Saikai Enoshima Offshore Wind (Round 2)

Located in the East China Sea off Nagasaki Prefecture. Sumitomo/TEPCO partnership.

Status
Advanced Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
MEMiraie Enoshima G.K. — 100% 
Location
Japan
East China Sea
Technology
Capacity 420 MW 
Turbines
Foundation
Site & conditions
Site rights Seabed rights held 
Origination Japan Offshore Wind Round 2 (general sea-area public solicitation) · 2023 ·
Water depth 8–20 m  Wind speed 7.7 m/s @ 150 m 
Revenue & grid
Offtake Premium · 22.18 JPY_per_kWh  Grid Not recorded  Connection Kyushu Electric Power grid (Nagasaki) 
Schedule
FID Not taken
COD · announced Aug 2029 
COD · Hafrok 2029 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2029
expected year of commercial operation
Chance of delivery
≈81% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. A secured offtake contract puts this one well above that; a market with a thinner delivery record and technical complexity weigh only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2028: 3.9% (conditional on completion) 2029: 50.2% (conditional on completion) 2030: 29.5% (conditional on completion) 2031: 10.6% (conditional on completion) 2032: 3.8% (conditional on completion) 2033: 1.4% (conditional on completion) 2034: 0.6% (conditional on completion)2026now20272028202950%20302031203220332034 Developer-announced COD: 2029 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2029
COD probability by year, conditional on completion
YearProbability
20283.9%
2029 (expected)50.2%
203029.5%
203110.6%
20323.8%
20331.4%
20340.6%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2026. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2031; the faster quarter of similar projects would be done by 2029, the slower quarter not until 2031.
3
Result
Expected commercial operation 2029, likely range 2029–2031 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈81%, which rates it Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2024’25’26’27’28’29Developer-announced COD: 2029-08 announced COD Aug 2029Japan Offshore Wind Round 2 (general sea-area public solicitation) — awarded to Sumitomo / TEPCO Renewable Power (consortium みらいえのしま)Japan Offshore Wind Round 2 (general sea-area public solicitation) Dec 2023 · auction recordCommercial operation 2029 ·Hafrok expectedJapan Offshore Wind Round 2 (general sea-area public solicitation) — awarded to Sumitomo / TEPCO Renewable Power (consortium みらいえのしま) 2023-12 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYSumitomo Corporation Sumitomo Corporation Sumitomo Corporation not among today’s recorded owners — no sale recordedTEPCO Renewable Power Inc. TEPCO Renewable Power I… TEPCO Renewable Power I… exited 2023-12Miraie Enoshima G.K. — 100% today · operator Miraie Enoshima G.K. Miraie Enoshima G.K. 100%Japan Offshore Wind Round 2 (general sea-area public solicitation) — awarded to Sumitomo / TEPCO Renewable Power (consortium みらいえのしま) Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake contract duration and price levels · money of the day

420 MW contracted — tender award
Tender award · Japan Offshore Wind Round 2 (general sea-area public solicitation)
Price22.18 JPY/kWh ·Capacity420 MWAwardedDec 2023
Term20 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2029-08

Sources & verification

2/12 fields verified · rests on 10 sources (1 primary) · ◆ 2 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Auction results1
[11]
Aquilo Energy / EEAS2026-06-22◆ jp-round2-2023-jp-tenders-study
Japanese offshore-wind tenders study: 30-yr occupancy permit, scheduled operation <=8 years after Occupancy Plan certification
supportsTender award · Japan Offshore Wind Round 2 (general sea-area public solicitation)
Trade press8
[2]
Sumitomo Corporation2023-12-13
“Sumitomo Corporation … has received notification that our Consortium … has been appointed to design, build and operate an offshore wind project in the sea area off the coast of Enoshima Island, Saikai…”
supportsCommercial operationTotal capacity
[3]
Shulman Advisory2023-12
“For Saikai-Enoshima: bid price 22.18 yen/kWh. The auction was subject to the Feed-in Premium (FIP) regime with an upper limit of 29 yen/kWh … The winner was Sumitomo Corporation and TEPCO Renewable Po…”
supportsMechanismStrike / priceDetail
[4]
DeepWind (third-party aggregator)2026-05-26
“SPV Name: Miraie Enoshima G.K. (みらいえのしま合同会社) … Stakeholders: Sumitomo Corporation; TEPCO Renewable Power … Draft EIA Statement (準備書) — Last updated May 26, 2026 … 5th Statutory Council Meeting: Februa…”
supportsConsentStatusConnection point
[5]
Sumitomo Corp2023◆ Appointed as Operators of Offshore Wind …
supportsoperator
[6]
DeepWind (Nagasaki Saikai Enoshima project)2025
supportsTotal capacity
[7]
Global Energy Monitor (GEM.wiki)2026-07-02
supportsCoordinates
[8]
GEBCO Compilation Group2020
supportsWater depth
[9]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsTotal capacityWater depthCoordinates