Aurora Offshore Wind (Sweden)
Located approximately 22 km south of Gotland and 30+ km east of Öland in the Swedish EEZ Baltic Sea.
Status
Cancelledlifecycle stage
Ownership
OX2 — 51% ◆
Ingka Investments — 49% ◆Location
Baltic Sea
Technology
Capacity
5,500 MW ◆
Turbines
275 × 20 MW ◆
Model
not yet named · 15-25 MW Class ◆
Foundation
—
Site & conditions
Site rights
Application filed 2024-11 ◆
Water depth
49–90 m ≈
Distance from shore
30 km ◆
Wind speed
10.0 m/s @ 150 m ≈
Revenue & grid
Offtake
Other project cancelled ◆
Grid
No agreement ◆
Connection
N/A ◆
Schedule
COD
—
Cancelled
4 Nov 2024 ◆
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
2 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 12 sources (4 primary) · ◆ 9 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator5
[1]
OX22022-06-27◆ OX2 applies for a permit to construct th…
“OX2 has applied for a permit to construct the offshore wind farm Aurora under the Act concerning Sweden's Exclusive Economic Zone. The project specifies up to 370 wind turbines with a maximum height o…”
supportsTurbinesModelUnit capacityTotal capacity
[2]
OX22024-04-03◆ OX2 and ingka investments offshore wind …
“OX2 and Ingka Investments' offshore wind farm Aurora receives Natura 2000 permit. The Aurora wind farm is located approximately 22 kilometers south of Gotland and over 30 kilometers east of Oland in t…”
supportsDistance from shoreCoordinates
[8]
Ingka Group2022-12
“The three wind power projects are Galatea-Galene in Kattegat, Triton in the Baltic Sea south of Sweden and Aurora between the islands Öland and Gotland. ... Ingka Investments, the investment arm of In…”
supportsoperatorowner
[11]
Swedish Government (Regeringskansliet)2024-11-04◆ Avslag på 13 havsbaserade vindkraftparke…
“Regeringen har den 4 november 2024 beslutat att inte ge tillstånd enligt lagen (1992:1140) om Sveriges ekonomiska zon för att bygga och driva 13 projekterade vindkraftparker i Östersjön utanför Sverig…”
supportsConsentCancelledSite rightsConsent applied
[12]
AUR Energipark AB (OX2)2022-06-27◆ Ansökan om tillstånd enligt lagen (1992:…
“Behörighetshandlingar för ombuden biläggs, Bilaga E. Malmö den 27 juni 2022 AUR Energipark AB”
supportsConsentSite rightsConsent applied
Trade press7
[3]
offshoreWIND.biz2024-06-03◆ Swedish County Recommends Gov’t Approval…
Press report — cited, not quoted; read it at the source link.
supportsBackground
[4]
offshoreWIND.biz2024-11-04◆ Sweden rejects 13 Baltic offshore projec…
Press report — cited, not quoted; read it at the source link.
supportsMechanismDetailStatusConnection pointport
[5]
Euronews2024-11-05◆ Sweden rejects applications for thirteen…
Copyrighted source — cited, not quoted; read it at the source link.
supportsBackground
[6]
Defense News2024-11-11◆ Why Sweden nixed new wind farms for fear…
Copyrighted source — cited, not quoted; read it at the source link.
supportsBackground
[7]
WindEurope2024-11-05◆ Sweden puts its industrial competitivene…
“Sweden has rejected 13 offshore wind applications in the Baltic Sea with a combined capacity of almost 32 GW and representing around SEK 550 billion in private investment.”
supportsBackground
[9]
[10]