Arcadis Ost 1

Located 19km northeast of Rugen Island. Connected to 50Hertz Ostwind 2 system.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok’s transactions record

2018’19’20’21’22’23’24’25’26BNetzA Offshore Wind Auction 2018 (transitional) — awarded to KNK Wind GmbH (acquired by Parkwind → built as Arcadis Ost 1)BNetzA Offshore Wind Auction 2018 (transitional) Apr 2018 · auction recordView the source for Consent grantedConsent granted Mar 2021 View the source for Final investment decisionFinal investment decision Jun 2021 View the sources for Offshore constructionOffshore construction Jun 2022 View the sources for First powerFirst power Jan 2023 View the sources for Commercial operationCommercial operation Dec 2023 BNetzA Offshore Wind Auction 2018 (transitional) — awarded to KNK Wind GmbH (acquired by Parkwind → built as Arcadis Ost 1) 2018-04 ORIGINATIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDVirya Energy (Colruyt Group) → JERA — 100.0% · closed 2023-07 2023-03 ACQUISITIONTransfer(s) not in Hafrok's record — shown as a gap, never guessed. UNRECORDEDTODAYKNK Wind GmbH (acquired by Parkwind → built as Arcadis Ost 1) KNK Wind GmbH KNK Wind GmbH not among today’s recorded owners — no sale recordedVirya Energy (Colruyt Group) Virya Energy Virya Energy exited 2023-03JERA JERA JERA exited 2023-03Parkwind Ost GmbH — 100% today · operator Parkwind Ost GmbH Parkwind Ost GmbH 100%BNetzA Offshore Wind Auction 2018 (transitional) — awarded to KNK Wind GmbH (acquired by Parkwind → built as Arcadis Ost 1) Transfer(s) not in Hafrok's record — shown as a gap, never guessed. Virya Energy (Colruyt Group) → JERA — 100.0% · closed 2023-07 100%Transfer(s) not in Hafrok's record — shown as a gap, never guessed.
Dashed tick marks today (9 Sep 2026). The teal diamond on the spine is origination — the seabed award or round that created the project. Every other ownership event lives in the band below: one station per recorded deal, dated at its label, in deal order rather than to calendar scale. Secondary trades appear only at the interchanges; grey lines are parties whose entry or exit Hafrok’s record does not hold.
Announced-COD history: 20232023-12 · 2 recorded revisions · slipped +0.5 yr (first announced 2023)

Revenue & offtake the regime the project was built under

Offtake regime on record
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Satellite installation tracker
counted from satellite radar images · a structure standing in the sea on a given date, not a turbine producing power · a guide, not a sourced fact
Installation · counted from satellite
Foundations27 of 27100% · first seen 2022-06-08
Turbines25 of 2793% · first seen 2022-07-26
Latest count2024-12-30from 307 satellite passes · 1 substation platform left out so the counts compare with the turbine number · the count has ended: the build is complete
Hafrok counts foundations and turbines from satellite radar images (≈): a structure is counted once it is seen standing in the sea, which is not the same as producing power. A structure first seen in the last 60 days is not yet confirmed, because on a single image a freshly set foundation and a ship holding position look alike. Substation platforms are left out so the counts compare with the number of turbines. Rows marked with a dot (·) come from Hafrok’s own registers; a supplier or contract appears only where a source states it — everything else reads “not recorded”, never guessed.
Structures standing over time · count
strong line = confirmed · light line = seen in the last 60 days, not yet confirmed · the chart counts every structure (27 turbines + 1 platform); the table counts turbines only
foundationsturbines up (a substation top being set in place counts here too)
102028 planned (turbines and platforms)latest count 2024-12-30foundations — running total, confirmedJun 2022 — 9 this month · 9 in totalJul 2022 — 18 this month · 27 in totalDec 2022 — 0 this month · 27 in totalJan 2023 — 0 this month · 27 in totalFeb 2023 — 0 this month · 27 in totalMar 2023 — 0 this month · 27 in totalApr 2023 — 0 this month · 27 in totalMay 2023 — 1 this month · 28 in totalJun 2023 — 0 this month · 28 in totalOct 2023 — 0 this month · 28 in totalApr 2024 — 0 this month · 28 in totalJun 2024 — 0 this month · 28 in totalturbines up — running total, confirmedJun 2022 — 0 this month · 0 in totalJul 2022 — 1 this month · 1 in totalDec 2022 — 2 this month · 3 in totalJan 2023 — 3 this month · 6 in totalFeb 2023 — 4 this month · 10 in totalMar 2023 — 3 this month · 13 in totalApr 2023 — 5 this month · 18 in totalMay 2023 — 3 this month · 21 in totalJun 2023 — 1 this month · 22 in totalOct 2023 — 1 this month · 23 in totalApr 2024 — 2 this month · 25 in totalJun 2024 — 1 this month · 26 in total28 foundations26 turbines upJun 2022Dec 2022Feb 2023Apr 2023Jun 2023Apr 2024
Satellite image
Image taken2026-09-07Copernicus Sentinel-1 radar satellite, northbound pass
Farm covered100%the whole farm lies inside the image
Structures ringed28 confirmed · 0 not yet confirmedas counted on 2024-12-30 · the image is newer than the count, so a bright spot without a ring may be a structure not yet counted
Construction ports
PortPort of Rønne (Bornholm) turbine pre assembly
Contains modified Copernicus Sentinel data 2026, processed by ESA and by Microsoft Planetary Computer.
Latest satellite radar image · 2026-09-07
a radar picture, not a photograph: the sea is dark, steel is bright · black is beyond the edge of the image
confirmed structure (28)seen recently, not yet confirmed (0)probably a substation platform (a larger structure than a turbine; the register above has the facts)farm boundary
Satellite radar image over Arcadis Ost 1, 2026-09-07
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
Offshore substationArcadis Ost 1 offshore substation·220 (export) kV · in service 2022 · owner Parkwind (wind farm developer) with 50Hertz Transmission — reported as jointly operated by Parkwind and the TSO
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
202220232024developer’s stated start 2023-Q4nowArcadis Ost 1 offshore substationArcadis Ost 1 offshore substationin service 2022in service 2022

Sources & verification

16/18 fields verified · rests on 13 sources (9 primary) · ◆ 7 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[13]
Bundesnetzagentur — Marktstammdatenregister2026-08-23◆ Marktstammdatenregister (MaStR) offshore…
“Park row "Arcadis Ost I": 27 units, 257.175 MW gross, statuses {'In Betrieb': 27}, operators ['Parkwind Ost'], commissioned 2023-01-20..2023-11-26, planned None..None.”
supportsRegister entry
Operator8
[1]
Staatliches Amt für Landwirtschaft und Umwelt Vorpommern (StALU VP)2021-03-31◆ Genehmigung nach § 16 BImSchG Offshore-W…
“Der Firma Parkwind Ost GmbH...wird auf ihren Antrag vom 26.04.2019 in der Fassung vom 01.02.2021 die immissionsschutzrechtliche Genehmigung gemäß § 16 Absatz 1 BImSchG zur wesentlichen Änderung des ge…”
supportsoperatorConsentModelUnit capacityFoundation+2 more
[2]
Parkwind2021-06-15◆ JERA Nex bp - Parkwind | Arcadis Ost 1 r…
"Arcadis Ost 1 reaches financial close on global wind day [...] 257MW [...] 27 Vestas V174 - 9,5MW wind turbine generators [...] successful in the 2018 auction [...] awarded a market premium [...] abo…
supportsFinal investment decisionOffshore constructionTurbinesModelUnit capacity+1 more
[3]
Parkwind2022-11-24
“The first out of the 27 Vestas V174 – 9.5MW turbines has successfully been installed [...] on November 24th 2022 [...] The installation campaign has started in June 2022 [...] using a unique floating …”
supportsOffshore constructionTurbinesModelUnit capacity
[4]
Parkwind2023-01-17
“The first Arcadis Ost 1 turbines have been successfully energized, and are now producing energy. It is the first wind farm equipped with Vestas V174-9.5MW turbines and Parkwind's first international p…”
supportsFirst powerModelUnit capacity
[6]
Parkwind / JERA Nex bp Parkwind2024-12
“257 MW [...] 27 turbines [...] inaugurated on December 5th 2023 [...] 19 km off Rügen Island in the federal state of Mecklenburg-Western Pomerania [...] Parkwind used a floating turbine installation m…”
supportsCommercial operationTurbinesTotal capacityDistance from shoreCoordinates
[7]
Vattenfall2021-07-29◆ Vattenfall takes on direct marketing for…
“Vattenfall will be marketing the Arcadis Ost 1 offshore windfarm [...] operators of newly installed renewable generation in Germany are obliged to sell the electricity they produce directly on the mar…”
supportsMechanismDetail
[8]
50Hertz2024◆ 50hertz.com > Grid > Grid developement >…
“Ostwind 2 is the project to connect the Baltic Sea wind farms Arcadis Ost 1 and Baltic Eagle to the German extra-high voltage transmission grid [...] The connection to the German extra-high voltage tr…”
supportsStatusConnection point
[14]
Parkwind2023-07-26◆ JERA Nex bp Parkwind | Acquisition of Pa…
“JERA Co., Inc. successfully closed its acquisition of 100% of the shares of Parkwind NV from Virya Energy [...] Starting as of today, Parkwind will operate as part of JERA Co., Inc.”
supports↳ parent
Trade press4
[5]
offshoreWIND.biz2023-12-05◆ Parkwind's Arcadis Ost 1 Offshore Wind F…
Press report — cited, not quoted; read it at the source link.
supportsFirst powerCommercial operationCOD historyTurbinesModel
[9]
offshoreWIND.biz2020-01-08
Press report — cited, not quoted; read it at the source link.
supportsturbine pre assembly
[11]
GEBCO Compilation Group2020
supportsWater depth
[12]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed