Galatea

Southern half of the Galatea-Galene cluster.

Status
Proposedlifecycle stage
Ownership
OX2 — 51% 
INIngka — 49% 
Location
Sweden
Kattegat
Technology
Capacity 1,300 MW 
Turbines
Foundation
Site & conditions
Site rights Not established we have not found a document granting or refusing rights over this seabed — a gap in our research, not a finding about the project 
Water depth 32–62 m  Wind speed 9.7 m/s @ 150 m 
Revenue & grid
Offtake
Grid
Schedule
FID Not taken
COD · developer

Delivery outlook not forecast

We don't put a delivery estimate on this project yet. No authority has granted rights to this site, so there is nothing to date a schedule from. That changes the moment the seabed is awarded, a consent application is filed, or the project is named in an auction.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageProposed
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

1/9 fields verified · rests on 5 sources
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator2
[1]
OX22024
supportsTotal capacity
[4]
Ingka Group2022-08-29
“Ingka Investments, the investment arm of Ingka Group, acquires a 49 percent share in three offshore wind development projects in Sweden. [Galatea-Galene in Kattegat, Triton, and Aurora]”
supportsdeveloperowner
Trade press3
[2]
Global Energy Monitor2026
supportsCoordinates
[3]
GEBCO Compilation Group2020
supportsWater depth
[5]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed