Gunfleet Sands

Gunfleet Sands 1 (30 turbines) and Gunfleet Sands 2 (18 turbines), combined 172.8 MW.

Status
Operationallifecycle stage
Ownership
Ørsted — 50.1% ◆
JNJERA Nex bp — 24.95% ◆
JERA — 50% (12.47% net) ◆
BP — 50% (12.47% net) ◆
DBDevelopment Bank of Japan — 24.95% ◆
Location
United Kingdom
North Sea
Technology
Capacity 172.8 MW ◆ Turbines 48 × 3.6 MW ◆ Model Siemens Swt 3-6-107 ◆ Foundation Monopile ◆
Site & conditions
Site rights Seabed rights held ∴
Origination Crown Estate Round 1 · 2001 ·
Water depth 2–15 m ◆ Distance from shore 7 km ◆ Wind speed 9.0 m/s @ 100 m ≈
Revenue & grid
Offtake Other ◆ Grid Secured ◆ Connection Clacton substation (132 kV), Essex; export cable lands at … ◆
Schedule
FID 2007 ∅
COD 2010-Q2 ◆

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

6 dated milestones on the spine, each with its source · 4 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 14 sources (13 primary) · ◆ 8 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
legislation.gov.uk2004-03-25◆ The Gunfleet Sands Offshore Wind Farm Or…
“The works which the undertaker is authorised to construct and maintain by article 3(1) are the following works on or near Gunfleet Sands, off the coast near Clacton-on-Sea, Essex: (a) up to 30 wind tu…”
supportsConsentConsent granted
[13]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 2489: Site Name "Gunfleet Sands II", Development Status "Operational", Installed Capacity 64.8 MWelec, Operator "Orsted (formerly Dong Energy)"; Ref ID 2490: Si…”
supportsRegister entry
Operator5
[2]
Ørsted2019-05◆ 190514 Gunfleet Sands Web Aw
"The Gunfleet Sands Offshore Wind Farm is located approximately 7 km (4.3 miles) south-east of Clacton-on-Sea, Essex. The project consists of three phases: Gunfleet Sands 1, with 30 3.6 MW turbines; G…
supportsCommercial operationCOD historyTurbinesUnit capacityTotal capacity+2 more
[11]
JERA2025
“Investors: JERA Nex bp, Ørsted A/S, Development Bank of Japan”
supportsoperatorowner
[14]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-000224: "Gunfleet Sands Offshore Wind Farm", Status "Built", MW Connected 99.9, Effective From n/a, Customer "GUNFLEET SANDS LIMITED"; PRO-000229: "Gunfle…”
supportsRegister entry
[19]
Ørsted (investor news via Nasdaq)2026-10-12◆ Ørsted to take full ownership of Gunflee…
“Ørsted has exercised a long-standing buyback right in relation to the Gunfleet Sands 1 & 2 Offshore Wind Farm, in which Ørsted currently holds a 50.1 % ownership interest. Under the agreement, Ørsted …”
supportsStatus note
[22]
JERA Co., Inc.2025-08-04
"JERA and bp have completed the formation of JERA Nex bp, a new standalone, equally owned joint venture," with the transaction completed on August 1, 2025. The JV is "50:50-owned" by JERA and bp.
supports↳ parent
Trade press7
[3]
Power Technology (GlobalData)
Press report — cited, not quoted; read it at the source link.
supportsFirst powerTurbinesModelUnit capacityFoundation+1 more
[4]
Offshore Wind (4C Offshore)2013-12-27◆ DBJ Acquires Stake in Gunfleet Sands OWF…
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionOffshore construction
[8]
Transmission Investment (TC Gunfleet Sands OFTO Ltd)
“Assets connect the 184MW Gunfleet Sands 1 and 2 offshore windfarms to the 132kV electricity distribution network at Clacton substation in Essex. Export cable voltage: 132 kV, offshore cable length: 9 …”
supportsStatusConnection point
[10]
Renewable Energy Magazine2013-09-16
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacity
[12]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[15]
Ørsted2025-Q2◆ Orsted — orsted factsheet asset book q2 …
“Gunfleet Sands 1&2 (48 x SWT-3.6-107) | JERA, Development Bank of Japan (DBJ) | 172.8 | 172.8 | 172.8 | Full | 1 | 0.501 | 2010 | ROC | 2029 | - | 1.5”
supportsMechanismDetail
[16]
Ørsted2025-03-31◆ Orsted — orsted factsheet asset book q1 …
“OFFSHORE - Asset Book updated as of 31 March 2025 ... Gunfleet Sands 1&2 (48 x SWT-3.6-107) | JERA, Development Bank of Japan (DBJ) | 172.8 | 172.8 | 172.8 | Full | 1 | 0.501 | 2010 | ROC | 2029 | - |…”
supportsTotal capacity
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.