Inch Cape
Located ~15 km off the Angus coast in the Outer Firth of Tay, Scotland.
Status
Under Constructionlifecycle stage
DeliveringHafrok completion outlook
Ownership
ESB — 50% ◆RRRed Rock Renewables — 50% ◆
Location
North Sea
Technology
Capacity
1,080 MW ◆
Turbines
72 × 15 MW ◆
Model
Vestas V236 15-0 ◆
Foundation
Jacket+Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Water depth
34–64 m ◆
Distance from shore
15 km ◆
Wind speed
10.0 m/s @ 150 m ≈
Revenue & grid
Offtake
CfD · AR4 · £37.35/MWh ◆
Grid
Secured ◆
Connection
Cockenzie, East Lothian — new 220/275kV onshore substation … ◆
Schedule
FID
27 Jan 2025 ◆
COD · announced
2027 ◆
COD · Hafrok
2027 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2027
expected year of commercial operation
Chance of delivery
≈98%
estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
| Year | Probability |
|---|---|
| 2027 (expected) | 86.7% |
| 2028 | 13.3% |
| Stated | Announced COD |
|---|---|
| 2026-06-03 | 2027 (held since 2024-12-13, 4 statements) |
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in
2023. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of
2025; the faster quarter of similar projects would be done by 2024, the slower quarter not until 2026. Dates already in the past are moved up to today — this project has run beyond the typical timing.3
Result
Expected commercial operation
2027, likely range 2025–2027 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it
Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
JV entry · 2020-11
Red Rock Power (SDIC Power) → ESB 50%
- Stake
- 50%
- Consideration
- not disclosed
- Announced
- 2020-11
- Project stage
- consented
ESB (Irish state utility) acquired a 50% stake in Inch Cape Offshore Limited from Red Rock Power (owned by China's SDIC Power since 2016), establishing a 50:50 joint venture. Total project development cost estimated at EUR ~3bn at that time. Deal value not publicly disclosed. Project subsequently won CfD in AR4 (July 2022).
Evidence
- power-technology.com — Irish energy group ESB acquires 50% stake in Inch Cape offshore wind farm ↗ 2020-11 ◆ held
From Hafrok’s transactions record
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: held (announced 2027, unchanged) · the full guidance history is in the delivery chart above
Revenue & offtake contract duration and price levels · money of the day
CfD-backed — 2 allocation rounds
● CfD · AR4
Price£37.35/MWh ·Basis2012 real · CPI-indexed
Capacity1,080 MWAwardedJul 2022Term15 yrs · delivery 2026/27
● CfD · AR6
Price£54.23/MWh ·Basis2012 real · CPI-indexed
Capacity266.11 MWAwardedSep 2024Term15 yrs · delivery 2027/28
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-07, then an assumed +2.0%/yr (central-bank target). Cfd terms run 15 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR4CfD · AR6
Installation how the build is going · from satellite counts and Hafrok’s registers
Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations53 of 72≈74% · first seen 2025-12-27
Turbinesnone yet≈0 of 72
Latest count2026-08-31from 281 satellite passes · 1 substation platform left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (72 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
Installation contracts
FoundationsLes Alizés◇Jan De Nul · foundation installation vessel · 2025-12 → 2026-06 · Completed
FoundationsSeaway Alfa Lift◇Seaway7 · foundation installation vessel · 2026 → · Underway
TurbinesWind Mover◇Cadeler · turbine installation vessel · 2026-Q4 · Contracted
Offshore substationSleipnir◇Heerema · heavy-lift vessel · 2025-08 → 2025-08 · CompletedSatellite image
Image taken2026-09-07≈Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered100%≈the whole farm lies inside the image
Structures ringed54 confirmed · 0 not yet confirmed≈as counted on 2026-08-31 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Dundee ◆turbines
PortPort of Leith ◆foundations
PortPort of Montrose ◆operations base
PortPort of Blyth ◆cables
PortWallsend (Smulders yard ◆fabrication
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (54)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary

Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationInch Cape Offshore Substation Platform (Siemens Energy OTM)·under construction · owner Inch Cape Offshore Wind Limited (ESB 50% / Red Rock Renewables 50%)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
Sources & verification
18/19 fields verified · rests on 30 sources (32 primary) · ◆ 24 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator6
[1]
Marine Scotland (Scottish Government)2019-06-17◆ Section 36 Consent - Construction and Op…
“Decision Notice and Section 36A Declaration both issued on 17 June 2019 for the construction and operation of Inch Cape Offshore Windfarm, Firth of Forth. ... Section 36 Consent - Construction and Ope…”
supportsConsentConsent granted
[3]
BEIS (UK Government)2022-07-07◆ Contracts for Difference Allocation Roun…
“Inch Cape Offshore Limited — 1,080 MW at £37.35/MWh (2012 prices), Allocation Round 4.”
