7SeasMed
Located approximately 35 km off Marsala, Sicily. Grid landfall planned near Marsala.
Status
Early Developmentlifecycle stage
ProspectiveHafrok completion outlook
Ownership
GRGreenIT — 50% ◆
CICopenhagen Infrastructure Partners — 50% ◆
Location
Mediterranean Sea
Technology
Capacity
250 MW ◆
Turbines
21 × 12 MW ◇
Foundation
Floating ◆
Site & conditions
Site rights
Application filed 2024-03 ◇
Water depth
100–600 m ◇
Distance from shore
35 km ◆
Wind speed
7.5 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
Not recorded ◇
Connection
Landfall and connection to national transmission network … ◇
Schedule
FID
Not taken
COD · announced
2031 ◆
COD · Hafrok
2035 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2035
expected year of commercial operation
The developer says 2031; Hafrok expects 2035 — 4 years later.
Chance of delivery
≈56%
estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. This one sits below that: a market with a thinner delivery record and technical complexity. A secured offtake contract helps only slightly.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
| Year | Probability |
|---|---|
| 2034 | 14.1% |
| 2035 (expected) | 28.0% |
| 2036 | 22.7% |
| 2037 | 14.6% |
| 2038 | 8.7% |
| 2039 | 5.1% |
| 2040 | 3.1% |
| 2041 | 1.8% |
| 2042 | 1.1% |
| 2043 | 0.7% |
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (
2026), adds the time similar projects (floating, in developing offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before
2035 is not credible.3
Still needs an offtake award: IT-FER2-OFFSHORE
The project has no offtake contract yet. The next visible auction is around
2027 Q3; winners typically reach final investment decision about 2 years after an award (2029 Q3), then build time on top gives 2033 Q3. The milestone timing is already later than that, so it stands.4
Result
Expected commercial operation
2035, likely range 2035–2041 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈56%, which rates it
Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline verified milestones only — each date carries its provenance mark
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD.
Revenue & offtake route to market — open
No offtake secured — route to market open
Targeting Italy FER2 auction (Type E-1 competitive procedure). FER2 decree entered into force 13 August 2024 with €185/MWh tariff for offshore wind. First auction delayed; as of March 2025 project still awaiting launch of the FER2 auction framework. ◇
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
Italy first dedicated offshore auction (FER2 offshore contingent) ◇
stated by industry at Seanergy (May 2026) after informal MASE–Commission talks — strike-price revision by end-2026, auction "at the latest in 2027"; no MASE notice
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2031
Sources & verification
8/17 fields verified · rests on 8 sources (4 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator4
[1]
Copenhagen Offshore Partners2024-03-22◆ Copenhagen Offshore Partners | 7SeasMed …
"Yesterday, the 250MW 7SeasMed Floating Offshore Wind Project was granted approval of its Environmental Impact Assessment (EIA)" on March 22, 2024. The project is "owned by a consortium including Gree…
supportssponsorTotal capacityFoundation
[4]
Watson Farley & Williams2024-08◆ Italy’s new FER 2 Decree: focus on incen…
"On 12 August 2024, the new FER 2 decree...was published on the official website ...and entered into force on 13 August 2024." "Access to incentives for offshore wind power plants is reserved exclusiv…
supportsDetailOfftake history
[5]
Saipem2025-03-05◆ Saipem and Divento sign collaboration ag…
"The 7 Seas Med floating wind project, located in the Strait of Sicily over 35 km from the coast, with a capacity of 252 MW...awaiting the completion of the definition of the regulatory framework for …
supportsCommercial operationDistance from shore
[6]
Divento Energia2025◆ 7 Seas Med « Divento
"approximately 35 km from the coast in the Strait of Sicily" with "21 floating horizontal axis wind turbines with a power of 12 MW each." "landfall and connection to the National Electricity Transmiss…
supportsTurbinesUnit capacityStatusConnection pointWater depth+2 more
Auction pipeline1
[9]
reNEWS2026-05-20◆ renews-seanergy-fer2-strike-2026-05
Press report — cited, not quoted; read it at the source link.
supportsItaly first dedicated offshore auction (FER2 offshore contingent)
Trade press3
[2]
Ecquologia2024-03-21◆ Via libera al primo parco eolico offshor…
"Lo scorso 21 marzo, il progetto 7 Seas Med ha ricevuto il decreto di compatibilità ambientale (decreto VIA)." (On 21 March, the 7 Seas Med project received the environmental compatibility decree [VIA…
supportsConsentSite rightsConsent applied
[7]
offshoreWIND.biz2024-03-25
Press report — cited, not quoted; read it at the source link.
supportsBackground