Jiangsu Rudong H7 (State Power Investment Corporation)

Jiangsu Rudong H7 (State Power Investment Corporation). GEM records phase 1 400 MW (2021) operating.

Status
Operationallifecycle stage
Ownership
RHRudong Haixiang Offshore Windpower 
Location
China
Yellow Sea
Technology
Capacity 400 MW 
Turbines
Foundation Fixed-bottom (structure not recorded) 
Site & conditions
Site rights Seabed rights held 
Revenue & grid
Offtake
Grid
Schedule
FID Taken · date not recorded  COD 2021 

Project timeline verified milestones only — each date carries its provenance mark

Dashed tick marks today (9 Sep 2026).

Revenue & offtake the regime the project was built under

Offtake regime of the vintage — not a recorded contract
National offshore wind tariff, grandfathered vintage (NDRC notices 2014 and 2019)

Built in the national-tariff era. A project approved by end-2018 that connected all its turbines by end-2021 keeps the tariff in force at approval — 0.85 CNY/kWh nearshore / 0.75 CNY/kWh intertidal (incl. VAT); a project approved in 2019 or 2020 took a competitively set price capped at the guide price of 0.80 (2019) / 0.75 (2020) CNY/kWh. Either way the part above the local coal benchmark price was paid from the national renewable energy fund. The record does not yet say which case applied to this project. ·

A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation complete
not yet surveyed by satellite; the built farm can be, on request
Installation · on record
StageOperational
In operation since2021

Sources & verification

0/7 fields verified · rests on 2 sources · ◆ 2 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Trade press2
[1]
Global Energy Monitor2026◆ Jiangsu Rudong H7 (State Power Investmen…
supportsoperatorConsentFinal investment decisionCommercial operationSite rights+3 more
[2]
Global Energy Monitor◆ Global Wind Power Tracker Methodology
“Offshore hard mount: have wind turbines that are usually designed for installation in water no deeper than 60 meters [...] Offshore floating: are an emerging technology designed for installation in de…”
supportsFoundation