supportsMechanismStrike / priceDetailCfD · AR4
[4]
DESNZ (UK Government)2024-09-03◆ Contracts for Difference Allocation Roun…
“Inch Cape Offshore Limited — 266 MW at £54.23/MWh, rebid capacity (previously awarded in AR4), Allocation Round 6.”
supportsMechanismStrike / priceDetailCfD · AR6
[16]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2527: Site Name "Inch Cape", Development Status "Awaiting Construction", Installed Capacity 1080 MWelec, Operator "Red Rock Power (ICOL)"”
supportsRegister entry
[18]
Department for Energy Security and Net Zero2026-08-03◆ Renewable Energy Planning Database (REPD…
“REPD Q2 2026 quarterly extract — Ref ID 2527: Site Name "Inch Cape", Development Status "Under Construction", Installed Capacity 1080 MWelec, Operator "Red Rock Power (ICOL)", Record Last Updated 08/0…”
supportsRegister entry
[32]
Scottish Government Marine Directorate (MD-LOT)2026-08-23◆ Scottish MD-LOT marine projects register…
“Register row "Inch Cape Offshore Windfarm" (key ml/inch-cape-offshore-windfarm): Application stage "Post-consent", type "Renewables - Wind". Register row "Inch Cape Offshore Windfarm (Revised Design)"…”
supportsRegister entry
Operator16
[2]
Inch Cape Offshore Limited2025-01-27◆ Scottish flagship offshore wind project …
“The equal joint owners of Inch Cape Offshore Wind Farm, ESB and Red Rock Renewables, announced today that the flagship Scottish project has reached financial close raising more than £3.5 billion of fu…”
supportsFinal investment decisionFirst powerCommercial operationStatusConnection point
[6]
Inch Cape Offshore Limited2026-06-04
“Inch Cape Offshore Wind Farm is owned by Inch Cape Offshore Limited, an equal joint venture between Edinburgh-based renewable and sustainable energy company, Red Rock Renewables and Ireland's leading …”
supportsTurbinesTotal capacityFoundationWater depthDistance from shore
[7]
Inch Cape Offshore Limited2026-04-14
“the project's 72 turbines will be marshalled from the port laydown area [Port of Dundee]. Port of Leith is the most prominent contributor with the ongoing marshalling and completion activity for the p…”
supportsturbinesoperations base
[15]
Inch Cape Offshore Limited2026-06-03◆ All monopiles installed at Scotland's In…
“The project is on track for first power in late-2026 and full commercial operations in 2027.”
supportsCOD historyLes Alizés — foundation installation
[17]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000348: "Inch Cape Offshore Wind Farm Platform 1", Status "Consents Approved", MW Connected 0, Effective From 2026-02-21, Customer "INCH CAPE OFFSHORE LIM…”
supportsRegister entry
[19]
National Energy System Operator (NESO)2026-08-14◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 14 August 2026 — PRO-000348: "Inch Cape Offshore Wind Farm Platform 1", Status "Consents Approved", MW Increase 540.00, MW Effective From 2026-02-21, Gate "2"; PRO-000349: "…”
supportsRegister entry
[20]
Inch Cape Offshore Limited2026-08-06◆ Transition piece installation at Inch Ca…
“Installation of all 54 monopile transition pieces at Inch Cape Offshore Wind Farm is now complete, marking another key step in the Scottish project’s offshore construction. The milestone comes just tw…”
supportsSeaway Alfa Lift — foundation installation
[21]
Inch Cape Offshore Limited2026-08-17◆ Inch Cape focus turns to Dundee and turb…
“Prior to installation, Forth Ports’ Port of Dundee will host the components of the project’s 72 wind turbine generators which will each comprise a four-section tower, three 115.5-metre-long blades and…”
supportsWind Mover — turbine installation
[23]
Inch Cape Offshore Limited2025-08-27◆ First section of export cable sets sail …
“The initial 28-kilometre section of Inch Cape’s first export cable sailed out from the Port of Blyth last night en route to its installation location off the Scottish coast.”
