Neptunus Offshore Wind (Sweden)

Located off the Blekinge coast in southern Sweden, approximately 50 km from shore. OX2 and Ingka Investments applied January 2024.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageCancelled
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

6/14 fields verified · rests on 6 sources (1 primary) · ◆ 2 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator3
[2]
OX22024-01-16
“OX2 and Ingka Investments have applied for a permit to build and operate the offshore wind farm Neptunus, planned to be built about 50 kilometers from the coast of Blekinge, south of Sweden. The plant…”
supportsTurbinesTotal capacityDistance from shore
[3]
OX22023
“The transaction includes the offshore projects Pleione located east of Gotland and Neptunus located southeast of Blekinge ... OX2 has agreed with Ingka Investments, the investment arm of Ingka Group –…”
supportsoperatorowner
[6]
Swedish Government (Regeringskansliet)2024-11-04◆ Avslag på 13 havsbaserade vindkraftparke…
“Regeringen har den 4 november 2024 beslutat att inte ge tillstånd enligt lagen (1992:1140) om Sveriges ekonomiska zon för att bygga och driva 13 projekterade vindkraftparker i Östersjön utanför Sverig…”
supportsConsentSite rights
Trade press3
[1]
Offshore Wind Biz2024-11-04◆ Sweden rejects 13 Baltic offshore projec…
Press report — cited, not quoted; read it at the source link.
supportsMechanismDetailStatusConnection point
[4]
Global Energy Monitor2026-07-02
supportsCoordinates
[5]
GEBCO Compilation Group2020