London Array

Located in Outer Thames Estuary. Phase 2 cancelled due to bird migration concerns. Round 2 development.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2004’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 2 — awarded to (London Array Ltd — E.ON / RWE / Masdar / La Caisse)Crown Estate Round 2 Dec 2003 · auction recordView the source for Consent grantedConsent granted Dec 2006 View the source for Final investment decisionFinal investment decision May 2009 View the sources for Onshore constructionOnshore construction Jul 2009 View the sources for Offshore constructionOffshore construction Mar 2011 View the source for First powerFirst power Oct 2012 View the source for Commercial operationCommercial operation Apr 2013 Crown Estate Round 2 — awarded to (London Array Ltd — E.ON / RWE / Masdar / La Caisse) 2003-12 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDØrsted → CDPQ — 25% · €799m · closed 2014-06 2014-01 FARMDOWNØrsted → Schroders Greencoat — 25% · €829m · closed 2023-08 2023-07 DIVESTMENTTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAY(London Array Ltd — E.ON / RWE / Masdar / La Caisse) not among today’s recorded owners — no sale recordedØrsted Ørsted Ørsted exited 2023-07CDPQ — 25% today CDPQ CDPQ 25%Schroders Greencoat Schroders Greencoat Schroders Greencoat exited 2023-07RWE — 30% today · operator RWE RWE 30%Greencoat UK Wind — 25% today Greencoat UK Wind Greencoat UK Wind 25%Masdar — 20% today Masdar Masdar 20%Crown Estate Round 2 — awarded to (London Array Ltd — E.ON / RWE / Masdar / La Caisse) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Ørsted → CDPQ — 25% · €799m · closed 2014-06 25%Ørsted → Schroders Greencoat — 25% · €829m · closed 2023-08 25%Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2013-Q22013-04 · 2 recorded revisions · held (announced 2013-Q2, unchanged)

Revenue & offtake the regime the project was built under

Offtake regime on record
RegimeRenewables Obligation: 2 ROCs/MWh reported (offshore wind banding under Renewables Obligation Order 2009, accredited 2013). Rate not yet verified against the Ofgem RO accreditation register — unsourced pending vault of that record.
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite survey
the farm as it stands, counted from satellite radar images · built before the count began, so there is no build to chart
Satellite survey
Structures standing177175 turbines + 1 platform expected · 1 more than expected — a met mast, a platform not on the register, or a position the survey missed
Surveyed2026-09-01from 117 satellite passes
Built2011-03 → 2013-04offshore construction to start of operation, from the record
Hafrok counts the structures standing in the sea from satellite radar images (≈) and reads the count against the turbines and platforms on record. The farm was built before this count began, so the images show it complete; they cannot date its construction. Rows marked with a dot (·) come from Hafrok’s own registers.
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed177 confirmed · 0 not yet confirmedas counted on 2026-09-01 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Ramsgate operations base
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (177)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over London Array, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationLondon Array offshore substations (2, described collectively)·33/150 kV · owner Blue Transmission London Array Limited (OFTO)

Sources & verification

16/18 fields verified · rests on 12 sources (10 primary) · ◆ 10 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[12]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2511: Site Name "London Array Phase 1", Development Status "Operational", Installed Capacity 630 MWelec, Operator "Siemens Gamesa Renewable Energy"”
supportsRegister entry
Operator7
[1]
London Array Limited2025◆ Key Facts – London Array
"Offshore consent granted...in December 2006. Onshore planning permission...August 2007. Phase One formal approval...May 2009. Shareholder investment announced: €2.2 billion. Onshore substation ground…
supportsConsentFinal investment decisionOnshore constructionOffshore constructionCommercial operation+10 more
[2]
London Array Limited2025◆ Our Shareholders
“RWE Renewables London Array Limited – 30% project share. La Caisse – 25% project share. Greencoat UK Wind PLC – 25% project share. Masdar Energy UK Limited – 20% project share.”
supportsowner
[3]
RWE AG2022-02-21◆ RWE to take on operations, service & mai…
“Following a competitive tender process RWE has been successful in winning the operations, service & maintenance contract at the 175 turbine, 630MW London Array Offshore Wind Farm. This has been conduc…”
supportsTurbinesTotal capacityDistance from shoreoperations base
[5]
London Array Limited2013-07-04◆ Inauguration – London Array
“Orsted, E.ON and Masdar today, (4 July 2013) officially opened the worlds largest offshore wind farm, London Array”
supportsBackground
[7]
London Array Limited2012-10-29◆ World’s largest offshore wind farm gener…
"29/10/12. 630MW scheme. 175 turbines. under construction since March 2011." ... DONG Energy, E.ON and Masdar today (29/10/12) announced that the first power had been produced at the London Array Offs…
supportsFirst power
[9]
RWE AG2023-11-21◆ London Array offshore wind farm 10 years…
“Located 20km off the north Kent coast in the Outer Thames Estuary, RWE-operated London Array has a 630MW capacity. London Array was the world's largest offshore wind farm when commissioned in 2013. Ap…”
supportsTotal capacity
[13]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000201: "London Array Offshore Wind Farm", Status "Built", MW Connected 630, Effective From n/a, Customer "LONDON ARRAY LIMITED"”
supportsRegister entry
Financier1
[6]
Mubadala Investment Company2013-07-04◆ Prime Minister David Cameron inaugurates…
“DONG Energy, E.ON and Masdar today, (4 July 2013) officially opened the world's largest offshore wind farm, London Array, at a ceremony attended by Prime Minster David Cameron, alongside other dignita…”
supportsOnshore constructionOffshore constructionTurbinesUnit capacityTotal capacity
Trade press3
[8]
NS Energy Business2024
Press report — cited, not quoted; read it at the source link.
supportsModelUnit capacityFoundation
[10]
London Array2025◆ Our Shareholders
supportsoperatorowner
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed