Shandong Bandaonan U1 Phase 2
Phase 2 of SPIC's 900 MW Bandaonan U1 site, in the sea south of Rushan, Weihai, Shandong.
Status
Operationallifecycle stage
Ownership
Location
Yellow Sea
Technology
Capacity
450 MW ◆
Turbines
53 ◆
Foundation
—
Site & conditions
Site rights
Seabed rights held ∴
Water depth
25–31 m ◆
Distance from shore
24 km ◆
Revenue & grid
Offtake
—
Grid
—
Schedule
COD
26 Oct 2024 ◆
Project timeline verified milestones only — each date carries its provenance mark
Dashed tick marks today (9 Sep 2026).
Revenue & offtake the regime the project was built under
Offtake regime of the vintage — not a recorded contract
Post-subsidy era — provincial pricing (NDRC notice 2021)
Built after the national subsidy ended. From 2021, newly approved offshore wind projects are priced by the provincial price authority — through competitive allocation where conditions allow — with no central subsidy; the grid company settles the part within the local coal benchmark price. A project approved before 2021 that connected after the 2021 deadline takes the guide price of its connection year. Provincial top-ups (Guangdong, Shandong, Zhejiang and others) exist and are recorded on projects only where a source states them. · ◇
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation complete
not yet surveyed by satellite; the built farm can be, on request
Installation · on record
StageOperational
In operation since2024-10-26
Sources & verification
9/9 fields verified · rests on 2 sources · ◆ 2 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[1]
威海市人民政府 (Weihai Municipal Government)2024-10-29◆ 山东半岛南U1场址二期450兆瓦项目并网,U场址实现全容量并网
“10月26日上午11时许,伴随集电线断路器和风机高压开关柜断路器陆续合闸,位于乳山市南侧海域的 国家电投山东半岛南海上风电基地U1场址二期450兆瓦项目成功并网。这标志着我国单体最大的平价 海上风电项目——山东半岛南U场址海上风电项目正式实现全容量并网。…山东半岛南U场址海上风电 项目总装机容量为150万千瓦,分为国家电投山东能源投资建设的U1场址90万千瓦,国家能源集团 投资建设的U2场址60万…”
supportsoperatorCommercial operationSite rightsTotal capacity
[2]
山东省能源局 (Shandong Provincial Energy Bureau)2023-03-02◆ 国家电投半岛南U场址海上风电项目 (900MW, 两期)
“国家电投半岛南U场址海上风电项目,位于威海乳山南侧海域,场址中心距离海岸24公里,平均水深 25—31米…总装机容量900兆瓦,分两期建设…二期拟建设53台单机容量8.5兆瓦风电机组。 [EN] SPIC's Bandaonan U site offshore wind project lies in the sea south of Rushan, Weihai; site centre 24 …”
supportsConsentTurbinesWater depthDistance from shore