Guangdong Zhuhai Guishan Offshore Wind Demonstration Project
Guangdong Zhuhai Guishan Offshore Wind Demonstration Project. GEM records phase 1 120 MW (2019) operating.
Status
Operationallifecycle stage
Ownership
NONanfang Offshore Windpower United Development ◇
Location
South China Sea
Technology
Capacity
120 MW ◇
Turbines
—
Foundation
Fixed-bottom (structure not recorded) ◇
Site & conditions
Site rights
Seabed rights held ∴
Revenue & grid
Offtake
—
Grid
—
Schedule
FID
Taken · date not recorded ∴
COD
2019 ◇
Project timeline verified milestones only — each date carries its provenance mark
Dashed tick marks today (9 Sep 2026).
Revenue & offtake the regime the project was built under
Offtake regime of the vintage — not a recorded contract
National offshore wind tariff, grandfathered vintage (NDRC notices 2014 and 2019)
Built in the national-tariff era. A project approved by end-2018 that connected all its turbines by end-2021 keeps the tariff in force at approval — 0.85 CNY/kWh nearshore / 0.75 CNY/kWh intertidal (incl. VAT); a project approved in 2019 or 2020 took a competitively set price capped at the guide price of 0.80 (2019) / 0.75 (2020) CNY/kWh. Either way the part above the local coal benchmark price was paid from the national renewable energy fund. The record does not yet say which case applied to this project. · ◇
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.
Installation how the build is going · from satellite counts and Hafrok’s registers
Installation complete
not yet surveyed by satellite; the built farm can be, on request
Installation · on record
StageOperational
In operation since2019
Sources & verification
0/7 fields verified · rests on 2 sources · ◆ 2 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Trade press2
[1]
Global Energy Monitor2026◆ Guangdong Zhuhai Guishan Offshore Wind D…
supportsoperatorConsentFinal investment decisionCommercial operationSite rights+3 more
[2]
Global Energy Monitor◆ Global Wind Power Tracker Methodology
“Offshore hard mount: have wind turbines that are usually designed for installation in water no deeper than 60 meters [...] Offshore floating: are an emerging technology designed for installation in de…”
supportsFoundation