Norfolk Boreas
Part of Norfolk Offshore Wind Zone. Located 50-80km off Norfolk coast. All permits obtained but economics dependent on CfD.
Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
RWE — 100% ◆Location
North Sea
Technology
Capacity
1,380 MW ◆
Turbines
—
Foundation
—
Site & conditions
Site rights
Seabed rights held ∴
Origination
Crown Estate Round 3 · 2010 ·
Water depth
26–37 m ≈
Wind speed
10.1 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
Applied ◆
Connection
Necton 400kV Substation — NESO TEC register entry at Scoping … ◆
Schedule
FID
Not taken
COD · Hafrok
2032 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2032
expected year of commercial operation
Chance of delivery
≈73%
estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. This one sits below that: its size and technical complexity. A secured offtake contract helps only slightly.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
| Year | Probability |
|---|---|
| 2031 | 14.1% |
| 2032 (expected) | 28.0% |
| 2033 | 22.7% |
| 2034 | 14.6% |
| 2035 | 8.7% |
| 2036 | 5.1% |
| 2037 | 3.1% |
| 2038 | 1.8% |
| 2039 | 1.1% |
| 2040 | 0.7% |
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in
2021. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of
2025; the faster quarter of similar projects would be done by 2023, the slower quarter not until 2026.3
Still needs an offtake award: UK-CFD-AR8
The project has no offtake contract yet. The next visible auction is around
2026 Q4; winners typically reach final investment decision about 2 years after an award (2028 Q4), then build time on top gives 2031 Q4. That is later than the milestone timing, so the auction sets the date.4
Result
Expected commercial operation
2032, likely range 2032–2033 (the middle half of outcomes for similar projects). The auction step above sets the date: the round has to be won before building can start.5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈73%, which rates it
Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2010-01
Crown Estate Round 3
- Awarded to
- East Anglia Offshore Wind Ltd (ScottishPower Renewables + Vattenfall)
- Zone
- Norfolk Bank (East Anglia) zone
- Basis
- seabed award
From the auction results — the round that created the project.
Portfolio sale · 2023-12
Vattenfall → RWE 100%
- Stake
- 100%
- Consideration
- not disclosed
- Announced
- 2023-12
- Closed
- 2024-03
- Project stage
- consented
Part of the GBP 963m (EUR ~1,107m) Norfolk Offshore Wind Zone portfolio sale. Boreas had been paused by Vattenfall in July 2023 after costs rose ~40%, making the AR4 CfD strike price of GBP 37.35/MWh uneconomic. RWE restarted development after acquisition. Per-project value not disclosed. (GBP 1,025m ~ EUR 1,199m @ GBP/EUR 0.8552 2024-03 ECB avg.)
Evidence
- group.vattenfall.com — Vattenfall and RWE conclude sale of Norfolk Offshore Wind Zone ↗ 2023-12 ◆ held
- Vattenfall — Vattenfall — q1 report 2024 ↗ 2024-Q1 ◆ held
From Hafrok’s transactions record
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Revenue & offtake route to market — open
No offtake secured — route to market open
CfD · AR4 awarded 2022-07, terminated. No live offtake on record. ◇
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
CfD allocation round
The UK's principal route — a 15-year, CPI-indexed, two-sided CfD awarded in annual competitive rounds.
Next visible round · from the auction calendar
CfD Allocation Round 8 ◇
AR8 confirmed (gov update, Mar 2026) to OPEN July 2026 — brought forward from the earlier mid/late-2026 expectation
Corporate PPA
Bilateral long-term offtake with corporate buyers; can cover part of output alongside or ahead of a CfD.
Merchant
Uncontracted sale into the wholesale market — no price floor, full exposure to power prices.
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operationnot stated
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemNorfolk Boreas HVDC·1400 MW · ±320 kV · planned, expected 2030
Export & onshore
Onshore connectionNecton Converter Station (Norfolk Vanguard / Boreas)·400 kV · planning · also serves Norfolk Vanguard East, Norfolk Vanguard West
Converter supplierSiemens Energy·Norfolk Boreas HVDC · TBD · for National Grid ESO
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
Sources & verification
5/11 fields verified · rests on 15 sources (8 primary) · ◆ 11 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[4]
UK Government (legislation.gov.uk)2021-12-10◆ The Norfolk Boreas Offshore Wind Farm Or…
“The Norfolk Boreas Offshore Wind Farm Order 2021 — grants development consent for, and authorises Norfolk Boreas Limited to construct, operate and maintain a generating station located in the North Se…”
supportsConsentConsent granted
[13]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 6483: Site Name "The East Anglia Array - Norfolk Boreas", Development Status "Under Construction", Installed Capacity 1400 MWelec, Operator "RWE Renewables UK L…”
supportsRegister entry
Operator5
[3]
NESO2026-06-12◆ NESO Transmission Entry Capacity (TEC) R…
“Norfolk Boreas,NORFOLK BOREAS LIMITED,Necton 400kV Substation,2,0,920,1320,31/12/2030,Scoping,Direct Connection,NGET,Wind Offshore,a1f8e0000015WV0AAM,PRO-000399-2,”
supportsStatusConnection point
[5]
RWE (norfolkzone.rwe.com)2026-06-15◆ About Vanguard West, East & Boreas Offsh…
“Each project is designed to have a capacity of 1.4 gigawatts (GW). The project has received its Development Consent Order (DCO), awarded to Norfolk Boreas Offshore Wind Farm by the Secretary of State …”
supportsTotal capacity
[6]
RWE Offshore Wind GmbH2024-03-27◆ RWE expands its UK offshore wind develop…
“Norfolk Vanguard West, Norfolk Vanguard East and Norfolk Boreas — each with a planned capacity of 1.4 gigawatts (GW). RWE will work on securing preferred supplier agreements for all key components for…”
supportsTotal capacity
[14]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000399-1: "Norfolk Boreas", Status "Awaiting Consents", MW Connected 0, Effective From 2029-10-01, Customer "NORFOLK BOREAS LIMITED"; PRO-000399-2: "Norfo…”
supportsRegister entry
[15]
RWE2026-08◆ RWE — RWE Factbook 2026
“Boreas6
UK, 1,380 MW1 ... 6 Formerly known as Norfolk Boreas”
supportsTotal capacity
Auction results1
[17]
BEIS (gov.uk)2022-07◆ cfd-ar4-results-2022
Offshore Wind (Pot 3) cleared GBP 37.35, delivery 2026/27: Inch Cape Phase 1 1,080.00 MW; EA3 Phase 1 1,372.34 MW; Norfolk Boreas Phase 1 1,396.00 MW; Hornsea Project Three 2,852.00 MW; Moray West 294…
supportsOfftake history
Auction pipeline1
[18]
DESNZ (gov.uk)2026◆ govuk-cfd-ar8
gov.uk AR8 collection — Allocation Framework, statutory framework and CIB documents published ahead of the round.
supportsCfD Allocation Round 8
Trade press5
[8]
offshoreWIND.biz2026-01◆ Global Investor Joining RWE on Two Norfo…
Press report — cited, not quoted; read it at the source link.
supportsoperator
[9]
[10]
[11]
[12]
Unverified import1
[1]