N-6.7 (Waterkant)
90 km from Borkum. Initially partnered with Ming Yang for 16x 18.5 MW turbines, switched to Siemens Gamesa for economic efficiency and supply chain reasons.
Status
Early Developmentlifecycle stage
ExpectedHafrok completion outlook
Ownership
LULuxcara — 100% ◇
Location
North Sea
Technology
Capacity
300 MW ◆
Turbines
—
Foundation
—
Site & conditions
Site rights
Seabed rights held ∴
Origination
BNetzA Offshore Wind Auction 2023 (central model, qualitative) · 2023 ·
Water depth
39–41 m ≈
Distance from shore
90 km ◇
Wind speed
10.3 m/s @ 150 m ≈
Revenue & grid
Offtake
Merchant ◆
Grid
Not recorded ◆
Connection
Grid connection via TenneT planned for end of 2028. ◆
Schedule
FID
Not taken
COD · announced
2028 ◆
COD · Hafrok
2033 expected
Delivery outlook modelled by Hafrok · calibrated on delivered projects
2033
expected year of commercial operation
The developer says 2028; Hafrok expects 2033 — 5 years later.
Chance of delivery
≈66%
estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. A secured offtake contract puts this one well above that; technical complexity weighs only slightly against it.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
| Year | Probability |
|---|---|
| 2032 | 14.1% |
| 2033 (expected) | 28.0% |
| 2034 | 22.7% |
| 2035 | 14.6% |
| 2036 | 8.7% |
| 2037 | 5.1% |
| 2038 | 3.1% |
| 2039 | 1.8% |
| 2040 | 1.1% |
| 2041 | 0.7% |
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (
2026), adds the time similar projects (in established offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before
2033 is not credible.3
Result
Expected commercial operation
2033, likely range 2033–2039 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈66%, which rates it
Expected on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record
Origination · 2023-08
BNetzA Offshore Wind Auction 2023 (central model, qualitative)
- Awarded to
- Waterkant Energy GmbH
- Basis
- integrated tender
From the auction results — the round that created the project.
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Revenue & offtake route to market — open
No offtake secured — route to market open
Zero-subsidy BNetzA auction (August 2023); no offtake contract exists. ◇
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
Germany offshore tender — 2027 (FEP cluster) ◇
indicative
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2028
Sources & verification
4/12 fields verified · rests on 11 sources (2 primary) · ◆ 3 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[2]
[5]
Bundesamt für Seeschifffahrt und Hydrographie (BSH)2023-01-05◆ BSH - N-6.7
“Die Eignungsfeststellung für die Fläche N-6.7 wurde durch Rechtsverordnung vom 5. Januar 2023 festgestellt. Die BNetzA hat die Ausschreibung für die Fläche N-6.7 am 27. Februar 2023 bekannt gemacht.”
supportsConsent
Operator4
[3]
Luxcara2023-08
“Waterkant Energy [won] site N-6.7 … 270 MW offshore wind farm in the German North Sea … The project can be connected to the national transmission grid as early as 2028. … the first time in Germany, th…”
supportsCommercial operationStatusConnection point
[4]
Luxcara2025-08-25
“Luxcara has additionally reserved 19 turbines of the same type [15.5 MW SG 14-236 DD] … the neighboring Waterkant project (approximately 300 MW) … grid connection end of 2028.”
supportsCommercial operationTotal capacity
[6]
[7]
Auction pipeline1
[11]
Bundesnetzagentur2026◆ bnetza-noncentral-2027
BNetzA — 2026 non-central offshore tenders suspended; N-10.1/N-10.2/N-12.4/N-12.5/N-13.1/N-13.2 moved to tender year 2027.
supportsGermany offshore tender — 2027 (FEP cluster)
Trade press3
[8]
4C Offshore2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[9]
[10]
Unverified import1
[1]