Thor

Denmark's largest offshore wind farm. Located 22 km west of Thorsminde, Jutland.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2027
expected year of commercial operation
Chance of delivery
≈98% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2027: 86.7% (conditional on completion) 2028: 13.3% (conditional on completion)2026now202787%2028 Developer-announced COD: 2027 — in line with Hafrok’s expected year ANNOUNCED = EXPECTED 2027developer cod guidance2021-12 → 2026-03: the developer guided 2027 in 7 statements — sources [2] [3] [4] [8] [17] [16] [9] — click for the sources2026-032027 · held since 2021-12 (×7) [2 +6]
COD probability by year, conditional on completion
YearProbability
2027 (expected)86.7%
202813.3%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2026-03-172027 (held since 2021-12-01, 7 statements)
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2024. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2026; the faster quarter of similar projects would be done by 2025, the slower quarter not until 2027.
3
Result
Expected commercial operation 2027, likely range 2025–2027 (the middle half of outcomes for similar projects). The developer's announced date falls inside that likely range, so the announced date is adopted.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈98%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2022’23’24’25’26’27Developer-announced COD: 2027 announced COD 2027Thor offshore wind tender — awarded to Thor Wind Farm I/S (RWE)Thor offshore wind tender Dec 2021 · auction recordView the sources for Onshore constructionOnshore construction 2024-Q4 View the sources for Offshore constructionOffshore construction Apr 2025 View the source for First powerFirst power 16 Mar 2026 Commercial operation 2027 ·Hafrok expectedThor offshore wind tender — awarded to Thor Wind Farm I/S (RWE) 2021-12 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDRWE → NBIM — 49.0% · closed 2025-06 2025-03 FARMDOWNTODAYThor Wind Farm I/S (RWE) Thor Wind Farm I/S Thor Wind Farm I/S not among today’s recorded owners — no sale recordedRWE — 51% today · operator RWE RWE 51%Norges Bank Investment Management — 49% today NBIM NBIM 49%Thor offshore wind tender — awarded to Thor Wind Farm I/S (RWE) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. RWE → NBIM — 49.0% · closed 2025-06 49%
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: held (announced 2027, unchanged) · the full guidance history is in the delivery chart above

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations72 of 72100% · first seen 2025-04-13
Turbines48 of 7267% · first seen 2025-07-19
Latest count2026-08-31from 347 satellite passes · 1 substation platform left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (72 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
20406073 planned (turbines and platforms)latest count 2026-08-31foundations — running total, confirmedfoundations — running total, seen in the last 60 days and not yet confirmedApr 2025 — 1 this month · 1 in totalMay 2025 — 9 this month · 10 in totalJun 2025 — 14 this month · 24 in totalJul 2025 — 25 this month · 49 in totalAug 2025 — 12 this month · 61 in totalSep 2025 — 12 this month · 73 in totalNov 2025 — 0 this month · 73 in totalDec 2025 — 0 this month · 73 in totalJan 2026 — 0 this month · 73 in totalFeb 2026 — 0 this month · 73 in totalMar 2026 — 0 this month · 73 in totalApr 2026 — 0 this month · 73 in totalMay 2026 — 0 this month · 73 in totalJun 2026 — 0 this month · 73 in totalJul 2026 — 0 this month · 73 in totalAug 2026 — 0 this month · 73 in totalturbines up — running total, confirmedturbines up — running total, seen in the last 60 days and not yet confirmedApr 2025 — 0 this month · 0 in totalMay 2025 — 0 this month · 0 in totalJun 2025 — 0 this month · 0 in totalJul 2025 — 2 this month · 2 in totalAug 2025 — 0 this month · 2 in totalSep 2025 — 1 this month · 3 in totalNov 2025 — 1 this month · 4 in totalDec 2025 — 1 this month · 5 in totalJan 2026 — 1 this month · 6 in totalFeb 2026 — 1 this month · 7 in totalMar 2026 — 6 this month · 13 in totalApr 2026 — 11 this month · 24 in totalMay 2026 — 12 this month · 36 in totalJun 2026 — 2 this month · 38 in totalJul 2026 — 6 this month · 44 in totalAug 2026 — 5 this month · 49 in total73 foundations49 turbines upApr 2025Jun 2025Aug 2025Nov 2025Jan 2026Mar 2026May 2026Jul 2026MPI Adventure · FoundationsBrave Tern · Turbines
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed73 confirmed · 0 not yet confirmedas counted on 2026-08-31 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Esbjerg ·turbines · quay 10000 m · crane 300 t · draft 15 m
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (73)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Thor, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationThor Offshore Substation·under construction · owner Thor Wind Farm I/S (RWE 51% / Norges Bank Investment Management 49%)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
202520262027Hafrok expects the farm to start in 2027developer’s stated start 2027nowThor Offshore SubstationThor Offshore Substationplatform installed 2025-07platform installed 2025-07

