Guangdong SPIC Zhanjiang Xuwen Phase 2
Located adjacent to Xuwen Phase 1. SPIC expanding the southernmost offshore wind cluster in China.
Status
Operationallifecycle stage
Ownership
SIState Power Investment Corporation — 100% ◇
Location
South China Sea
Technology
Capacity
300 MW ◆
Turbines
25 × 12 MW ◆
Foundation
—
Site & conditions
Site rights
Seabed rights held ∴
Water depth
1–10 m ≈
Wind speed
7.5 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
—
Schedule
COD
17 Dec 2024 ◆
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
3 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 7 sources (1 primary)
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[7]
Guangdong Provincial Department of Ecology and Environment (广东省生态环境厅)2022-10-13
“广东省生态环境厅关于国家电投广东湛江徐闻海上风电场300MW增容项目环境影响报告书的批复 粤环审〔2022〕245号 ... 在落实《报告书》提出的各项污染防治对策、生态保护措施和应急措施的前提下,工程建设对环境产生的不利影响可得到减缓,从海洋生态环境保护的角度考虑,工程建设可行。我厅同意批准《报告书》。”
supportsConsentConsent granted
Trade press5
[2]
offshoreWIND.biz2024-12
Press report — cited, not quoted; read it at the source link.
supportsoperatorOffshore constructionCommercial operationSite rightsTotal capacity
[3]
[4]
[5]
China Forging Machinery Co., Ltd.2024-10-16
“The impeller docking of the Xuwen Capacity Enhancement Offshore Wind Farm Project was completed and passed the acceptance of the four parties, marking successful completion of construction. First pile…”
supportsOffshore constructionCommercial operationSite rightsTurbinesUnit capacity
[8]
Unverified import1
[1]