Aurora Offshore Wind Power Project

Status
Proposedlifecycle stage
Ownership
GOGalea Offshore Wind Corp. — 100% 
Location
Philippines
Philippine Sea
Technology
Capacity 600 MW 
Turbines
Foundation
Site & conditions
Site rights Exploration right Exploration permit · Department of Energy (Philippines)  Water depth 85–348 m  Wind speed 7.3 m/s @ 150 m 
Revenue & grid
Offtake
Grid
Schedule
FID Not taken
COD · developer

Delivery outlook not forecast

We don't put a delivery estimate on this project yet. No authority has granted rights to this site, so there is nothing to date a schedule from. That changes the moment the seabed is awarded, a consent application is filed, or the project is named in an auction.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take.
Next visible round · from the auction calendar
Green Energy Auction GEA-5 (offshore wind)
expected H2 2026 · scheduled · the round’s published documents do not name this project
NOA + TOR issued 25 Nov 2025 (Supplemental TOR 29 Jan 2026); Qualified-Supplier registration began 2 Mar 2026; ERC-approved GEAR reserve price PhP 11.00/kWh (23 Feb 2026); bids mid-2026, awards H2 2026.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageProposed
Offshore constructionnot started
Expected start of operationnot stated

Sources & verification

1/9 fields verified · rests on 6 sources · ◆ 1 document held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
DOE2025
supportsownerTotal capacity
[5]
Department of Energy (Philippines)2025-09-30◆ Awarded Wind Energy Service Contracts (A…
“Register 'AWARDED WIND PROJECTS as of 30 SEPTEMBER 2025' (Department of Energy, Renewable Energy Management Bureau), row: Aurora - Aurora Offshore Wind Power Project Galea Offshore Wind Corp. Pre-Deve…”
supportsSite rights
Auction pipeline1
[6]
Department of Energy (Philippines)2026
DOE GEA-5 — first offshore-wind-only Green Energy Auction; NOA/TOR 25 Nov 2025; 3,300 MW fixed-bottom OSW; GEAR PhP 11.00/kWh; awards targeted H2 2026.
supportsGreen Energy Auction GEA-5 (offshore wind)
Trade press3
[2]
Global Energy Monitor2026
supportsCoordinates
[3]
GEBCO Compilation Group2020
supportsWater depth
[4]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed