Jammerland Bugt

Open-door project located south of Kalundborg, between Asnaes and Reerso peninsulas in the Great Belt area. 16 turbines at 256m height.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2032
expected year of commercial operation
The developer says 2029; Hafrok expects 2032 — 3 years later.
Chance of delivery
≈37% estimated chance this project reaches commercial operation
Advanced Development projects complete ≈75% of the time on Hafrok's record. This one sits well below that: technical complexity and no offtake contract yet. It is then halved while the majority stake has no sponsor: TotalEnergies announced its exit in 2026-08 and no successor is named.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2031: 14.1% (conditional on completion) 2032: 28.0% (conditional on completion) 2033: 22.7% (conditional on completion) 2034: 14.6% (conditional on completion) 2035: 8.7% (conditional on completion) 2036: 5.1% (conditional on completion) 2037: 3.1% (conditional on completion) 2038: 1.8% (conditional on completion) 2039: 1.1% (conditional on completion) 2040: 0.7% (conditional on completion)2026now202820292030203228%EXPECTED2034203620382040 Developer-announced COD: 2029 ANNOUNCED 2029
COD probability by year, conditional on completion
YearProbability
203114.1%
2032 (expected)28.0%
203322.7%
203414.6%
20358.7%
20365.1%
20373.1%
20381.8%
20391.1%
20400.7%
How Hafrok got this date
1
Starting point: the last dated milestone
Consent granted in 2024. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2028; the faster quarter of similar projects would be done by 2026, the slower quarter not until 2029.
3
Merchant project — financing counted from today
The project has no offtake contract yet. This project's route offers no support scheme: it has to sign a power contract and take a financing decision on its own, and Hafrok counts that from today (2026 Q3) rather than from a tender it cannot enter. The permits are not affected; winners typically reach final investment decision about 2 years after an award (2028 Q3), then build time on top gives 2031 Q3. That is later than the milestone timing, so the auction sets the date.
4
Result
Expected commercial operation 2032, likely range 2031–2033 (the middle half of outcomes for similar projects). The developer's announced date (2029) is earlier than similar projects have managed — Hafrok's own date is used and the difference is flagged above.
5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Advanced Development projects that went on to complete — ≈75%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Consented projects have historically completed at very high rates, but the 2023–25 downturn showed consented-but-unfinanced projects can still fail — the estimate holds back for the offtake and financing gates still ahead. Then adjust for this project's own evidence — offtake, market, size, technical complexity — and halve the result while the majority stake has no sponsor (TotalEnergies announced its exit in 2026-08; no successor is named — from the ownership ledger, cleared the day a buyer is recorded) — to ≈37%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2025’26’27’28’29’30’31’32Developer-announced COD: 2029 announced COD 2029View the source for Consent grantedConsent granted 17 Dec 2024 Commercial operation 2032 ·Hafrok expectedNo origination on record — who held the site before the first recorded deal is not known; shown as a gap, never guessed. UNRECORDEDEuropean Energy / SONFOR → TotalEnergies — 85.0% · closed 2024-12 2024-01 FARMDOWNTotalEnergies → None — 85% 2026-08 DIVESTMENTTODAYEuropean Energy — 15% today European Energy European Energy 15%SONFOR SONFOR SONFOR exited 2024-01TotalEnergies — 85% today TotalEnergies TotalEnergies 85%European Energy / SONFOR → TotalEnergies — 85.0% · closed 2024-12 European Energy / SONFOR → TotalEnergies — 85.0% · closed 2024-12 85% → consortium
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. Ownership lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.

Revenue & offtake route to market — open

No offtake secured — route to market open

Open-door nearshore; electricity to be sold on the wholesale electricity market or through Corporate PPAs (CPPAs) per developer. No signed offtake contract as of 2026-06-15. Not a CfD route.

The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
Nordsøen Syd (North Sea South)
expected H2 2028 · planned · the round’s published documents do not name this project
announced

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageAdvanced Development
Offshore constructionnot started
Expected start of operation2029

Sources & verification

5/14 fields verified · rests on 12 sources (4 primary) · ◆ 4 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[3]
Energistyrelsen (Danish Energy Agency)2024-12-17◆ Energistyrelsen giver tilladelse til at …
“Energistyrelsen udsteder etableringstilladelse til Jammerland Bugt Kystnær Havmøllepark ... projektet vil have en samlet kapacitet på 240 MW ... Tilslutningspunktet bliver Energinets eksisterende højs…”
supportsConsentSite rightsTotal capacityConsent granted
Operator4
[4]
TotalEnergies2024-01-23◆ Renewables: TotalEnergies and European E…
“acquisition by TotalEnergies of a 85% equity stake in the Jammerland Bugt offshore wind project (240 MW) ... have obtained exclusivity and grid connection permits ... The electricity generated by thes…”
supportsDetailStatusConnection pointOfftake history
[5]
European Energy2024-12-20
“TotalEnergies acquired 85 per cent of the share capital in the 240 MW Jammerland Bay ... European Energy will continue to be a minority owner in Jammerland Bay offshore wind farm ... the offshore park…”
supportsCommercial operation
[7]
European Energy2024-12◆ TotalEnergies, European Energy and SONFO…
supportsowner
[8]
European Energy2025-03
supportsTurbinesUnit capacityTotal capacity
Auction pipeline1
[15]
Danish Energy Agency (Energistyrelsen)2025-11◆ dea-3-tenders-2025
DEA — Nordsøen Syd, >=1,000 MW, bid deadline autumn 2028.
supportsNordsøen Syd (North Sea South)
Trade press5
[9]
offshoreWIND.biz2024-12
Press report — cited, not quoted; read it at the source link.
supportsTurbinesFoundation
[10]
4C Offshore2025
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[11]
Global Energy Monitor2026-07-02
supportsCoordinates
[12]
GEBCO Compilation Group2020
supportsWater depth
[13]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsTurbinesUnit capacityTotal capacityFoundationWater depth+1 more