Yangjiang Fanshi I
Yangjiang Fanshi I (阳江帆石一), the first of two 1,000 MW CGN farms south of Nanpeng Island off Yangjiang, Guangdong.
Status
Operationallifecycle stage
Ownership
Location
South China Sea
Technology
Capacity
1,000 MW ◇
Turbines
73 ◇
Foundation
Jacket ◇
Site & conditions
Site rights
Seabed rights held ∴
Water depth
40–48 m ◇
Distance from shore
60 km ◇
Revenue & grid
Offtake
—
Grid
—
Schedule
COD
24 Sep 2026 ◇
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
2 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 4 sources · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Trade press4
[1]
阳江日报 (Yangjiang Daily)2025-02-17◆ 阳江帆石一海上风电项目全面施工
Press report — cited, not quoted; read it at the source link.
supportsoperatorOffshore constructionSite rightsTurbinesTotal capacity+3 more
[2]
[3]
风电头条 (NetEase Hao; via 中国风电新闻网 / 阳江Plus)2025-02-18◆ 中广核阳江帆石一海上风电项目全面施工
Copyrighted source — cited, not quoted; read it at the source link.
supportsOffshore constructionSite rights
[4]
科技日报 (Science and Technology Daily)2026-09-24◆ 中广核广东阳江帆石200万千瓦海上风电项目实现全容量投运
Copyrighted source — cited, not quoted; read it at the source link.
supportsConsentCommercial operation