Kailia Energia
Located off the coastline between Brindisi and San Cataldo, Puglia. Part of Nadara's 2.5 GW Puglia floating wind portfolio (paired with Odra Energia).
Technology
Capacity
1,170 MW ◆
Turbines
78 ◆
Foundation
Floating ◆
Site & conditions
Site rights
Not established we have not found a document granting or refusing rights over this seabed — a gap in our research, not a finding about the project ∅
Water depth
27–102 m ≈
Distance from shore
20 km ◆
Wind speed
7.6 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
Not recorded ∅
Schedule
FID
Not taken
COD · developer
2032 announced ◆
Delivery outlook not forecast
We don't put a delivery estimate on this project yet. No authority has granted rights to this site, so there is nothing to date a schedule from. That changes the moment the seabed is awarded, a consent application is filed, or the project is named in an auction.
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
the dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 7 sources (1 primary) · ◆ 3 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator1
[1]
Nadara2024-03-14◆ Kailia floating offshore wind project: E…
“Kailia Energia submitted the Environmental Impact Assessment (EIA) to the Ministry of Environment and Energy Security (MASE) and the Ministry of Culture (MiC) ... maximum expected installed capacity o…”
supportsConsentCommercial operationTurbinesTotal capacityFoundation+1 more
Auction pipeline1
[7]
reNEWS2026-05-20◆ renews-seanergy-fer2-strike-2026-05
Press report — cited, not quoted; read it at the source link.
supportsItaly first dedicated offshore auction (FER2 offshore contingent)
Trade press5
[2]
[3]
[4]
4C Offshore2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[5]
[6]