial operation in September 2026. Sofia remains firmly on tr…”
supportsCommercial operationCOD historyTurbines
[12]
RWE AG2022-12-21◆ Back to the future – RWE picks Blyth for…
“RWE has signed up Port of Blyth as Offshore Construction Base for its 1.4 gigawatts (GW) Sofia Offshore Wind Farm. Located 195km off the UK coast on Dogger Bank, the new-build Offshore Construction Ba…”
supportsfoundationsturbinesoffshore construction base
[13]
RWE (sofiawindfarm.com)2025-03-17
“The turbine installation vessel the Wind Peak, manufactured by Cadeler, has arrived at the Port of Hull, where it has begun the first load-out of turbine components for the Sofia Offshore Wind Farm.”
supportsfoundationsturbinesoffshore construction base
[20]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000404: "Sofia Offshore Wind Farm", Status "Built", MW Connected 1320, Effective From n/a, Customer "SOFIA OFFSHORE WIND FARM LIMITED"”
supportsRegister entry
[21]
Cadeler A/S2026-06-12◆ Cadeler completes final turbine installa…
“Copenhagen, 12 June 2026 – Cadeler has completed the installation of all 100 wind turbines at the 1.4 GW Sofia Offshore Wind Farm in the UK North Sea. The installation of turbine number 100 marks the …”
supportsStatus note
[23]
Sofia Offshore Wind Farm (RWE)2026-06-11◆ Rwe completes installation of all turbin…
“RWE, a world leader in offshore wind, has successfully completed the installation of all 100 of its 14 megawatts (MW) turbines at the Sofia Offshore Wind Farm, marking a key milestone in the construct…”
supportsStatus note
OEM1
[11]
Siemens Gamesa2021-03-31◆ Sofia’s giant leap: Siemens Gamesa selec…
“Siemens Gamesa Renewable Energy (SGRE) has been awarded the firm order from RWE for the 1.4 GW Sofia offshore wind power project.”
supportsTurbinesModelUnit capacity
Record source2
[24]
Cadeler A/S2026-06-12◆ cadeler-completes-final-turbine-installa…
...e Wind Farm in the UK North Sea. The installation of turbine number 100 marks the completion of Cadeler's turbine installation campaign and Wind Peak's first installation project since her delivery…
supportsWind Peak — turbine installation
[25]
RWE2024-08-29◆ rwe-sofia-ocp-2024-08
The installation was carried out by Heerema, using its Sleipnir heavy lift vessel as a subcontractor to the GE Vernova/Seatrium consortium responsible for the OCP. The platform... weighing over 13,000…
supportsSleipnir — substation installation
Trade press4
[16]
offshoreWIND.biz2026-02-19
Press report — cited, not quoted; read it at the source link.
supportsCommercial operation
[17]
[18]
[22]
offshoreWIND.biz2026-06-13◆ All 100 siemens gamesa turbines in place…
Press report — cited, not quoted; read it at the source link.
supportsStatus note