Formosa 6

Haiguang (海廣), off Xianxi Township, Changhua County — Synera Renewable Energy's first project in central Taiwan and, at 800 MW, the largest single site awarded in Taiwan's zonal-development programme to date.

Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
SRSynera Renewable Energy — 100% 
Location
Taiwan
Taiwan Strait
Technology
Capacity 800 MW  Turbines 57  Foundation Jacket 
Site & conditions
Site rights Seabed rights held Tender award · 經濟部 (Ministry of Economic Affairs) · 2024-08 
Origination Taiwan Round 3 Zonal Development — Block 3.2 (區塊開發 3-2) · 2024 ·
Water depth 31–46 m  Distance from shore 35 km  Wind speed 10.4 m/s @ 150 m 
Revenue & grid
Offtake PPA 
Grid
Schedule
FID Not taken
COD · announced 2029 
COD · Hafrok 2029 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2029
expected year of commercial operation
Chance of delivery
≈84% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract puts this one well above that; its size and technical complexity weigh only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2028: 3.9% (conditional on completion) 2029: 50.2% (conditional on completion) 2030: 29.5% (conditional on completion) 2031: 10.6% (conditional on completion) 2032: 3.8% (conditional on completion) 2033: 1.4% (conditional on completion) 2034: 0.6% (conditional on completion)2026now20272028202950%20302031203220332034 Developer-announced COD: 2029 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2029
COD probability by year, conditional on completion
YearProbability
20283.9%
2029 (expected)50.2%
203029.5%
203110.6%
20323.8%
20331.4%
20340.6%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2026. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2030; the faster quarter of similar projects would be done by 2028, the slower quarter not until 2031.
3
Result
Expected commercial operation 2029, likely range 2028–2031 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈84%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2024’25’26’27’28’29Developer-announced COD: 2029 announced COD 2029View the source for Consent appliedConsent applied 15 May 2024 Taiwan Round 3 Zonal Development — Block 3.2 (區塊開發 3-2) — awarded to Synera Renewable EnergyTaiwan Round 3 Zonal Development — Block 3.2 (區塊開發 3-2) Aug 2024 · auction recordCommercial operation 2029 ·Hafrok expectedTaiwan Round 3 Zonal Development — Block 3.2 (區塊開發 3-2) — awarded to Synera Renewable Energy 2024-08 ORIGINATIONTODAYSynera Renewable Energy — 100% today · operator Synera Renewable Energy Synera Renewable Energy 100%Taiwan Round 3 Zonal Development — Block 3.2 (區塊開發 3-2) — awarded to Synera Renewable Energy
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2029

Sources & verification

10/14 fields verified · rests on 11 sources (1 primary) · ◆ 7 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[7]
MOEA Energy Administration (經濟部能源署)2024-08-05◆ 附件、離岸風力發電區塊開發第二期容量分配結果
“「附件、離岸風力發電區塊開發第二期容量分配結果 — 獲選申請案/序位/獲配容量(MW)/完工併聯年度: 又德風力發電股份有限公司籌備處 1 700 118;海廣發電股份有限公司籌備處 2 800 118; 渢妙二號離岸風力發電股份有限公司籌備處 4 600 118;海鼎一風力發電股份有限公司籌備處 5 360 117; 德帥風力發電股分有限公司籌備處 6 240 117」 (Official Ro…”
supportsCommercial operationSite rightsTotal capacity
Operator1
[8]
Synera Renewable Energy (風睿能源)2026◆ Formosa 6 / 海廣風電
"Status In development | Installed capacity 800 MW | Foundation Jacket | Number of turbines 57 | Location 35 km off the coast of Changhua County, Taiwan | Water depth 31-46 m | Area 84 km2". Also: "Wi…
supportsTurbinesTotal capacityFoundationWater depthDistance from shore
Trade press9
[2]
offshoreWIND.biz2025-08
Press report — cited, not quoted; read it at the source link.
supportsoperatorTotal capacity
[3]
LSPR2024
supportsTotal capacity
[4]
Global Energy Monitor2026-07-02
supportsCoordinates
[6]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[9]
Liberty Times (自由時報)2024-05-16◆ 海廣風場通過環評
Press report — cited, not quoted; read it at the source link.
supportsConsentConsent applied
[10]
Central News Agency (中央社)2025-02-14◆ 經部:離岸風電3-2期海廣風場完成簽約 4家已補件
Press report — cited, not quoted; read it at the source link.
supportsSite rights
[11]
Commercial Times (工商時報)2026-04-13◆ 策略轉向 台電擬投資海廣風場
Press report — cited, not quoted; read it at the source link.
supportsStatus note
[12]
offshoreWIND.biz2026-09-09◆ Formosa 6 Offshore Wind Farm and Star Tr…
Press report — cited, not quoted; read it at the source link.
supportsMechanismDetail
[13]
Taipei Times2026-09-10◆ Star Trade, Synera ink corporate power p…
Copyrighted source — cited, not quoted; read it at the source link.
supportsFirst powerMechanismDetail