Tyrsky
Technology
Capacity
1,400 MW ◇
Turbines
95 ◇
Foundation
—
Site & conditions
Site rights
Not established we have not found a document granting or refusing rights over this seabed — a gap in our research, not a finding about the project ∅
Water depth
2–16 m ≈
Distance from shore
30 km ◇
Wind speed
8.4 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
—
Schedule
FID
Not taken
COD · developer
—
Delivery outlook not forecast
We don't put a delivery estimate on this project yet. No authority has granted rights to this site, so there is nothing to date a schedule from. That changes the moment the seabed is awarded, a consent application is filed, or the project is named in an auction.
Revenue & offtake route to market — open
No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take.
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageProposed
Offshore constructionnot started
Expected start of operationnot stated
Sources & verification
1/11 fields verified · rests on 7 sources · ◆ 1 document held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator3
[1]
[2]
[4]
Ingka Group2023-05-12
“Ingka Investments, the investment arm of Ingka Group, acquires a 49 percent share in three offshore wind development projects in Finland. [Halla, Laine and Tyrsky, Gulf of Bothnia]”
supportsdeveloperowner
Auction pipeline1
[7]
Metsähallitus2026-01◆ fi-ebba-edith-relaunch
Metsähallitus will continue Ebba/Edith development and relaunch the tender later.
supportsFinland Ebba & Edith re-tender
Trade press3
[3]
[5]
[6]