Kailia Energia
Located off the coastline between Brindisi and San Cataldo, Puglia. Part of Nadara's 2.5 GW Puglia floating wind portfolio (paired with Odra Energia).
Technology
Capacity
1,170 MW ◆
Turbines
78 ◆
Foundation
Floating ◆
Site & conditions
Site rights
Not established we have not found a document granting or refusing rights over this seabed — a gap in our research, not a finding about the project ∅
Water depth
27–102 m ≈
Distance from shore
20 km ◆
Wind speed
7.6 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
Not recorded ∅
Schedule
FID
Not taken
COD · developer
2032 announced ◆
Delivery outlook not forecast
We don't put a delivery estimate on this project yet. No authority has granted rights to this site, so there is nothing to date a schedule from. That changes the moment the seabed is awarded, a consent application is filed, or the project is named in an auction.
Revenue & offtake route to market — open
No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take.
Next visible round · from the auction calendar
Italy first dedicated offshore auction (FER2 offshore contingent) ◇
stated by industry at Seanergy (May 2026) after informal MASE–Commission talks — strike-price revision by end-2026, auction "at the latest in 2027"; no MASE notice
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageProposed
Offshore constructionnot started
Expected start of operation2032
Construction ports
PortBrindisi ∅
Sources & verification
8/15 fields verified · rests on 7 sources (1 primary) · ◆ 3 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator1
[1]
Nadara2024-03-14◆ Kailia floating offshore wind project: E…
“Kailia Energia submitted the Environmental Impact Assessment (EIA) to the Ministry of Environment and Energy Security (MASE) and the Ministry of Culture (MiC) ... maximum expected installed capacity o…”
supportsConsentCommercial operationTurbinesTotal capacityFoundation+1 more
Auction pipeline1
[7]
reNEWS2026-05-20◆ renews-seanergy-fer2-strike-2026-05
Press report — cited, not quoted; read it at the source link.
supportsItaly first dedicated offshore auction (FER2 offshore contingent)
Trade press5
[2]
[3]
[4]
4C Offshore2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[5]
[6]