Three Gorges Dafeng (H8-1+H9+H15+H17)

Located off Dafeng Port, Jiangsu. Three offshore substations. Annual generation ~2.6 TWh.

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

4 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 13 sources (1 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[5]
Jiangsu Provincial Development and Reform Commission (江苏省发展和改革委员会)2023-09-25
“苏发改能源发〔2023〕995号 ... 依据《行政许可法》《江苏省企业投资项目核准和备案管理办法》等有关规定,同意建设大丰80万千瓦海上风电项目。(成文日期:2023年9月25日)”
supportsConsentConsent granted
Trade press11
[2]
offshoreWIND.biz2025-12
Press report — cited, not quoted; read it at the source link.
supportsFirst powerCommercial operationTurbinesTotal capacityStatus+1 more
[3]
Global Energy Monitor2026-07-02
supportsoperatorCoordinates
[4]
GEBCO Compilation Group2020
supportsWater depth
[6]
Xinhuanet Jiangsu (新华网江苏频道)2025-03-02
Press report — cited, not quoted; read it at the source link.
supportsConstruction startSite rights
[7]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[8]
扬子晚报 (via 盐城发布)2025-09-16◆ 1713吨巨桩落海 (三峡江苏大丰800兆瓦 完成全部单桩施工)
Copyrighted source — cited, not quoted; read it at the source link.
supportsTurbinesFoundation
[9]
扬子晚报 (Yangtse Evening Post)2026-07-20◆ 三峡江苏大丰800兆瓦海上风电项目年度发电量突破10亿千瓦时
Copyrighted source — cited, not quoted; read it at the source link.
supportsCommercial operationTurbinesTotal capacity
[10]
扬子晚报 (via 央视新闻客户端)2025-12-20◆ 我国离岸最远海上风电项目全容量并网 (三峡江苏大丰800兆瓦)
Copyrighted source — cited, not quoted; read it at the source link.
supportsCommercial operationTotal capacity
[11]
Global Energy Monitor2026◆ Jiangsu Dafeng H15 (Three Gorges) Offsho…
supportsConstruction startSite rights
[13]
Global Energy Monitor2026◆ Jiangsu Dafeng H17 (Three Gorges) Offsho…
supportsConstruction startSite rights
[14]
Global Energy Monitor2026◆ Jiangsu Dafeng H9 (Three Gorges) Offshor…
supportsConstruction startSite rights
Unverified import1
[1]
unknown
Press report — cited, not quoted; read it at the source link.
supportsTurbinesTotal capacityWater depthCoordinates
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.