Broadshore Hub

ScotWind Floating. Three development areas (Broadshore, Sinclair, Scaraben). Could power over 1 million homes. Capacity increased from 900MW.

Status
Early Developmentlifecycle stage
ProspectiveHafrok completion outlook
Ownership
Nadara — 100% 
Location
United Kingdom
North Sea
Technology
Capacity 1,100 MW 
Turbines
Foundation Floating 
Site & conditions
Site rights Seabed rights held 
Origination ScotWind Leasing · 2022 ·
Water depth 58–98 m  Distance from shore 47 km  Wind speed 10.7 m/s @ 150 m 
Revenue & grid
Offtake
Grid Applied  Connection Longside 400kV Substation — NESO TEC register entry at Scoping … 
Schedule
FID Not taken
COD · announced 2033 
COD · Hafrok 2034 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2034
expected year of commercial operation
The developer says 2033; Hafrok expects 2034 — 1 year later.
Chance of delivery
≈56% estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. This one sits well below that: its size and technical complexity. A secured offtake contract helps only slightly.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2033: 14.1% (conditional on completion) 2034: 28.0% (conditional on completion) 2035: 22.7% (conditional on completion) 2036: 14.6% (conditional on completion) 2037: 8.7% (conditional on completion) 2038: 5.1% (conditional on completion) 2039: 3.1% (conditional on completion) 2040: 1.8% (conditional on completion) 2041: 1.1% (conditional on completion) 2042: 0.7% (conditional on completion)2026now2028203020322033203428%EXPECTED2036203820402042 Developer-announced COD: 2033 ANNOUNCED 2033
COD probability by year, conditional on completion
YearProbability
203314.1%
2034 (expected)28.0%
203522.7%
203614.6%
20378.7%
20385.1%
20393.1%
20401.8%
20411.1%
20420.7%
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (2026), adds the time similar projects (floating, in established offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.
2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before 2034 is not credible.
3
Still needs an offtake award: UK-CFD-AR8
The project has no offtake contract yet. The next visible auction is around 2026 Q4; winners typically reach final investment decision about 2 years after an award (2028 Q4), then build time on top gives 2032 Q4. The milestone timing is already later than that, so it stands.
4
Result
Expected commercial operation 2034, likely range 2034–2040 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.
5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈56%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2022’23’24’25’26’27’28’29’30’31’32’33’34Developer-announced COD: 2033 announced COD 2033ScotWind Leasing — awarded to Falck RenewablesScotWind Leasing Jan 2022 · auction recordCommercial operation 2034 ·Hafrok expectedScotWind Leasing — awarded to Falck Renewables 2022-01 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYFalck Renewables Falck Renewables Falck Renewables not among today’s recorded owners — no sale recordedNadara — 100% today · operator Nadara Nadara 100%ScotWind Leasing — awarded to Falck Renewables Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
CfD allocation round
The UK's principal route — a 15-year, CPI-indexed, two-sided CfD awarded in annual competitive rounds.
Next visible round · from the auction calendar
CfD Allocation Round 8
expected H2 2026 · scheduled · the round’s published documents do not name this project
AR8 confirmed (gov update, Mar 2026) to OPEN July 2026 — brought forward from the earlier mid/late-2026 expectation
Corporate PPA
Bilateral long-term offtake with corporate buyers; can cover part of output alongside or ahead of a CfD.
Merchant
Uncontracted sale into the wholesale market — no price floor, full exposure to power prices.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2033

Sources & verification

7/14 fields verified · rests on 11 sources (5 primary) · ◆ 8 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[10]
Scottish Government Marine Directorate (MD-LOT)2026-08-23◆ Scottish MD-LOT marine projects register…
“Register row "Broadshore Hub Offshore Wind Farms" (key node/24780): Application stage "Pre-application", type "Renewables - Wind".”
supportsRegister entry
Operator4
[1]
Nadara (Broadshore project website)2024◆ Home - Broadshore
“The Broadshore Offshore Wind Farm is being developed by Nadara, with the aim of contributing to a world-leading floating offshore wind industry in the UK. The Broadshore initiative will harness the va…”
supportsFoundationDistance from shore
[2]
Nadara (Broadshore project website)2024-11◆ Broadshore Hub developers seek community…
“The three offshore wind farms—Broadshore, Sinclair, and Scaraben—collectively known as the Broadshore Hub, with a combined capacity of up to 1.1 GW, located 47 km north of Fraserburgh.”
supportsConsentTotal capacity
[5]
NESO2026-06-12◆ NESO Transmission Entry Capacity (TEC) R…
“Broadshore Offshore Wind Farm,Broadshore Offshore Wind Farm Limited,Longside 400kV Substation,,0,900,900,31/10/2033,Scoping,Direct Connection,SHET,Wind Offshore,a1f8e00000158hcAAA,PRO-002171,”
supportsCommercial operationStatusConnection point
[9]
National Energy System Operator (NESO)2026-07-21◆ NESO Transmission Entry Capacity (TEC) R…
“NESO TEC Register, edition 21 July 2026 - PRO-002171: "Broadshore Offshore Wind Farm", Status "Scoping", MW Connected 0, Effective From 2033-10-31, Customer "Broadshore Offshore Wind Farm Limited"”
supportsRegister entry
Auction pipeline1
[11]
DESNZ (gov.uk)2026◆ govuk-cfd-ar8
gov.uk AR8 collection — Allocation Framework, statutory framework and CIB documents published ahead of the round.
supportsCfD Allocation Round 8
Trade press5
[3]
offshoreWIND.biz2024-02-13◆ BlueFloat, Renantis Press Ahead with 1.1…
Press report — cited, not quoted; read it at the source link.
supportsBackground
[4]
offshoreWIND.biz2025-11-28◆ Nadara acquires BlueFloat JV stakes in 1…
Press report — cited, not quoted; read it at the source link.
supportsoperator
[6]
Global Energy Monitor2026-07-02
supportsCoordinates
[7]
GEBCO Compilation Group2020
supportsWater depth
[8]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed