Morgan

Crown Estate Round 4. Combined Morgan and Mona capacity was 3GW. Turbine tip height up to 364m.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

on hold — no credible date; the chart shows when a restarted project might complete
The developer's last guidance was 2031 · not treated as a schedule while the project is on hold
Chance of delivery
≈13% estimated chance this project reaches commercial operation
Projects put on hold complete ≈15% of the time on Hafrok's record. This one sits below that: a very large build, technical complexity and no offtake contract yet. Only a restart would change that — there is no dated schedule to judge against.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2030: 20.0% (conditional on completion) 2031: 20.0% (conditional on completion) 2032: 20.0% (conditional on completion) 2033: 20.0% (conditional on completion) 2034: 20.0% (conditional on completion)2026now20272028202920302031203220332034 Developer-announced COD: 2031 ANNOUNCED 2031
COD probability by year, conditional on completion
YearProbability
203020.0%
203120.0%
203220.0%
203320.0%
203420.0%
How Hafrok got this date
1
On hold — no dated schedule
The project is recorded as On Hold, so no sequence of milestones can be trusted. Hafrok publishes no expected year; the chart instead spreads the remaining chance of completion over the years a restarted project might finish in.
2
Chance of delivery — separate from timing
Start from the share of On Hold projects that went on to complete — ≈15%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Historically only a minority of projects put on hold returned to delivery — the estimate reflects that. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈13%, which rates it Fragile on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2021’22’23’24’25’26’27’28’29’30’31Developer-announced COD: 2031 announced COD 2031Crown Estate Round 4 — awarded to Consortium of EnBW and BPCrown Estate Round 4 Feb 2021 · auction recordView the source for Consent grantedConsent granted 29 Aug 2025 Crown Estate Round 4 — awarded to Consortium of EnBW and BP 2021-02 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDJERA Nex bp / EnBW (Morgan Offshore Wind Limited) → None — 100% 2026-01 DIVESTMENTTODAYBP BP BP not among today’s recorded owners — no sale recordedEnBW — 50% today · partner EnBW EnBW 50%JERA Nex bp — 50% today · operator JERA Nex bp JERA Nex bp 50%Crown Estate Round 4 — awarded to Consortium of EnBW and BP Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
CfD allocation round
The UK's principal route — a 15-year, CPI-indexed, two-sided CfD awarded in annual competitive rounds.
Next visible round · from the auction calendar
CfD Allocation Round 8
expected H2 2026 · scheduled · the round’s published documents do not name this project
AR8 confirmed (gov update, Mar 2026) to OPEN July 2026 — brought forward from the earlier mid/late-2026 expectation
Corporate PPA
Bilateral long-term offtake with corporate buyers; can cover part of output alongside or ahead of a CfD.
Merchant
Uncontracted sale into the wholesale market — no price floor, full exposure to power prices.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageOn Hold
Offshore constructionnot started
Expected start of operation2031
Construction ports
PortBelfast Harbour D1 Terminal ·quay 500 m · crane 840 t · draft 10 m

Sources & verification

3/17 fields verified · rests on 12 sources (6 primary) · ◆ 8 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
Planning Inspectorate (PINS)2025-08-29◆ Morgan Offshore Wind Project: Generation…
“Morgan Offshore Wind Project: Generation Assets ... Applicant: Morgan Offshore Wind Limited ... Decision: Granted ... Date: 29 August 2025 ... Irish Sea, positioned 22.22 km from the Isle of Man and 3…”
supportsConsentConsent granted
[8]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 10919: Site Name "Morgan Offshore Wind Farm", Development Status "Awaiting Construction", Installed Capacity 1500 MWelec, Operator "BP Oil UK Limited / ENBW UK …”
supportsRegister entry
[11]
The Planning Inspectorate (PINS)2026-08-23◆ PINS national infrastructure application…
“Project reference EN010136: "Morgan Offshore Wind Project: Generation Assets"; applicant "Morgan Offshore Wind Limited"; Stage "Post-decision"; anticipated submission April 2024; applied 2024-04-24; a…”
supportsRegister entry
Operator4
[6]
NESO2026-06-12◆ NESO Transmission Entry Capacity (TEC) R…
“Morgan Offshore Wind Farm,Morgan Offshore Wind Limited,Penwortham 400kV Substation,,0,1500,1500,30/11/2029,Scoping,Direct Connection,NGET,Wind Offshore,a1f4L000000EH8dQAG,PRO-001594,”
supportsStatusConnection point
[9]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-001594: "Morgan Offshore Wind Farm", Status "Scoping", MW Connected 0, Effective From 2029-11-30, Customer "Morgan Offshore Wind Limited"”
supportsRegister entry
[12]
The Crown Estate2026-07-24◆ The Crown Estate launches accelerated te…
“The Crown Estate has today launched a competitive tender process to secure a new developer to build and operate the up to 1.5GW Morgan wind farm in the Irish Sea. Following the previous developer's de…”
supportsSite rights
[13]
JERA Co., Inc.2025-08-04
"JERA and bp have completed the formation of JERA Nex bp, a new standalone, equally owned joint venture," with the transaction completed on August 1, 2025. The JV is "50:50-owned" by JERA and bp.
supports↳ parent
Auction pipeline1
[14]
DESNZ (gov.uk)2026◆ govuk-cfd-ar8
gov.uk AR8 collection — Allocation Framework, statutory framework and CIB documents published ahead of the round.
supportsCfD Allocation Round 8
Trade press4
[2]
Offshore Wind Biz2025-09-03
Press report — cited, not quoted; read it at the source link.
supportsTurbinesTotal capacityFoundation
[3]
Offshore Wind Biz2026-01-19◆ JERA Nex BP Acquires Full Ownership of M…
Press report — cited, not quoted; read it at the source link.
supportsoperatorpartnerCommercial operation
[5]
NS Energy Business
Press report — cited, not quoted; read it at the source link.
supportsModelUnit capacityWater depthDistance from shoreCoordinates
[7]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed