Baltic Eagle

Located 27-30km northeast of Rugen Island. Connected to 50Hertz Ostwind 2 (shared with Arcadis Ost 1).

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2018’19’20’21’22’23’24’25’26BNetzA Offshore Wind Auction 2018 (transitional) — awarded to Iberdrola (Baltic Eagle GmbH)BNetzA Offshore Wind Auction 2018 (transitional) Apr 2018 · auction recordView the source for Consent grantedConsent granted Apr 2022 View the source for Onshore constructionOnshore construction 2022 View the sources for Commercial operationCommercial operation 2025-Q3 BNetzA Offshore Wind Auction 2018 (transitional) — awarded to Iberdrola (Baltic Eagle GmbH) 2018-04 ORIGINATIONIberdrola → Masdar — 49.0% · €375m · closed 2024-Q1 2023-07 FARMDOWNTODAYIberdrola — 51% today · operator Iberdrola Iberdrola 51%Masdar — 49% today · co-investor Masdar Masdar 49%BNetzA Offshore Wind Auction 2018 (transitional) — awarded to Iberdrola (Baltic Eagle GmbH) Iberdrola → Masdar — 49.0% · €375m · closed 2024-Q1 49%
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 202420242025-07 · 3 recorded revisions · slipped +1.0 yr (first announced 2024)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations50 of 50100% · first seen 2022-10-16 · 8 more than the record expects — a met mast, a platform not on the register, or a survey artefact
Turbines50 of 50100% · first seen 2023-05-08
Latest count2026-08-29from 650 satellite passes · 1 substation platform left out so the counts compare with the turbine number · anything first seen in the last 60 days is not yet confirmed
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (50 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
204051 planned (turbines and platforms)latest count 2026-08-29foundations — running total, confirmedOct 2022 — 1 this month · 1 in totalApr 2023 — 1 this month · 2 in totalMay 2023 — 9 this month · 11 in totalJun 2023 — 7 this month · 18 in totalJul 2023 — 8 this month · 26 in totalAug 2023 — 25 this month · 51 in totalApr 2024 — 0 this month · 51 in totalMay 2024 — 0 this month · 51 in totalJun 2024 — 0 this month · 51 in totalJul 2024 — 1 this month · 52 in totalAug 2024 — 0 this month · 52 in totalSep 2024 — 0 this month · 52 in totalOct 2024 — 0 this month · 52 in totalFeb 2025 — 0 this month · 52 in totalMar 2025 — 0 this month · 52 in totalApr 2025 — 0 this month · 52 in totalMay 2025 — 2 this month · 54 in totalJun 2025 — 2 this month · 56 in totalJul 2025 — 2 this month · 58 in totalAug 2025 — 1 this month · 59 in totalturbines up — running total, confirmedOct 2022 — 0 this month · 0 in totalApr 2023 — 0 this month · 0 in totalMay 2023 — 1 this month · 1 in totalJun 2023 — 0 this month · 1 in totalJul 2023 — 0 this month · 1 in totalAug 2023 — 0 this month · 1 in totalApr 2024 — 3 this month · 4 in totalMay 2024 — 11 this month · 15 in totalJun 2024 — 12 this month · 27 in totalJul 2024 — 9 this month · 36 in totalAug 2024 — 6 this month · 42 in totalSep 2024 — 5 this month · 47 in totalOct 2024 — 1 this month · 48 in totalFeb 2025 — 1 this month · 49 in totalMar 2025 — 1 this month · 50 in totalApr 2025 — 1 this month · 51 in totalMay 2025 — 0 this month · 51 in totalJun 2025 — 0 this month · 51 in totalJul 2025 — 0 this month · 51 in totalAug 2025 — 0 this month · 51 in total59 foundations51 turbines upOct 2022Jun 2023Apr 2024Jul 2024Oct 2024Apr 2025Jul 2025
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed59 confirmed · 0 not yet confirmedas counted on 2026-08-29 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Sassnitz-Mukran ~30km ·installation and operations · draft 13.5 m
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (59)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Baltic Eagle, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationBaltic Eagle Offshore Substation (OSS)·220/66 kV · in service 2023 · owner Iberdrola (wind farm owner; farm-owned platform, not TSO-owned)
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
2023202420252026developer’s stated start 2025-Q3nowBaltic Eagle Offshore Substation (OSS)Baltic Eagle Offshore Substation …in service 2023in service 2023

Sources & verification

17/18 fields verified · rests on 11 sources (5 primary) · ◆ 4 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
Bundesamt fuer Seeschifffahrt und Hydrographie (BSH)2022-04-22◆ Planfeststellungsbeschluss Offshore-Wind…
“BSH Az: 5111/Baltic Eagle/PFV Rostock, den 22. April 2022 Planfeststellungsbeschluss […] (1) 50 (fuenfzig) Offshore Windenergieanlagen (OWEA) mit folgenden Parametern: […] Nennleistung je WEA: 9,525 M…”
supportsConsentTurbinesModelUnit capacityTotal capacity+5 more
[14]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Baltic Eagle": 50 units, 476.25 MW gross, statuses {'In Betrieb': 50}, operators ['Baltic Eagle GmbH'], commissioned 2024-05-02..2024-09-21, planned None..None.”
supportsRegister entry
Operator2
[3]
Masdar2023-11-02◆ Masdar | Iberdrola and Masdar close thei…
"Following confirmation that all the necessary regulatory approvals have been received, Iberdrola will have a majority stake of 51% in the project. [...] minimum regulated tariff of EUR 64.6/MWh for t…
supportsMechanismStrike / priceDetail
[8]
Iberdrola2025-07-10
supportsCommercial operation
Trade press7
[5]
offshoreWIND.biz2022-04-25
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decisionOnshore construction
[6]
offshoreWIND.biz2021-06-30
Press report — cited, not quoted; read it at the source link.
supportsTurbinesModelUnit capacity
[7]
offshoreWIND.biz2024-03-18
Press report — cited, not quoted; read it at the source link.
supportsStrike / price
[9]
offshoreWIND.biz2025-07-10◆ Baltic Eagle Offshore Wind Farm Fully En…
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationCOD history
[10]
Power Technology2024-03-01
Press report — cited, not quoted; read it at the source link.
supportsStatusConnection pointinstallation and operations
[11]
Power Technology2023-11
Press report — cited, not quoted; read it at the source link.
supportsoperatorco-investor
[12]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed