Dieppe-Le Treport

AO2 Round 2 project. Located 17 km from Dieppe and 15.5 km from Le Treport, covering 110 km2.

Status
Under Constructionlifecycle stage
DeliveringHafrok completion outlook
Ownership
ENENGIE — 31% 
EDEDP Renewables — 29.5% 
SCSumitomo Corporation — 29.5% 
Location
France
English Channel
Technology
Capacity 496 MW  Turbines 62 × 8 MW  Model Siemens Gamesa SG 8-0-167 DD  Foundation Jacket 
Site & conditions
Site rights Seabed rights held 
Origination France Offshore Wind Round 2 (AO2) · 2014 ·
Water depth 14–25 m  Distance from shore 15.5 km  Wind speed 8.9 m/s @ 100 m 
Revenue & grid
Offtake FiT  Grid Secured · 2026-02-03  Connection Two 225 kV HVAC export cable circuits (each 23.5 km subsea) … 
Schedule
FID 26 Apr 2023  COD · announced 2026 
COD · Hafrok 2026 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2026
expected year of commercial operation
Chance of delivery
≈98% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; a market with a thinner delivery record and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2026: 86.7% (conditional on completion) 2027: 13.3% (conditional on completion)2026now87%2027 Developer-announced COD: 2026 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2026
COD probability by year, conditional on completion
YearProbability
2026 (expected)86.7%
202713.3%
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2024. From there Hafrok adds how long similar projects (in developing offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2027; the faster quarter of similar projects would be done by 2026, the slower quarter not until 2027 Q3.
3
Result
Expected commercial operation 2026, likely range 2026–2028 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2014’15’16’17’18’19’20’21’22’23’24’25’26Developer-announced COD: 2026 announced COD 2026France Offshore Wind Round 2 (AO2) — awarded to Engie + EDP RenewablesFrance Offshore Wind Round 2 (AO2) May 2014 · auction recordView the sources for Consent grantedConsent granted 26 Feb 2019 View the source for Final investment decisionFinal investment decision 26 Apr 2023 View the source for Offshore constructionOffshore construction Jun 2024 View the source for Onshore constructionOnshore construction 2024 Commercial operation 2026 ·Hafrok expectedFrance Offshore Wind Round 2 (AO2) — awarded to Engie + EDP Renewables 2014-05 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDEDP Renewables → Sumitomo Corporation — 13.5% · €21m 2018-12 FARMDOWN — 60.5% 2020-07 JV ENTRYTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYENGIE — 31% today ENGIE ENGIE 31%EDP Renewables — 29.5% today EDP Renewables EDP Renewables 29.5%Sumitomo Corporation — 29.5% today Sumitomo Corporation Sumitomo Corporation 29.5%Ocean Winds Ocean Winds Ocean Winds exited 2020-07Banque des Territoires — 10% today Banque des Territoires Banque des Territoires 10%France Offshore Wind Round 2 (AO2) — awarded to Engie + EDP Renewables Transfer(s) not in Hafrok's record — shown as a gap, never guessed. EDP Renewables → Sumitomo Corporation — 13.5% · €21m 13.5%Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake contract duration and price levels · money of the day

496 MW contracted — tender award
Tender award · France Offshore Wind Round 2 (AO2)
Price€131/MWh ·Capacity496 MWAwardedMay 2014
Term20 yrs

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations62 of 62100% · first seen 2025-04-14
Turbines3 of 625% · first seen 2026-07-24
Latest count2026-08-31from 330 satellite passes · 1 substation platform left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (62 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
20406063 planned (turbines and platforms)latest count 2026-08-31foundations — running total, confirmedfoundations — running total, seen in the last 60 days and not yet confirmedApr 2025 — 1 this month · 1 in totalJun 2025 — 1 this month · 2 in totalSep 2025 — 6 this month · 8 in totalOct 2025 — 5 this month · 13 in totalFeb 2026 — 8 this month · 21 in totalMar 2026 — 12 this month · 33 in totalApr 2026 — 4 this month · 37 in totalMay 2026 — 12 this month · 49 in totalJun 2026 — 14 this month · 63 in totalJul 2026 — 0 this month · 63 in totalAug 2026 — 0 this month · 63 in totalturbines up — running total, confirmedturbines up — running total, seen in the last 60 days and not yet confirmedApr 2025 — 0 this month · 0 in totalJun 2025 — 0 this month · 0 in totalSep 2025 — 0 this month · 0 in totalOct 2025 — 0 this month · 0 in totalFeb 2026 — 0 this month · 0 in totalMar 2026 — 0 this month · 0 in totalApr 2026 — 0 this month · 0 in totalMay 2026 — 0 this month · 0 in totalJun 2026 — 0 this month · 0 in totalJul 2026 — 1 this month · 1 in totalAug 2026 — 3 this month · 4 in total63 foundations4 turbines upApr 2025Sep 2025Feb 2026Apr 2026Jun 2026Aug 2026
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed63 confirmed · 0 not yet confirmedas counted on 2026-08-31 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortLe Havre ·turbine assembly · quay 400 m · draft 12 m
PortCherbourg ·foundation storage · draft 14 m
PortDieppe operations base
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (63)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Dieppe-Le Treport, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationDieppe Le Tréport offshore substation (poste électrique en mer)·under construction · owner unknown
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20252026Hafrok expects the farm to start in 2026developer’s stated start 2026nowDieppe Le Tréport offshore substation (poste électrique en mer)Dieppe Le Tréport offshore substa…platform installed 2025platform installed 2025