supportsOnshore constructionOffshore constructionSite rights
[24]
Inch Cape Offshore Limited2025-08-04◆ Offshore substation installed at inch ca…
“The Inch Cape Offshore Wind Farm offshore jacket foundation and substation platform have been successfully installed at the North Sea site of this flagship 1.1 gigawatt Scottish project. The Siemens E…”
supportsOnshore constructionOffshore constructionSite rights
[27]
Inch Cape Offshore Limited2026-02-24◆ Inch cape boosts uk jobs supply chain ec…
“The flagship Scottish project is under construction with visible activity and a team of more than 100 working at the Port of Leith, ongoing work on its substation at Cockenzie, a new operations facili…”
supportsturbinesfoundationsoperations basecablesfabrication
[28]
Inch Cape Offshore Limited2023-11-20◆ Inch cape offshore substation assembly a…
“The assembly and fit-out of the offshore substation platform and jacket foundation for the 1.1 gigawatt (GW) Inch Cape Offshore Wind has now kicked off at the Smulders yard in Wallsend, Newcastle. A c…”
supportsturbinesfoundationsoperations basecablesfabrication
[29]
Inch Cape Offshore Limited2025-10-23◆ First offshore export cable installed at…
“The 220 kV, three-phase export cable was installed in three 28-kilometre sections by Enshore Subsea using the CMOS Installer cable lay vessel operating from the Port of Blyth.”
supportsturbinesfoundationsoperations basecablesfabrication
[30]
Inch Cape Offshore Limited2022-02-07◆ Inch cape selects montrose port as offsh…
“Inch Cape Offshore Limited has selected Montrose Port as the future operations and maintenance base for its offshore wind farm – which will see up to 72 turbines located 15 km off the Angus coast.”
supportsturbinesfoundationsoperations basecablesfabrication
[31]
Inch Cape Offshore Limited2024-12-12◆ Forth ports to invest 50 million in leit…
“Forth Ports, the UK's third largest port operator, has announced a £50 million private investment in infrastructure at the Port of Leith having secured its largest ever offshore wind contract, the del…”
supportsturbinesfoundationsoperations basecablesfabrication
[35]
Inch Cape Offshore Limited2022-09-28◆ Inch cape offshore limited selects vesta…
“Inch Cape Offshore Limited, the joint venture between Red Rock Power Limited (RRPL) and ESB, has appointed Vestas as the preferred wind turbine supplier for the 1.1 GW Inch Cape Offshore Wind Farm. Th…”
supportsTurbinesModelUnit capacityturbinesfoundations+3 more
OEM1
[9]
Vestas2024-12-13◆ Vestas wins 1.1 GW order for the Inch Ca…
“Vestas has secured a firm and unconditional order for the 1.1 GW Inch Cape Offshore Wind project in Scotland from Inch Cape Offshore Limited, an equal joint venture between ESB and Red Rock Renewables…”
supportsTurbinesModelUnit capacity
Record source1
[41]
Inch Cape Offshore Limited2025-08-04◆ inchcape-oss-installed-2025-08
The Siemens Energy Offshore Transformer Module (OTM) and its 68-metre jacket foundation are now in position 21 kilometres from the Angus coast having been installed by Heerema Marine Contractors (HMC)…
supportsSleipnir — substation installation
Trade press6
[8]
Forth Ports2025-10-15
“The first eight XXL monopile foundations were transported by a heavy transport vessel which docked at the recently-opened deep water riverside Charles Hammond Berth [Port of Leith].”
supportsfoundations
[12]
[13]
East Lothian Courier2024-11-07
“Work has been under way on the construction of the project's substation since early 2023.”
supportsOnshore constructionOffshore constructionSite rights
[14]
[22]
Inch Cape Offshore Limited2021-01-27◆ Public Notice of Application – Variation…
“offshore generating station known as Inch Cape Offshore Wind Farm, located 15-22km east off Angus coastline with a total area of 150km 2 (central latitude and longitude co-ordinates: 56 o 49.457’N 2…”
supportsCoordinates
[40]
Inch Cape Offshore Limited2020-11-09◆ Red Rock Power forms new Inch Cape joint…
“Edinburgh-based Red Rock Power Limited has formed a 50:50 joint venture with ESB, the leading Irish energy group, for Inch Cape Offshore Limited and its offshore wind farm development.”
supportsoperatorowner