San Borondon
Located off southeast coast of Gran Canaria, Canary Islands. Iberdrola describes total programme as up to 300 MW of clean energy off the Spanish coast.
Technology
Capacity
238 MW ◇
Turbines
17 × 14 MW ◇
Foundation
Floating ◇
Site & conditions
Site rights
Not established we have not found a document granting or refusing rights over this seabed — a gap in our research, not a finding about the project ∅
Water depth
50–200 m ◇
Revenue & grid
Offtake
Other ◇
Grid
—
Schedule
FID
Not taken
COD · developer
2032 announced ◇
Delivery outlook not forecast
We don't put a delivery estimate on this project yet. No authority has granted rights to this site, so there is nothing to date a schedule from. That changes the moment the seabed is awarded, a consent application is filed, or the project is named in an auction.
Revenue & offtake route to market — open
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageProposed
Offshore constructionnot started
Expected start of operation2032
Construction ports
PortPuerto de La Luz (Las Palmas de Gran Canaria) ◇operations base
Sources & verification
1/14 fields verified · rests on 8 sources · ◆ 1 document held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator1
[1]
Iberdrola2021-06
“Iberdrola plans first industrial-scale floating offshore wind farm in Spain with an investment of more than €1 billion”
supportsCommercial operationFoundation
Auction pipeline1
[8]
MITECO (Spain)2026
RD 962/2024 framework; draft auction order consultation ran 4-24 Feb 2026 (two-sided CfD, floating, POEM zones); order not yet adopted, no call as of mid-2026. Target 1-3 GW by 2030.
supportsSpain first offshore wind auction
Trade press6
[2]
Canarias72021-06-03◆ Iberdrola prevé 17 molinos de 14 MW en e…
“17 turbines of 14 MW each... floating foundation systems (sistemas de cimentación flotante) on steel semi-submersible platforms... Area: 44 square kilometers, distance from shore: ~3 kilometres, water…”
supportsTurbinesUnit capacityFoundationWater depthoperations base
[3]
Enerdata2021-06-04
Press report — cited, not quoted; read it at the source link.
supportsConsentTotal capacity
[4]
Power Technology (GlobalData)
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacityTotal capacityFoundation
[5]
Offshore Wind Biz2026-02-04
Press report — cited, not quoted; read it at the source link.
supportsMechanismDetailOfftake history
[6]
Power Technology2024
Press report — cited, not quoted; read it at the source link.
supportsoperator
[7]