Sources & verification

18/19 fields verified · rests on 15 sources (15 primary) · ◆ 11 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
Energistyrelsen (Danish Energy Agency)2024-10-31◆ Thor establishment permit (etableringsti…
“Energistyrelsen har den 31. oktober 2024 givet etableringstilladelse til Thor Havvindmoellepark. Moellerne placeres med en afstand paa 22-34 kilometer ud for Thorsminde. Projektomraadet udgoer ca. 200…”
supportsConsentDistance from shoreCoordinates
[2]
Energistyrelsen (Danish Energy Agency)2021-12-01◆ DEA Thor result
“Thor Wind Farm I/S, where stakeholders are RWE AG, RWE Renewables GmbH, RWE Renewables Management UK Limited [won] following a historically low bid price ... a minimum price of only 0.01 oere/kWh ... …”
supportsMechanismDetail
[6]
Norwegian Environment Agency (Miljodirektoratet) — Espoo consultation2022-05-25
“Thor OWF is planned within a 220 km2 site approximately 22 km from the west coast of Jutland, off Thorsminde ... nominal installed capacity of approx. 1,000 MW ... a maximum of either 72 or 48 turbine…”
supportsFoundationDistance from shore
Operator7
[3]
RWE2021-12-01◆ Success in offshore auction: RWE secures…
“RWE secures concession for 1,000-megawatt wind farm off the Danish coast ... awarded the concession ... by the Danish Energy Agency ... scheduled to reach full operation in 2027 ... Denmark's largest …”
supportsTotal capacityMechanismDetail
[8]
RWE2024-10-31◆ First foundations for RWE’s Danish offsh…
“The Danish Energy Agency has granted RWE the offshore construction permit for its Danish offshore wind farm Thor ... Offshore work will begin - as planned - in spring 2025 ... Located approximately 22…”
supportsOnshore constructionOffshore constructionturbines
[9]
RWE2026-03-17◆ First generation at Thor offshore wind f…
“Shortly after the installation of the first turbine, Thor delivered electricity into the Danish grid for the first time. The grid is operated by Energinet ... 1.1-gigawatt project with RWE holding 51%…”
supportsFinal investment decisionFirst powerCOD historyStatusConnection point
[12]
RWE2025-06-04◆ Rwe and nbim jointly realise offshore wi…
“NBIM now holds a 49% equity stake in both the Nordseecluster and Thor offshore wind projects. RWE, with a 51% stake, remains in charge of construction and operations throughout the lifecycle of these …”
supportsoperatorowner
[15]
RWE2026-03-04◆ First turbine up at denmarks largest off…
“RWE has achieved a significant milestone in the construction of the 1.1-gigawatt Thor offshore wind farm by successfully installing the first turbine off Denmark's west coast near Jutland. ... Thor wi…”
supportsBrave Tern — turbine installation
[17]
RWE2025-11-11◆ Foundation installation works completed …
“RWE has completed the installation of the foundations for the 1.1-gigawatt Thor offshore wind farm in the Danish North Sea. In September, the final of 72 monopiles for the wind turbines was installed.…”
supportsOnshore constructionOffshore constructionMPI Adventure — foundation installation
[18]
RWE2025-04-30◆ Rwe installs first foundation at thor of…
“RWE has taken an important step in the construction of the 1.1 gigawatt (GW) Thor offshore wind farm in the Danish North Sea: the first of 72 monopile foundations has been successfully installed.”
supportsOnshore constructionOffshore construction
Financier1
[5]
European Investment Bank2024-06-25
“The EIB supports the construction of a new 1.1-Gigawatt wind farm ... with a loan of EUR 1.2 billion ... 72 wind turbines with 15 MW capacity each ... approximately 22 kilometres from Thorsminde ... T…”
supportsCommercial operationUnit capacityTotal capacityFoundationDistance from shore
OEM1
[4]
Siemens Gamesa2023-01-12◆ Tremendous Thor: RWE selects Siemens Gam…
“72 units of Siemens Gamesa's flagship SG 14-236 DD offshore wind turbines are planned to be installed ... It features a capacity of almost 15 MW ... 1,000-MW offshore wind power plant in Denmark. ... …”
supportsTurbinesModelUnit capacityTotal capacity
Record source1
[19]
Jan De Nul Group2025-04-30◆ first-foundation-denmarks-largest
...pril 2025, Jan De Nul kicked off the installation campaign of the monopile foundations for RWE’s Thor offshore wind farm. Heavy-lift vessel Les Alizés installed the first of 72 monopiles for Denmar…
supportsLes Alizés — foundation installation
Trade press2
[11]
NS Energy Business
Press report — cited, not quoted; read it at the source link.
supportsWater depth
[13]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed