N-12.3

BNetzA auction result June 2024. Grid connection target end of 2030.

Status
Early Developmentlifecycle stage
ProspectiveHafrok completion outlook
Ownership
EOEnBW Offshore Projektgesellschaft 1 GmbH — 100% 
Location
Germany
North Sea
Technology
Capacity 1,000 MW 
Turbines
Foundation Monopile 
Site & conditions
Site rights Seabed rights held 
Origination BNetzA Offshore Wind Auction 2024 (dynamic bidding / concession) · 2024 ·
Water depth 38–43 m  Wind speed 10.4 m/s @ 150 m 
Revenue & grid
Offtake Merchant  Grid Offered · 2024-06  Connection Statutory TSO grid connection right under WindSeeG §12 granted … 
Schedule
FID Not taken
COD · announced 2032 
COD · Hafrok 2033 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2033
expected year of commercial operation
The developer says 2032; Hafrok expects 2033 — 1 year later.
Chance of delivery
≈64% estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. A secured offtake contract lifts this one above that; its size and technical complexity pull the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2032: 14.1% (conditional on completion) 2033: 28.0% (conditional on completion) 2034: 22.7% (conditional on completion) 2035: 14.6% (conditional on completion) 2036: 8.7% (conditional on completion) 2037: 5.1% (conditional on completion) 2038: 3.1% (conditional on completion) 2039: 1.8% (conditional on completion) 2040: 1.1% (conditional on completion) 2041: 0.7% (conditional on completion)2026now202820302032203328%EXPECTED2034203620382040 Developer-announced COD: 2032 ANNOUNCED 2032developer cod guidance2026-03-18: the developer guided 2032 — source [8] — click for it2026-032032 [8]2026-06-16: the developer guided 2031 — source [2] — click for it2026-062031 [2]
COD probability by year, conditional on completion
YearProbability
203214.1%
2033 (expected)28.0%
203422.7%
203514.6%
20368.7%
20375.1%
20383.1%
20391.8%
20401.1%
20410.7%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2026-03-182032
2026-06-162031
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (2026), adds the time similar projects (in established offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.
2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before 2033 is not credible.
3
Result
Expected commercial operation 2033, likely range 2033–2039 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈64%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2025’26’27’28’29’30’31’32’33Developer-announced COD: 2032 announced COD 2032BNetzA Offshore Wind Auction 2024 (dynamic bidding / concession) — awarded to EnBW Offshore Projektgesellschaft 1 GmbHBNetzA Offshore Wind Auction 2024 (dynamic bidding / concession) Jun 2024 · auction recordCommercial operation 2033 ·Hafrok expectedBNetzA Offshore Wind Auction 2024 (dynamic bidding / concession) — awarded to EnBW Offshore Projektgesellschaft 1 GmbH 2024-06 ORIGINATIONTODAYEnBW Offshore Projektgesellschaft 1 GmbH — 100% today · operator EnBW Offshore Projektge… EnBW Offshore Projektge… 100%BNetzA Offshore Wind Auction 2024 (dynamic bidding / concession) — awarded to EnBW Offshore Projektgesellschaft 1 GmbH
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD. The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced COD: pulled forward -1.0 yr (first announced 2032) · the full guidance history is in the delivery chart above

Revenue & offtake route to market — open

No offtake secured — route to market open

Zero-subsidy BNetzA dynamic-bidding auction, June 2024, 55 bidding rounds. EnBW Offshore Projektgesellschaft 1 GmbH bid EUR 1.065 million/MW (total EUR 1.065 billion) with zero cents/kWh subsidy. EnBW plans future PPAs with industrial customers; no PPA has been confirmed signed as of 2026-06-16.

The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
Germany offshore tender — 2027 (FEP cluster)
expected 2027 · planned · the round’s published documents do not name this project
indicative

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2032

Sources & verification

7/13 fields verified · rests on 10 sources (3 primary) · ◆ 5 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[2]
Bundesnetzagentur (Federal Network Agency)2024-06-21◆ Bundesnetzagentur - Press - Results of d…
"EnBW Offshore Projektgesellschaft 1 GmbH with a bid of €1.065mn/MW for N 12.3." "The two offshore sites, which have a capacity of 1,500 MW and 1,000 MW respectively, are located about 120 km north-we…
supportsoperatorConsentCommercial operationCOD historyTotal capacity+5 more
Operator3
[3]
EnBW Energie Baden-Württemberg AG2024-06-21◆ EnBW awarded contract for offshore wind …
"The wind farm is set to enter operation 120 km northwest of Heligoland in 2031." "EnBW plans to sell much of the electricity produced by the offshore wind farm to industrial customers in the future t…
supportsCommercial operationTotal capacityMechanismDetail
[8]
EnBW2026-03-18◆ EnBW completes ground investigations for…
“The Dreekant offshore wind farm is set to go online 120 km northwest of Heligoland in 2032. ... "The data obtained is essential for planning the foundations. We are pleased that it is possible to use …”
supportsCommercial operationFoundation
[9]
EnBW Energie Baden-Württemberg AG2024-06◆ EnBW awarded contract for offshore wind …
"EnBW won the contract for a one gigawatt (GW) offshore wind farm in the North Sea." (EnBW erhaelt Zuschlag fuer 1-GW-Offshore- Windpark; the BNetzA result names the winning bidder as EnBW Offshore Pr…
supports↳ parents
Auction pipeline1
[10]
Bundesnetzagentur2026◆ bnetza-noncentral-2027
BNetzA — 2026 non-central offshore tenders suspended; N-10.1/N-10.2/N-12.4/N-12.5/N-13.1/N-13.2 moved to tender year 2027.
supportsGermany offshore tender — 2027 (FEP cluster)
Trade press4
[4]
offshoreWIND.biz2024
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[5]
4C Offshore2026-07-02
Press report — cited, not quoted; read it at the source link.
supportsCoordinates
[6]
GEBCO Compilation Group2020
supportsWater depth
[7]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
Press report — cited, not quoted; read it at the source link.
supportsTotal capacityWater depthCoordinates