Beleolico (Taranto Offshore)
Located in the external roadstead of the Port of Taranto, Apulia. Turbines span 0.1-2.5 km from shore.
Status
Operationallifecycle stage
Ownership
RSRenexia SpA — 100% ◆
THToto Holding — split undisclosed ◆
Location
Ionian Sea
Technology
Capacity
30 MW ◆
Turbines
10 × 3 MW ◆
Model
Mingyang Myse3 0-135 ◆
Foundation
Monopile ◆
Site & conditions
Site rights
Seabed rights held ∴
Water depth
4–18 m ◆
Revenue & grid
Offtake
FiT · €161.7/MWh ◆
Grid
Not recorded ◆
Connection
Torre Triolo substation ◆
Schedule
FID
Feb 2019 ◆
COD
2022-Q2 ◆
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
5 dated milestones on the spine, each with its source · 2 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 12 sources (7 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator9
[1]
[2]
[3]
Natixis CIB2019-02-26◆ Beleolico, first offshore windfarm in th…
"The approximately EUR 82 million debt package arranged by Natixis consists of a term loan, a VAT financing and a stand-by facility. The Borrower, Beleolico Srl, is owned by Renexia Spa, the renewable…
supportsFinal investment decisionWater depth
[5]
[6]
[7]
[8]
[9]
[12]
Renexia S.p.A.2026-07-21◆ Beleolico - Renexia
“RENEXIA Società per Azioni (joint stock company) subject to the management and coordination of toto holding s.p.a. – Nominal capital 5.000.000 € fully paid up – VAT and Tax Code and company registry n…”
supports↳ parents
Auction results1
[13]
Gestore dei Servizi Energetici (GSE)2016-12-22◆ gse-graduatoria-eolico-offshore-2016
"Procedura competitiva d'Asta al ribasso ai sensi dell'art. 12 del D.M. 23 giugno 2016 ... Codice identificativo della Procedura d'Asta: EOLF_PA2016" and the single ranking row "1 FER102027 IM_0603701…
supportsFeed-in tariff · GSE reverse auction, offshore wind contingent (DM 23 giugno 2016)
Trade press2
[10]
IWR Online2022-06-15
“The Beleolico offshore wind farm has now reached a milestone in early June 2022, feeding the first wind power into the Italian grid, according to European grid operator (Entso-E) data.”
supportsFirst powerCommercial operation
[11]
Il Post2022-04-21
“La prima autorizzazione ministeriale risale al 13 giugno 2013, con la pubblicazione in Gazzetta ufficiale di un decreto del ministero dei Trasporti e delle Infrastrutture”
supportsConsentConsent granted