Sources & verification

18/19 fields verified · rests on 16 sources (11 primary) · ◆ 8 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator10
[1]
Eoliennes en Mer Dieppe Le Treport (EMDT)2026-06
“La société Éoliennes en Mer Dieppe Le Tréport est un consortium constitué de trois actionnaires : Ocean Winds (60,5%), Sumitomo Corporation (29,5%) et La Caisse des dépots (10%).”
supportsTurbinesUnit capacityTotal capacityDistance from shore
[2]
Ocean Winds2023-04-26◆ Dieppe Le Tréport offshore wind farm rea…
“Ocean Winds, Sumitomo Corporation, and la Banque des Territoires as shareholders of the company 'Eoliennes en Mer Dieppe Le Treport' (EMDT) ... The EMDT project represents an investment of around EUR …”
supportsFinal investment decisionCommercial operationTurbinesTotal capacity
[3]
Eoliennes en Mer Dieppe Le Treport (EMDT)2019-02-26
“Les préfets de la région Normandie, de la Seine-Maritime et de la Somme ont autorisé, par arrêtés du 26 février 2019, la réalisation du parc éolien en mer au large de Dieppe et du Tréport et de son ra…”
supportsConsentConsent granted
[4]
Légifrance / Préfet de Seine-Maritime2018-10-12
“Arrêté du 12 octobre 2018 autorisant la société Eoliennes en Mer de Dieppe-Le Tréport (EMDT) à exploiter une installation de production d'électricité ... d'une puissance de 496 MW ... dans le domaine …”
supportsConsentTotal capacityConsent granted
[5]
Ministère de la Transition écologique (France)2023◆ Eolien en mer — French government offsho…
“Les lauréats des appels d'offres éolien en mer signent un contrat d'achat avec EDF Obligation d'Achat (EDF OA) pour une durée de 20 ans, à un tarif fixé lors de l'appel d'offres.”
supportsMechanismDetail
[8]
Nexans2026-02-03
“Nexans has officially handed over both 225 kV HVAC export cable circuits of the Dieppe–Le Tréport offshore wind farm to its client RTE (Réseau de Transport d'Électricité). This milestone marks the for…”
supportsStatusConnection point
[9]
Eoliennes en Mer Dieppe Le Treport (EMDT)2026-06
“Turbine installation: April–July 2026. Commercial Operation Date: November 2026. Ports: Le Havre (turbine components), Cherbourg (foundations staging). Pile installation: June–December 2024.”
supportsOnshore constructionOffshore constructionturbine assemblyfoundation storageoperations base
[10]
Ocean Winds2026-06-15◆ Ocean Winds celebrates the installation …
“Ocean Winds has announced the successful installation of the first wind turbine at the Dieppe Le Tréport offshore wind farm. First power and electricity production expected in the coming weeks.”
supportsStatus note
[11]
Ocean Winds2025-09-10◆ Ocean Winds celebrates the successful in…
“Ocean Winds celebrates the successful installation of the first jacket foundation at the Dieppe – Le Tréport offshore wind farm. The foundations were loaded at the Port of Cherbourg and installed by D…”
supportsFoundationturbine assemblyfoundation storageoperations base
[15]
DGEC — Ministère de la Transition écologique (eoliennesenmer.fr)2026-08-25◆ French Eoliennes en mer register (DGEC),…
“Register node 852 (node--type-project) at /facades-maritimes-en-france/facade-manche-mer-du-nord/dieppe-le-treport — title 'Dieppe-Le Tréport'; page text 1904 chars, hash e75e5e396a5d093e…. Identifyin…”
supportsRegister entry
Auction results1
[17]
CRE (Commission de regulation de l'energie) / DGEC2013◆ fr-ao2-cahier-des-charges
AO2 cahier des charges (18 Feb 2013): Lot 1 Le Treport 500 MW, Lot 2 Yeu-Noirmoutier 500 MW.
supportsTender award · France Offshore Wind Round 2 (AO2)
Trade press5
[6]
Offshore Wind Biz2025-09-10
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacityTotal capacityFoundation+3 more
[7]
Offshore Wind Biz2025-07-02
Press report — cited, not quoted; read it at the source link.
supportsDistance from shoreCoordinates
[12]
Power Technology (GlobalData)2022-06◆ Dieppe-Le Treport Offshore Wind Farm
Press report — cited, not quoted; read it at the source link.
supportsWater depth
[13]
Ocean Winds2024◆ Dieppe Le Tréport offshore wind farm rea…
supportsowner
[14]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed