Dogger Bank South East

Part of Dogger Bank South 3GW complex (DBS East + DBS West). Located 100km+ off northeast England coast.

Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
RWE — 51% 
Masdar — 49% 
Location
United Kingdom
North Sea
Technology
Capacity 1,500 MW  Turbines 100 
Foundation
Site & conditions
Site rights Seabed rights held 
Origination Crown Estate Round 4 · 2021 ·
Water depth 13–33 m  Wind speed 10.4 m/s @ 150 m 
Revenue & grid
Offtake CfD · AR7 · £91.2/MWh  Grid Applied  Connection Birkhill Wood 400kV substation (National Grid), TEC application 
Schedule
FID Not taken
COD · announced 2032 
COD · Hafrok 2032 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2032
expected year of commercial operation
Chance of delivery
≈81% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract puts this one well above that; a very large build and technical complexity weigh only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2031: 3.9% (conditional on completion) 2032: 50.2% (conditional on completion) 2033: 29.5% (conditional on completion) 2034: 10.6% (conditional on completion) 2035: 3.8% (conditional on completion) 2036: 1.4% (conditional on completion) 2037: 0.6% (conditional on completion)2026now20272028202920302031203250%20332034203520362037 Developer-announced COD: 2032 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2032
COD probability by year, conditional on completion
YearProbability
20313.9%
2032 (expected)50.2%
203329.5%
203410.6%
20353.8%
20361.4%
20370.6%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2026. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2030; the faster quarter of similar projects would be done by 2028, the slower quarter not until 2031.
3
Result
Expected commercial operation 2032, likely range 2028–2031 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈81%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2021’22’23’24’25’26’27’28’29’30’31’32Developer-announced COD: 2032 announced COD 2032Crown Estate Round 4 — awarded to RWE RenewablesCrown Estate Round 4 Feb 2021 · auction recordView the source for Consent grantedConsent granted 14 May 2026 Commercial operation 2032 ·Hafrok expectedCrown Estate Round 4 — awarded to RWE Renewables 2021-02 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYRWE — 51% today · operator RWE RWE 51%Masdar — 49% today · investor Masdar Masdar 49%Crown Estate Round 4 — awarded to RWE Renewables Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake contract duration and price levels · money of the day

CfD-backed offtake
CfD · AR7
Price£65.45/MWh ·
Basis2012 real · CPI-indexed
Capacity1,500 MWAwardedJan 2026
Term20 yrs · delivery 2030/31
Money-of-the-day values computed by Hafrok from the United Kingdom CPI index, 2012 real base — actual to 2026-07, then an assumed +2.0%/yr (central-bank target). Cfd terms run 20 years from start of generation in the contracted delivery year.
Contract price over time · £/MWh
solid = actual CPI indexation · dashed = assumed +2.0%/yr
CfD · AR7
50100150nowCfD · AR7 — £65.45/MWh · 2012 real · CPI-indexed · assumed indexationCfD · AR7 term · 20 yrs2026203020342038204220462050CfD · AR7 — £65.45/MWh · 2012 real · CPI-indexed£65.45/MWh · 2012 real · CPI-indexed

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2032
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 0
Platformnone on the register
Export & onshore
Onshore connectionBirkhill Wood 400kV Substation·400 kV · consented · also serves Dogger Bank D, Dogger Bank South West
Onshore connectionHigh Marnham Substation·400 kV · planning · also serves Dogger Bank D, Dogger Bank South West
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2026202720282029203020312032Hafrok expects the farm to start in 2032developer’s stated start 2032nowBirkhill Wood 400kV SubstationBirkhill Wood 400kV SubstationHigh Marnham SubstationHigh Marnham Substationexpected 2031expected 2031

Sources & verification

6/13 fields verified · rests on 15 sources (10 primary) · ◆ 10 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator5
[3]
DESNZ2026-01-14◆ Contracts for Difference Allocation Roun…
“Dogger Bank South East CfD Unit A ... RWE RENEWABLES UK DOGGER BANK SOUTH (EAST) LIMITED ... Offshore Wind 1500.00 65.45 91.20 2030/31 3 3”
supportsTotal capacityMechanismStrike / priceDetail
[5]
DESNZ2026-05-14◆ Dogger Bank South Offshore Wind Farms de…
“The Dogger Bank South Offshore Wind Farms DCO application has today been granted development consent by the Department for Energy Security and Net Zero.”
supportsConsentStatusConnection pointConsent granted
[10]
Department for Energy Security and Net Zero2026-05-06◆ Renewable Energy Planning Database (REPD…
“REPD Q1 2026 quarterly extract — Ref ID 11109: Site Name "Dogger Bank South East", Development Status "Application Submitted", Installed Capacity 1500 MWelec, Operator "RWE Renewables UK Limited / Mas…”
supportsRegister entry
[14]
Department for Energy Security and Net Zero2026-08-03◆ Renewable Energy Planning Database (REPD…
“REPD Q2 2026 quarterly extract — Ref ID 11109: Site Name "Dogger Bank South East", Development Status "Planning Permission Granted", Installed Capacity 1500 MWelec, Operator "RWE Renewables UK Limited…”
supportsRegister entry
[16]
The Planning Inspectorate (PINS)2026-08-23◆ PINS national infrastructure application…
“Project reference EN010125: "Dogger Bank South Offshore Wind Farms"; applicant "RWE Renewables UK Dogger Bank South (West) Ltd and RWE Renewables UK Dogger Bank South (East) Ltd"; Stage "Post-decision…”
supportsRegister entry
Operator5
[4]
RWE AG2026-01-14◆ RWE secures CfDs for 6.9 GW of offshore …
“In December 2023, Masdar (49%) and RWE (51%) joined forces to deliver DBS. On behalf of the partners, RWE is leading the development, construction and operation. Commissioning of the projects is expec…”
supportsCommercial operation
[7]
RWE/Masdar2026
supportsTurbines
[11]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-001375-1: "Dogger Bank South East", Status "Scoping", MW Connected 0, Effective From 2030-10-30, Customer "RWE Renewables UK Dogger Bank South (East) Limi…”
supportsRegister entry
[13]
RWE2025-03-20◆ RWE — 2025 03 20 rwe annual report 2024
“We have formed a partnership with Abu Dhabi-based clean energy firm Masdar to realise two offshore wind projects, which are planned for the southern section of Dogger Bank in the British North Sea. Th…”
supportsoperatorinvestor
[15]
RWE2026-05-14◆ Rwe and masdar receive planning permissi…
“RWE and Masdar will now conduct detailed final design work and progress procurement decisions with the aim of taking a final investment decision (FID) in 2027.”
supportsStatus note
Auction results1
[17]
DESNZ (gov.uk)2026-01◆ cfd-ar7-results-2026
Offshore Wind (Pot 3) cleared GBP 65.45 (2012) / 91.20 (2024): Awel y Môr A 775.00 MW; Dogger Bank South East/West Unit A 1,500.00 MW each; Norfolk Vanguard East A 1,380 / B 90 / C 75 MW; Norfolk Vang…
supportsCfD · AR7
Trade press3
[6]
GEM2026
supportsTotal capacityCoordinates
[8]
GEBCO Compilation Group2020
supportsWater depth
[9]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsTurbinesTotal capacityWater depthCoordinates