Humber Gateway

Located 8km east of Spurn Point, East Yorkshire.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2004’05’06’07’08’09’10’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26Crown Estate Round 2 — awarded to E.ON / RWECrown Estate Round 2 Dec 2003 · auction recordView the source for Consent grantedConsent granted Feb 2011 View the source for Onshore constructionOnshore construction 2012 View the source for Offshore constructionOffshore construction 2013 View the source for First powerFirst power Feb 2015 View the source for Commercial operationCommercial operation 2015-Q3 Crown Estate Round 2 — awarded to E.ON / RWE 2003-12 ORIGINATIONE.ON → RWE — 100% · closed 2019-10 2018-03 MERGERRWE → Schroders Greencoat — 49% · €726m · closed 2020-12 2020-11 FARMDOWNTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYE.ON E.ON E.ON not among today’s recorded owners — no sale recordedRWE — 51% today · operator RWE RWE 51%Schroders Greencoat Schroders Greencoat Schroders Greencoat exited 2020-11Greencoat UK Wind — 37.8% today Greencoat UK Wind Greencoat UK Wind 37.8%Greencoat Renewable Income — 11.2% today Greencoat Renewable Inc… Greencoat Renewable Inc… 11.2%Crown Estate Round 2 — awarded to E.ON / RWE E.ON → RWE — 100% · closed 2019-10 100%RWE → Schroders Greencoat — 49% · €726m · closed 2020-12 49%Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2015-Q22015-Q3 · 2 recorded revisions · held (announced 2015-Q2, unchanged)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite survey
the farm as it stands, counted from satellite radar images · built before the count began, so there is no build to chart
Satellite survey
Structures standing7473 turbines + 1 platform expected · every expected structure seen
Surveyed2026-09-01from 90 satellite passes
Built2013 → 2015-Q3offshore construction to start of operation, from the record
Hafrok counts the structures standing in the sea from satellite radar images (≈) and reads the count against the turbines and platforms on record. The farm was built before this count began, so the images show it complete; they cannot date its construction. Rows marked with a dot (·) come from Hafrok’s own registers.
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed74 confirmed · 0 not yet confirmedas counted on 2026-09-01 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Grimsby (Fish Docks) operations and maintenance
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (74)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Humber Gateway, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationHumber Gateway Offshore Substation·132 kV · in service 2015 · owner Humber Gateway OFTO (Balfour Beatty Investments / Equitix consortium)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
201520162017201820192020202120222023202420252026developer’s stated start 2015-Q3nowHumber Gateway Offshore SubstationHumber Gateway Offshore Substationin service 2015in service 2015

Sources & verification

17/18 fields verified · rests on 10 sources (6 primary) · ◆ 8 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[4]
Department of Energy and Climate Change (DECC)2011-02-09◆ Humber Gateway offshore wind farm given …
“Humber Gateway offshore wind farm given go-ahead ... The Yorkshire and Humber region could benefit from jobs and investment as E.ON was granted permission to construct a 230MW wind farm off the”
supportsConsentConsent granted
[10]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2544: Site Name "Humber Gateway A", Development Status "Operational", Installed Capacity 219 MWelec, Operator "E.ON Humber Wind Ltd/ Balfour Beatty Investments …”
supportsRegister entry
Operator4
[1]
RWE AG2025-10-01◆ RWE marks a decade of clean power and re…
“Humber Gateway's 73 turbines can collectively generate up to 219 megawatts (MW) of electricity, enough to power up to 199,000 typical UK homes. The wind farm was officially opened by Andrea Leadsom MP…”
supportsFinal investment decisionTurbinesUnit capacityTotal capacityDistance from shore+2 more
[3]
RWE AG2020-12-15◆ Power Purchase Agreement signed for Humb…
“RWE Renewables signed a Power Purchase Agreement (PPA) with E.ON UK under which the company will offtake 100% of the electricity produced by the Humber Gateway Offshore Wind Farm from 2022 until 2035.…”
supportsMechanismDetail
[7]
RWE2020-11◆ RWE to divest a 49% stake in the UK Humb…
supportsoperatorowner
[11]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000214: "Humber Gateway Offshore Wind Farm", Status "Built", MW Connected 220, Effective From n/a, Customer "RWE RENEWABLES UK HUMBER WIND LIMITED"”
supportsRegister entry
Trade press4
[5]
Power Technology2015◆ Humber Gateway Offshore Wind Farm, East …
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore constructionFoundationStatusConnection point+1 more
[6]
Power Technology2025◆ Power plant profile: Humber Gateway, UK
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationCOD historyTurbinesModelUnit capacity+1 more
[8]
E.ON UK (via windfair.net)2015-08-06
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[9]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed