Veja Mate

Located 95km NW of Borkum. Originally CIP/Highland Group; current owners acquired 2019-2022.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2010’11’12’13’14’15’16’17’18’19’20’21’22’23’24’25’26View the source for Consent grantedConsent granted Aug 2009 Permit holder: Cuxhaven Steel Construction GmbH — held by BARD Holding GmbH per the record's source 'augusta-bard-veja-mate-sale-2014'. BSH Genehmigung Veja Mate, 31 Aug 2009 — 'Auf den Antrag der Cuxhaven Steel Construction GmbH … vom 03.08.2007 in der Fassung vom 20.10.2008 werden Errichtung und Betrieb von 80 Windenergieanlagen … genehmigt.' (a BARD-group company). Owner: BARD Holding GmbH sold 'its Veja Mate offshore wind project' in 2014; Cuxhaven Steel Construction GmbH is a BARD-group company. The owner is as of the FIRST held document (2014), not asserted for the 2009 grant.Party of record at origination Aug 2009 · auction recordView the source for Final investment decisionFinal investment decision Jul 2015 View the source for Offshore constructionOffshore construction Apr 2016 View the sources for First powerFirst power Jan 2017 View the sources for Commercial operationCommercial operation May 2017 Permit holder: Cuxhaven Steel Construction GmbH — held by BARD Holding GmbH per the record's source 'augusta-bard-veja-mate-sale-2014'. BSH Genehmigung Veja Mate, 31 Aug 2009 — 'Auf den Antrag der Cuxhaven Steel Construction GmbH … vom 03.08.2007 in der Fassung vom 20.10.2008 werden Errichtung und Betrieb von 80 Windenergieanlagen … genehmigt.' (a BARD-group company). Owner: BARD Holding GmbH sold 'its Veja Mate offshore wind project' in 2014; Cuxhaven Steel Construction GmbH is a BARD-group company. The owner is as of the FIRST held document (2014), not asserted for the 2009 grant. 2009-08 ORIGINATIONBARD Holding GmbH → Highland Group Holdings (Laidlaw Capital Group) — 100% · closed 2014-11 2014-09-11 ACQUISITIONHighland Group Holdings (Laidlaw Capital Group) → Siemens Financial Services / Copenhagen Infrastructure Partners — stake not disclosed · closed 2015-07 2015-07-01 JV ENTRYHighland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 2019-02 DIVESTMENTSiemens Financial Services → Commerz Real / KGAL / Ingka Group — 20.0% · €132m · closed 2022-09 2022-07 TODAYBARD Holding GmbH BARD Holding GmbH BARD Holding GmbH exited 2014-09-11Highland Group Holdings (Laidlaw Capital Group) Highland Group Holdings Highland Group Holdings exited 2019-02Siemens Financial Services Siemens Financial Servi… Siemens Financial Servi… exited 2022-07Copenhagen Infrastructure Partners CIP CIP exited 2019-02Commerz Real — 36% today · operator Commerz Real Commerz Real 36%Ingka Investments — 33% today · co-owner Ingka Group Ingka Group 33%KGAL — 31% today · co-owner KGAL KGAL 31%wpd invest wpd invest wpd invest exited 2019-02Permit holder: Cuxhaven Steel Construction GmbH — held by BARD Holding GmbH per the record's source 'augusta-bard-veja-mate-sale-2014'. BSH Genehmigung Veja Mate, 31 Aug 2009 — 'Auf den Antrag der Cuxhaven Steel Construction GmbH … vom 03.08.2007 in der Fassung vom 20.10.2008 werden Errichtung und Betrieb von 80 Windenergieanlagen … genehmigt.' (a BARD-group company). Owner: BARD Holding GmbH sold 'its Veja Mate offshore wind project' in 2014; Cuxhaven Steel Construction GmbH is a BARD-group company. The owner is as of the FIRST held document (2014), not asserted for the 2009 grant. BARD Holding GmbH → Highland Group Holdings (Laidlaw Capital Group) — 100% · closed 2014-11 100%Highland Group Holdings (Laidlaw Capital Group) → Siemens Financial Services / Copenhagen Infrastructure Partners — stake not disclosed · closed 2015-07 Highland Group Holdings (Laidlaw Capital Group) → Siemens Financial Services / Copenhagen Infrastructure Partners — stake not disclosed · closed 2015-07 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 Highland Group Holdings / Siemens Financial Services / CIP → Commerz Real / Ingka Group / KGAL / wpd invest — 80.0% · closed 2019-05 80% → consortiumSiemens Financial Services → Commerz Real / KGAL / Ingka Group — 20.0% · €132m · closed 2022-09 Siemens Financial Services → Commerz Real / KGAL / Ingka Group — 20.0% · €132m · closed 2022-09 Siemens Financial Services → Commerz Real / KGAL / Ingka Group — 20.0% · €132m · closed 2022-09 20% → consortium
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 2017-Q22017-05 · 2 recorded revisions · held (announced 2017-Q2, unchanged)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite survey
the farm as it stands, counted from satellite radar images · built before the count began, so there is no build to chart
Satellite survey
Structures standing6867 turbines + 2 platforms expected · 1 fewer than expected — a position the survey missed
Surveyed2026-08-31from 115 satellite passes
Built2016-04 → 2017-05offshore construction to start of operation, from the record
Hafrok counts the structures standing in the sea from satellite radar images (≈) and reads the count against the turbines and platforms on record. The farm was built before this count began, so the images show it complete; they cannot date its construction. Rows marked with a dot (·) come from Hafrok’s own registers.
Satellite image
Image taken2026-09-06Copernicus Sentinel-1 radar satellite, southbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed68 confirmed · 0 not yet confirmedas counted on 2026-08-31 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortEsbjerg ·installation · quay 10000 m · crane 300 t · draft 15 m
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-06
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (68)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Veja Mate, 2026-09-06
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 2
Offshore substationVeja Mate Offshore Substation·155 kV · in service 2016 · owner Veja Mate wind farm owners — Highland Group Holdings, Siemens Financial Services and Copenhagen Infrastructure Partners' CI II (farm-owned platform)
HVDC systemBorWin2·800 MW · ±300 kV · in service 2015-01 · shared with Albatros, Deutsche Bucht
Converter supplierSiemens (HVDC PLUS); Prysmian cables·BorWin2 · Nordic Yards, Warnemünde, Germany · for TenneT
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20132014201520162017201820192020202120222023202420252026developer’s stated start 2017-Q2nowBorWin2BorWin2first planned 2013first planned 2013in service 2015-01in service 2015-01Veja Mate Offshore SubstationVeja Mate Offshore Substationin service 2016in service 2016

Sources & verification

16/18 fields verified · rests on 11 sources (5 primary) · ◆ 6 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
Bundesamt fuer Seeschifffahrt und Hydrographie (BSH)2009-08◆ Genehmigungsbescheid Offshore-Windpark V…
“Hamburg, den 31.08.2009 — Auf den Antrag der Cuxhaven Steel Construction GmbH [...] vom 03.08.2007 in der Fassung vom 20.10.2008 werden Errichtung und Betrieb von 80 Windenergieanlagen (WEA) einschlie…”
supportsConsentWater depthCoordinatesConsent granted
[12]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "OWP Veja Mate": 67 units, 422.1 MW gross, statuses {'In Betrieb': 67}, operators ['Veja Mate Offshore Project GmbH'], commissioned 2017-01-18..2017-05-31, planned None..None.”
supportsRegister entry
Operator2
[3]
Copenhagen Offshore Partners (COP)2017-01◆ Copenhagen Offshore Partners | Important…
“the first Siemens 6MW wind turbine has started supplying the German electricity grid [...] two months ahead of schedule. [...] Construction started on April 4, 2016, and financial close was reached on…”
supportsOffshore constructionFirst powerSite rightsStatusConnection point+1 more
[4]
Copenhagen Offshore Partners (COP)2017-05-31◆ Copenhagen Offshore Partners | Veja Mate…
“Veja Mate Offshore Wind Farm completes construction in 23 months. 402 MW, 67 units, Siemens SWT-6.0-154 model. Financial Close: July 1, 2015. Construction start: April 4, 2016. Completed in less than …”
supportsCommercial operationCOD historyTurbinesModelUnit capacity+1 more
Trade press7
[2]
Offshore Wind Biz2015-07-02◆ SgurrEnergy Supports Veja Mate Financial…
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decisionTurbinesModelUnit capacityFoundation+1 more
[5]
Offshore Wind Biz2017-05-31
Press report — cited, not quoted; read it at the source link.
supportsFirst powerCommercial operation
[6]
Offshore Wind Biz2019-02-13
Press report — cited, not quoted; read it at the source link.
supportsBackground
[7]
Offshore Wind Biz2022-07-11◆ Siemens Financial Services Sells Its Sta…
Press report — cited, not quoted; read it at the source link.
supportsoperatorco-owner
[8]
Watson Farley & Williams LLP2022-07-13
“The consortium's joint venture company VM Offshore Beteiligungsgesellschaft mbH ('VMOB') now holds 100% of the shares in VMOP [Veja Mate Offshore Project GmbH]. [...] A consortium consisting of Commer…”
supportsBackground
[9]
Fraunhofer IEE (windmonitor.de)2024
“Offshore-Windanlagen, die vor dem 1. Januar 2020 in Betrieb gehen, koennen alternativ zum regulaeren Anfangsvergaetungssatz einen erhoehten Anfangssatz nach dem 'Stauchungsmodell' von 19,4 ct/kWh fuer…”
supportsMechanismDetail
[10]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed