Shandong Energy Bozhong A
Part of Bozhong offshore wind base near Dongying, Shandong. Shanneng New Energy 80% / Yankuang Group 20%.
Status
Operationallifecycle stage
Ownership
SHShandong Energy Group — 100% ◇
Location
Bohai Sea
Technology
Capacity
501 MW ◇
Turbines
—
Foundation
Fixed-bottom (structure not recorded) ◇
Site & conditions
Site rights
Seabed rights held ∴
Water depth
12–16 m ≈
Wind speed
7.6 m/s @ 100 m ≈
Revenue & grid
Offtake
Other ◇
Grid
Not recorded ◇
Connection
220 kV offshore booster station to Dongying grid ◇
Schedule
FID
Taken · date not recorded ∴
COD
2022 ◇
Project timeline verified milestones only — each date carries its provenance mark
Dashed tick marks today (9 Sep 2026).
Revenue & offtake the regime the project was built under
Offtake regime: Grid parity — Shandong's first grid-parity offshore project
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation complete
not yet surveyed by satellite; the built farm can be, on request
Installation · on record
StageOperational
In operation since2022
Sources & verification
1/12 fields verified · rests on 9 sources · ◆ 2 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[5]
Trade press7
[2]
Global Energy Monitor2026-07-02◆ Shandong Bozhong A Offshore wind farm - …
“Shandong Bozhong A Offshore wind farm is an operating wind farm in Dongying, Shandong, China. ... Operating ... 2022”
supportsoperatorCommercial operationFoundationStatusConnection point+1 more
[3]
[4]
[6]
coaledu.net2022-02-23
“由山东能源集团开发的装机容量50万千瓦的渤中海上风电A场址工程项目顺利取得核准,这是山东省首个平价海上风电项目,也是全国海上风电进入平价时代后第一个取得核准的项目”
supportsConsentConsent granted
[7]
Solarbe (索比光伏网)2022-11-02
“项目自今年4月16日开工建设以来 ... 10月29日,由山东能源集团投资开发建设的渤中海上风电A场址项目首批机组顺利实现并网”
supportsFinal investment decisionOnshore constructionFirst powerSite rights
[8]
[9]
Global Energy Monitor◆ Global Wind Power Tracker Methodology
“Offshore hard mount: have wind turbines that are usually designed for installation in water no deeper than 60 meters [...] These turbines are mounted directly onto the sea floor. Offshore floating: ar…”
supportsFoundation
Unverified import1
[1]