SPIC Jieyang Shenquan Phase II
Located in Shenquan, Huilai, Jieyang, Guangdong.
Status
Operationallifecycle stage
Ownership
SIState Power Investment Corporation — 100% ◇
Location
South China Sea
Technology
Capacity
502 MW ◇
Turbines
50 ◇
Foundation
Fixed-bottom (structure not recorded) ◇
Site & conditions
Site rights
Seabed rights held ∴
Water depth
31–38 m ≈
Wind speed
8.8 m/s @ 100 m ≈
Revenue & grid
Offtake
—
Grid
Not recorded ◇
Connection
Jieyang 220 kV Shenquan substation ◇
Schedule
FID
Taken · date not recorded ∴
COD
2022 ◇
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
4 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 9 sources · ◆ 2 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Trade press8
[2]
offshoreWIND.biz2022-12
Press report — cited, not quoted; read it at the source link.
supportsTurbinesTotal capacity
[3]
Global Energy Monitor2026-07-02◆ Guangdong Jieyang Shenquan 2 Offshore wi…
“Guangdong Jieyang Shenquan 2 Offshore wind farm is an operating wind farm in Shenquan, Huilai, Jieyang, Guangdong, China. ... Operating ... 2022”
supportsoperatorFinal investment decisionCommercial operationFoundationStatus+2 more
[4]
[5]
每日风电 (chinawindnews.com)2018-11-27
“11月22日,国家电投广东公司揭阳神泉二35万千瓦海上风电项目获得揭阳市发改局核准”
supportsConsentConsent granted
[6]
[7]
The Paper (澎湃新闻)2022-12-02
Press report — cited, not quoted; read it at the source link.
supportsFirst power
[8]
[9]
Global Energy Monitor◆ Global Wind Power Tracker Methodology
“Offshore hard mount: have wind turbines that are usually designed for installation in water no deeper than 60 meters [...] These turbines are mounted directly onto the sea floor. Offshore floating: ar…”
supportsFoundation
Unverified import1
[1]
unknown
Press report — cited, not quoted; read it at the source link.
supportsTurbinesTotal capacityWater depthCoordinates