Baltica 9

Located approximately 48 km from coast, covering ~121 km2. Part of PGE's broader Baltic offshore portfolio (Baltica 2, 3, 9, plus F.E.W. Baltic II acquisition).

Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
EWElektrownia Wiatrowa Baltica 9 sp. z o.o. — 100% 
Location
Poland
Baltic Sea
Technology
Capacity 975 MW 
Turbines
Foundation
Site & conditions
Site rights Seabed rights held 
Origination Poland offshore CfD Phase 2 (first competitive auction) · 2025 ·
Water depth 35–56 m  Distance from shore 48 km  Wind speed 10.0 m/s @ 150 m 
Revenue & grid
Offtake CfD · 489 PLN/MWh  Grid Applied  Connection Preliminary grid connection conditions obtained; … 
Schedule
FID Not taken
COD · announced 2032 
COD · Hafrok 2032 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2032
expected year of commercial operation
Chance of delivery
≈82% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract puts this one well above that; a market with a thinner delivery record, its size and technical complexity weigh only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2031: 3.9% (conditional on completion) 2032: 50.2% (conditional on completion) 2033: 29.5% (conditional on completion) 2034: 10.6% (conditional on completion) 2035: 3.8% (conditional on completion) 2036: 1.4% (conditional on completion) 2037: 0.6% (conditional on completion)2026now20272028202920302031203250%20332034203520362037 Developer-announced COD: 2032 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2032developer cod guidance2026-04-15: the developer guided 20322026-042032 2026-06-16: the developer guided 2032-12 — source [1] — click for it2026-062032-12 [1]
COD probability by year, conditional on completion
YearProbability
20313.9%
2032 (expected)50.2%
203329.5%
203410.6%
20353.8%
20361.4%
20370.6%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2026-04-152032
2026-06-162032-12
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2026. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2031; the faster quarter of similar projects would be done by 2029, the slower quarter not until 2031.
3
Result
Expected commercial operation 2032, likely range 2029–2031 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈82%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2024’25’26’27’28’29’30’31’32Developer-announced COD: 2032 announced COD 2032View the source for Consent appliedConsent applied Aug 2023 Poland offshore CfD Phase 2 (first competitive auction) — awarded to PGEPoland offshore CfD Phase 2 (first competitive auction) Dec 2025 · auction recordCommercial operation 2032 ·Hafrok expectedPoland offshore CfD Phase 2 (first competitive auction) — awarded to PGE 2025-12 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYPGE PGE PGE not among today’s recorded owners — no sale recordedElektrownia Wiatrowa Baltica 9 sp. z o.o. — 100% today · operator Elektrownia Wiatrowa Ba… Elektrownia Wiatrowa Ba… 100%Poland offshore CfD Phase 2 (first competitive auction) — awarded to PGE Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: slipped so far +0.5 yr (first announced 2032) · the full guidance history is in the delivery chart above

Revenue & offtake contract duration and price levels · money of the day

975 MW contracted — tender award
Tender award · Poland offshore CfD Phase 2 (first competitive auction)
Price489 PLN/MWh ·Capacity975 MWAwardedDec 2025
Term25 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2032

Sources & verification

10/14 fields verified · rests on 8 sources (5 primary) · ◆ 6 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[9]
Ministry of Justice (Poland), National Court Register (KRS)2026-08-22◆ KRS odpis aktualny 0000936145 - Elektrow…
“Wspolnicy (shareholders) of ELEKTROWNIA WIATROWA BALTICA 9 SPOLKA Z OGRANICZONA ODPOWIEDZIALNOSCIA (KRS 0000936145): PGE POLSKA GRUPA ENERGETYCZNA SPOLKA AKCYJNA (KRS 0000059307), 14.314 udzialow o la…”
supports↳ parent
Operator3
[1]
PGE Polska Grupa Energetyczna (current report No. 49/2025)2025-12-19◆ Baltica 9 Project With The Right To Cove…
"Elektrownia Wiatrowa Baltica 9 sp. z o.o. ("Baltica 9" – a subsidiary of PGE), the company developing Baltica 9 offshore wind farm project with the capacity of 975 MW … the right to cover a negative …
supportsCOD historyTotal capacityMechanismStrike / priceDetail
[4]
PGE Polska Grupa Energetyczna (current report)2023-08-09◆ Obtaining The Decisions On The Permit To…
“Area 44.E.1 received a decision for construction of an offshore wind farm requested by Elektrownia Wiatrowa Baltica 9 sp. z o.o., in which PGE holds 100% of shares.”
supportsoperatorConsentConsent applied
[5]
PGE Baltica2025-12-19◆ PGE Baltica 9 project wins Contract for …
“975 MW Baltica 9 offshore wind farm is located in the western part of the Słupsk Bank, within basin 44.E.1, situated about 48 kilometres from the coast and will cover around 121 square kilometres … fi…”
supportsCommercial operationStatusConnection pointDistance from shoreCoordinates
Auction results1
[10]
Norton Rose Fulbright2026-06-22◆ pl-phase2-auction-2025-pl-owa
Poland Offshore Wind Act CfD: PLN 60,000/MW security, first power within 7 years of decision/auction-close
supportsTender award · Poland offshore CfD Phase 2 (first competitive auction)
Trade press3
[6]
Offshore Wind Biz2025-12-19◆ Poland Awards 3.4+ GW of Offshore Wind C…
Press report — cited, not quoted; read it at the source link.
supportsBackground
[7]
GEBCO Compilation Group2020
supportsWater depth
[8]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed