Guangdong Jieyang Qianzhan 1

Located in Qianzhan, Huilai, Jieyang, Guangdong. Adjacent to SPIC Jieyang Shenquan complex.

Status
Early Developmentlifecycle stage
ProspectiveHafrok completion outlook
Ownership
Location
China
South China Sea
Technology
Capacity 1,200 MW 
Turbines
Foundation
Site & conditions
Site rights Application filed  Water depth 7–26 m  Wind speed 8.2 m/s @ 150 m 
Revenue & grid
Offtake
Grid
Schedule
FID Not taken
COD · announced 2028 
COD · Hafrok 2033 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2033
expected year of commercial operation
The developer says 2028; Hafrok expects 2033 — 5 years later.
Chance of delivery
≈60% estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2032: 14.1% (conditional on completion) 2033: 28.0% (conditional on completion) 2034: 22.7% (conditional on completion) 2035: 14.6% (conditional on completion) 2036: 8.7% (conditional on completion) 2037: 5.1% (conditional on completion) 2038: 3.1% (conditional on completion) 2039: 1.8% (conditional on completion) 2040: 1.1% (conditional on completion) 2041: 0.7% (conditional on completion)2026now202820302032203328%EXPECTED2034203620382040 Developer-announced COD: 2028 ANNOUNCED 2028
COD probability by year, conditional on completion
YearProbability
203214.1%
2033 (expected)28.0%
203422.7%
203514.6%
20368.7%
20375.1%
20383.1%
20391.8%
20401.1%
20410.7%
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (2026), adds the time similar projects (in established offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.
2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before 2033 is not credible.
3
Result
Expected commercial operation 2033, likely range 2033–2039 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈60%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

2027’28’29’30’31’32’33Developer-announced COD: 2028 announced COD 2028Commercial operation 2033 ·Hafrok expected
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD.

Revenue & offtake route to market — open

No offtake secured — route to market open
The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
Guangxi Beihai Deep-Sea Offshore Wind Competitive Allocation (广西深远海竞配)
expected — · scheduled · the round’s published documents do not name this project
~6,500 MW deep-sea allocation launched ~2024-07 (Beihai south sea-area: N sites 5,700 MW + P site 800 MW, ~94-120 km offshore). No settled result yet.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2028

Sources & verification

0/9 fields verified · rests on 7 sources · ◆ 1 document held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Auction pipeline1
[7]
gdshe.org (relaying 北极星风力发电网)2024-07◆ cn-gx2024-launch
广西北海海上风电竞争性配置…N场址…规划容量570万千瓦,P场址规划容量80万千瓦 (~6,500 MW deep-sea), ~94-120 km offshore, 15-45 m depth.
supportsGuangxi Beihai Deep-Sea Offshore Wind Competitive Allocation (广西深远海竞配)
Trade press5
[2]
The Wind Power2026-02-03
Press report — cited, not quoted; read it at the source link.
supportsTotal capacity
[3]
Power Technology (GlobalData)
Press report — cited, not quoted; read it at the source link.
supportsoperatorConsentSite rightsTotal capacity
[4]
GEM2026
supportsTotal capacityCoordinates
[5]
GEBCO Compilation Group2020
supportsWater depth
[6]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
supportsCommercial operationTotal capacityWater depthCoordinates